COUNCIL'S INSURANCE REQUIREMENTS
As part of the Council’s overall arrangement for managing the risks of such a diverse organisation the Council provides for unavoidable risks by two methods:
Self insurance funds External insurance
This report provides Members with an up to date assessment of both these arrangements.
1. Self Insurance Funds (Insurance Reserves)
The transactions of the Insurance Funds for 2015/16 are summarised below: General Fund Insurance Reserve
Liability Property Fund Fund TOTAL £000 £000 £000 Balance at 1st April 2015 (249) (248) (497) Leaseholders contribution 0 (8) (8) Credits received from (1) (4) (5) insurance company Interest (1) (1) (2)
Claims Paid 203 42 245 Reduction in Liability (2) (1) (3) Provision Balance at 31st March 2016 (50) (220) (270)
Housing Revenue Account (HRA) Insurance Reserve
HRA Insurance Fund £000 Balance at 1st April 2015 0 HRA contribution (50)
Balance at 31st March 2016 (50)
1.1Liability Fund
It is prudent to keep an insurance reserve because there can often be a significant delay in the reporting of claims. This is particularly the case with those involving some form of industrial injury which may not surface until some years after the incident occurred, or cases involving children which are allowed to be reported many years after the incident.
The potential level of liability as estimated by the insurance company is calculated as the maximum liability likely to arise taking into account all known factors. This amount could increase or decrease depending on how the cases develop.
Provision has already been made for this liability in the 2015/16 accounts.
A more detailed analysis of the liability claims outstanding by year is given below: Year Number Value £’000 2015/16 4 105 2014/15 3 25 2013/14 3 38 2012/13 2 49 2011/12 1 28 MMI Provision 32 (See Paragraph 3.2) TOTAL 13 277
1.2Property Fund
As at the 31st March 2016 there were seven claims still to be settled with an estimated value of £12k.
1.3Housing Revenue Fund (HRA)
A new reserve of £50k for the funding of HRA claims was set up in 2015/16. Any future claims payable or claim provisions relating to the HRA will be charged against this fund.
2. Renewal of External Insurance Policies
The new premiums under the existing contract for 2016/17 and comparison to 2015/16 are shown below. The figures shown exclude the 6% Insurance Premium Tax (IPT) payable in 2015/16 and 9.5% IPT payable in 2016/17.
Type of Cover & 2015/16 2016/17 Insurer £000 £000
Property – AIG and HSB via RMP 82 94 Liability/Fidelity Guarantee - 87 99 Travellers Contractors All Risk 9 11 Engineering Inspection – HSB via 12 12 RMP Computer – HSB via RMP 2 3 Motor Vehicle – QBE via RMP 62 65 TOTAL 254 284
The total premiums have increase by £30k excluding IPT and by £42k when IPT is included.
3. Previous Insurance Providers
3.1Independent Insurance Company
Between 1992 and 1999 the Council’s liability insurers were the Independent Insurance Company. In 2001 the company was declared insolvent. From that point onwards full financial liability for any claims above the excess fell to the Council. These will be limited to claims for industrial injury with a long development period (e.g. industrial deafness) or claims involving children. We currently have four claims outstanding with an estimated liability of £61k which has been provided for in the insurance provision.
3.2Municipal Mutual Insurance Liability
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Council's Insurance RequirementsReport | 180 KB | DownloadRead as text |
Follow Cabinet at Ashfield and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 27 Jul 2026 | Local Government Reorganisation (Verbal Update and Q/A Session)RESOLVED that a) the information provided and the ongoing work being undertaken to support the transition programme, ... | Noted | Open |
| 27 Jul 2026 | Corporate Plan Year End Delivery 2025/26RESOLVED that a) the levels of delivery achieved against the Corporate Plan Priorities, as outlined in the report, be... | Noted | Open |
| 27 Jul 2026 | Corporate Risk Year End 2025/26 PositionRESOLVED that the current significant items on the Corporate Risk Register, as presented, be received and noted. Reas... | Noted | Open |
| 27 Jul 2026 | Update - Charitable Trust Issues at Lord Francis Park (Kirkby-in-Ashfield), Hucknall Leisure Centre and Titchfield Park (Hucknall)RESOLVED that a) the current position relating to Charitable Trust Issues at Lord Francis Park (Kirkby-In-Ashfield), ... | Noted | Open |
| 27 Jul 2026 | Appropriation of Land at Kingsway ParkRESOLVED that a) it be noted that the Secretary of State for Housing, Communities & Local Government granted consent ... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.