( i ). That Cabinet notes the outturn position of the 2015/16 Capital Programme; (ii). That Cabinet notes the slippage on the 2015/16 Capital Programme. a) That Cabinet notes the outturn position of the 2015/16 Capital Programme; b) That Cabinet notes the slippage on the 2015/16 Capital Programme. Reasons To report to those charged with Governance the financial position for the end of 2015/16 and comply with the Council’s Financial Regulations.
Word for word from the decision Ashfield published for this meeting.Source: democracy.ashfield.gov.uk
REPORT TO: CABINET DATE: 14th JULY 2016 CAPITAL OUTTURN 2015-16 HEADING: PORTFOLIO CORPORATE SERVICES HOLDER: KEY DECISION: NO SUBJECT TO CALL-IN: NO
1. PURPOSE OF REPORT The Capital Outturn details Capital Expenditure incurred in 2015/16, how this expenditure has been funded and provides explanations for major budget variances. The overall Capital Expenditure was £15.988m and under spent to budget by £1.937m. The main reason for the under spend related to General Fund projects which had not commenced or progressed as planned during the period plus a delay on the completion of the Darlison Court Housing Revenue Account (HRA) Development. This underspend is referred to as ‘slippage’. As a result of the above slippage and the use of £1.719m of Capital Receipts received in the year which were not included in the funding budget, (capital receipts had been set aside whilst clarification on the retention of receipts to fund new build projects was resolved) the Council has utilised less borrowing (£0.366m) and less of its grant funding and other funding (£1.571m).
2. RECOMMENDATION(S) Members are requested:
(i) Note the outturn position of the 2015/16 Capital Programme. (ii) Note the slippage on the 2015/16 Capital Programme.
3. REASONS FOR RECOMMENDATION(S) To report to those charged with Governance the financial position for the end of 2015/16 and comply with the Council’s Financial Regulations.
4. ALTERNATIVE OPTIONS CONSIDERED (with reasons why not adopted) None.
5. BACKGROUND 1. Introduction
Cabinet approved the Capital Programme for 2015/16 to 2019/20 on 29th February 2016. This is a report back to Cabinet on the financial out-turn of the capital expenditure against that Capital Programme. 2. Outturn 2015/16
The outturn position for 2015/16 can be summarised as follows: Capital Actual Variance Scheme programme Expenditure £000's £000's £000's Housing Revenue Account Management Fee 638 638 0 Catch up and Major Repairs 4,139 4,114 (25) Service Improvements 280 258 (22) Contingent Major Repairs 13 8 (5) Exceptional Extensive Works 192 192 0 Disabled adaptations - Treated as Revenue Expenditure From Capital Under Statute (REFCUS) 451 411 (40) Empty Homes 108 138 30 Darlison Court (New Builds) 4,806 4,550 (256) Brook Street Development 124 121 (3) Other Housing Revenue Account Schemes (less than £100k each) 87 59 (28) Total Housing Revenue Account 10,838 10,489 (349)
General Fund Hucknall Town Centre: Inner Relief Road 800 800 0 Beacon Drive / Conniston Road 117 126 9 Ellis Street Redevelopment 250 200 (50) Nottingham Road Recreation Ground 156 88 (68) Kirkby Regeneration and Civic Centre 400 273 (127) Green Deal Communities Project 830 772 (58) Car Park Extension and Car Parking Machines Lammas 102 98 (4) Improvement Grants 1996 Act Disabled Facility Grant 533 377 (156) Flood Support Schemes 270 221 (49) Office Accommodation Works 194 195 1 Sutton Town Regeneration 160 150 (10) Garden Waste Bins 1,031 569 (462) Northern Depot Office Rationalisation and Wireless CCTV Infrastructure 506 489 (17) Purchase of Vehicles 740 497 (243) Other General Fund Schemes (less than £100k each) 998 644 (354) Total General Fund 7,087 5,499 (1,588)
Total Expenditure 17,925 15,988 (1,937)
Funding Major Repairs Reserve 5,713 4,537 (1,176) Borrowing 1,654 1,288 (366) Government Grants and Other Contributions 6,169 4,644 (1,525) Revenue Contributions 4,389 3,779 (610) Deferred Capital Receipts 0 21 21 Capital Receipts 0 1,719 1,719 Total Funding 17,925 15,988 (1,937)
The outturn shows an under spend of £1.937m compared to the approved programme. A summary of the main variances are as follows:-
Housing Revenue Account (HRA)
The Darlison Court (new Builds) Scheme was under spent by £256k. These works will be rolled forward into the 2016/17 capital programme.
General Fund
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Plan Year End Delivery 2025/26RESOLVED that a) the levels of delivery achieved against the Corporate Plan Priorities, as outlined in the report, be...
Corporate Risk Year End 2025/26 PositionRESOLVED that the current significant items on the Corporate Risk Register, as presented, be received and noted. Reas...
Appropriation of Land at Kingsway ParkRESOLVED that a) it be noted that the Secretary of State for Housing, Communities & Local Government granted consent ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.