RESOLVED That Cabinet approves the allocation of the following funds to meet the cost of the regeneration of the Broomhill Road shops: (a) £24,000 from the High Street Innovation Fund; (b) £11,000 from the Revenue Grant Reserve Vacant Shops; (c) The Capital Programme for the scheme be amended to a maximum of £60,000 Reasons To regenerate the shops as a way of achieving overall area improvement; also to encourage new retailers to the area, which will bring additional rent and rates revenue for the Council and diversify the local retail offer to residents.
Word for word from the decision Ashfield published for this meeting.Source: democracy.ashfield.gov.uk
HEADING: Funding for the Regeneration of Broomhill Road Shops PORTFOLIO DEPUTY LEADER HOLDER: KEY DECISION: NO SUBJECT TO CALL-IN: YES
1. PURPOSE OF REPORT To gain approval to use funding from the Portas High Street Innovation Fund and the ADC Revenue Grant Reserve Vacant Shops, to contribute to the regeneration of the 4 Council owned shops in Broomhill Road Hucknall. Other contributory funding has been confirmed and is outlined below.
2. RECOMMENDATIONS It is recommended that: a. £24,000 is approved from the High Street Innovation Fund; b. £11,000 is approved from the Revenue Grant Reserve Vacant Shops; c. The Capital Programme for this scheme be amended to a maximum of £60,000
3. REASONS FOR RECOMMENDATION(S) The High Street Innovation Fund was approved via 2 Cabinet Reports on 14 June 2012, with an amendment on 23 February 2015. The scheme as currently approved specifies that the application should come from an existing occupant or new business and not from a landlord. This Cabinet Report therefore amends the scheme further to permit ADC as landlord, to draw down on the Fund.
Once the requested £24,000 is drawn down, the Fund will be exhausted and no further applications will be accepted.
An allocation of £11,000 can also be made from the Council’s Revenue Grant Reserve Vacant Shops fund.
Other sums already approved and included within the Capital Programme are a £20,000 contribution from NCC and £5,000 from the ADC Asset Management budget. The contributions from HSIF and the Revenue Grant Reserve Vacant Shops will therefore ensure that the scheme can go ahead with an agreed maximum budget of £60,000. There is no additional call on the General Fund.
This project was approved at the 25 November Regeneration Board.
4. ALTERNATIVE OPTIONS CONSIDERED (with reasons why not adopted) Do not regenerate the Broomhill Road shops: not recommended, as the area will continue to suffer from environmental blight and anti social behaviour. The Council owned asset will also continue to deteriorate and not earn rental income or business rates.
Regenerate the shops: recommended as a way of overall area improvement; also to encourage new retailers to the area which will bring additional rent and rates revenue for ADC and diversify the local retail offer to residents. 5. BACKGROUND There are 5 shops on the parade on Broomhill Road, of which 4 are Council owned and one privately owned. 3 are occupied (including the privately owned shop) and 2 are empty. They are all in a poor state of repair and also require security measures because of vandalism and anti social behaviour. ADC officers have been working with the local community to identify design and maintenance measures to regenerate the shops, bring the vacant ones back into use and generally improve the overall area. As of November, a planning application had been submitted and the scope of works put out to tender. Works can commence once Cabinet approves this funding in January and can be completed within a 3 month period.
A Project Initiation Document (PID) and Highlight Report have been written which set out the timelines and decision making processes. The Regeneration Board approved this project at its meeting on 24 November.
In terms of Governance, a steering group has been convened under the direction and management of the Service Director Economy, to drive the project. Reporting will continue to be through the Regeneration Board.
ADC Asset Management will control the work package(s) and the Regeneration Team will act as Client. Localities will continue to work with the community group on engagement activities.
Risks have been highlighted in the above documents and a risk log has been written:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Plan Year End Delivery 2025/26RESOLVED that a) the levels of delivery achieved against the Corporate Plan Priorities, as outlined in the report, be...
Corporate Risk Year End 2025/26 PositionRESOLVED that the current significant items on the Corporate Risk Register, as presented, be received and noted. Reas...
Appropriation of Land at Kingsway ParkRESOLVED that a) it be noted that the Secretary of State for Housing, Communities & Local Government granted consent ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.