RESOLVED That Cabinet agrees that: (a) The Council should bring the housing service provided by Ashfield Homes back in-house in order to: ( i ) Achieve significant efficiencies for re-investment in the Council’s housing service for tenants and in supporting other key services provided by the Council; (ii) More effectively deliver the Council’s housing priorities; and (iii) Remove organisational barriers (b) The Council should carry out a test of opinion of tenants and consult leaseholders and other residents to find out their views on this proposal and then take a final recommendation to Council at its meeting on 10 March 2016. Reasons To propose a new way forward in relation to the management of Council housing within Ashfield.
Word for word from the decision Ashfield published for this meeting.Source: democracy.ashfield.gov.uk
1 PURPOSE OF REPORT The purpose of this report is to propose a new way forward in relation to the management of council housing within Ashfield.
2 RECOMMENDATION(S) 2.1 That the Council should bring the housing service provided by Ashfield Homes back in house in order to a) Achieve significant efficiencies for reinvestment in the Council’s housing services for tenants and in supporting other key services provided by the Council b) More effectively deliver the Council’s housing priorities and c) Remove organisational barriers
2.2That the Council should carry out a test of opinion of tenants and consult leaseholders and other residents to find out their views on this proposal and then take a final recommendation to a full Council meeting on March 10th 2016. The Council has set out a statement of intent explaining what standards tenants, leaseholders and residents can expect from an in-house service. The contents of this statement are included in this report at 5.3 below. 3 REASONS FOR RECOMMENDATION(S) These recommendations are based on the analysis of three documents:- a) The Phase 1 Position Statement (a summary of the existing service produced by AHL and ADC officers) b) A Value for Money report produced by Ark Housing Consultancy c) A report from Chris Broughton Associates “The Soft Market Testing of Ashfield’s housing and housing management services”
The analysis of the documents and other evidence is at paragraph 7 of this report this is the Phase 2 Analysis of options for the future management of council housing in Ashfield.
The analysis is the work of the Interim Service Director Housing who was appointed to lead the housing options process. 4 ALTERNATIVE OPTIONS CONSIDERED (with reasons why not adopted) The Phase 2 report attached analyses two options 1) keeping Ashfield Homes Limited as the Council’s ALMO and 2) bringing it in-house. Both options have been tested against the criteria agreed by the Council and given weightings by the Steering Group that has overseen the project. This was the given scope of the review from a Cabinet report in July 2015 and no other options e.g. stock transfer were considered. 5 BACKGROUND 5.1 Context The Council set up Ashfield Homes Limited (AHL) in April 2002 as an Arms Length Housing Management Organisation (ALMO) in order to access government funding and deliver the Decent Homes Programme to improve the physical quality of council housing in the district. The Decent Homes programme was completed successfully in 2005.
The 6,800 council homes in the district are owned by Ashfield District Council (ADC) and AHL manages and maintains the housing on behalf of the Council. AHL is wholly owned by ADC with the Council being the company’s only shareholder. The initial agreement for setting up the company runs until 2027 but the Council has a series of break clauses where it can decide to serve notice on any change of ownership. The next break clause is April 2017 but the Council needs to give the company 12 months’ notice of using the break clause hence this review is due to be completed in time for that break clause to be enacted if necessary.
Further background to the set-up of Ashfield Homes can be read in the Phase 1 document, which also describes the results of a previous review of the future of AHL which was undertaken in 2011.
5.2The Process The Council appointed an Interim Service Director Housing to lead the process from September 2015 at the same time a project was set up with the architecture laid out below.
The purpose of the structure was to make sure that all relevant stakeholders in the process were represented in the process. It did not prove possible to find a leaseholder representative to be part of the Members’ Steering Group.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Plan Year End Delivery 2025/26RESOLVED that a) the levels of delivery achieved against the Corporate Plan Priorities, as outlined in the report, be...
Corporate Risk Year End 2025/26 PositionRESOLVED that the current significant items on the Corporate Risk Register, as presented, be received and noted. Reas...
Appropriation of Land at Kingsway ParkRESOLVED that a) it be noted that the Secretary of State for Housing, Communities & Local Government granted consent ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.