The following be agreed and recommended to Council for approval:- a) the proposed increase in Capital borrowing of £3.8m for 2020/21 and 2021/22; b) the potential use of Capital borrowing of £6m (estimated figure) to part fund the new Kirkby Leisure Centre; c) the carry forward of unused borrowing of £254k from 2016/17 into 2017/18.
Word for word from the decision Ashfield published for this meeting.Source: democracy.ashfield.gov.uk
The previous Capital Strategy covered the years 2017/18 – 2019/20. The revised capital strategy seeks to extend the capital strategy to cover years 2017/18 – 2021/22.
Recommendation(s) 1) The increase in Capital borrowing of £3.8m for years 2020/21 and 2021/22 be approved and recommended to Council 2) To approve the potential use of Capital Borrowing of £6m to part fund the new Kirkby Leisure Centre and recommend this is approved by Council (This figure is an estimate and subject to change through future reports following detailed cost assessments). 3) To approve and recommend to Council the carry forward of unused borrowing of £254k from 2016/17 into 2017/18.
Reasons for Recommendation(s)
To ensure that proposed capital expenditure could continue to be funded from borrowing to the end of 2021/22.
Alternative Options Considered (With Reasons Why Not Adopted)
None. Detailed Information
1. Changes to the Capital Strategy
The last Capital Strategy was approved on 30th November 2017 by Cabinet. The Capital Strategy has been revised on the basis that:-
1) Less capital expenditure (to be financed by borrowing) than projected was incurred as at 31st March 2017. This gap has been rolled forward into the current strategy. 2) The current capital strategy period ends on the 31st March 2020. The revised capital strategy includes the years 2020/21 and 2021/22. This allows the Capital Strategy to cover the same period as the proposed Capital Programme which is on the same agenda as this report. 3) The Authority is currently looking at options to provide a new leisure centre facility in Kirkby-in-Ashfield. The potential options are still being evaluated. It is expected that the Council will need to borrow at least £6m to fund this project.
2. The Capital Strategy
The borrowing limits for the General Fund have increased by £10.054m over the life of the Strategy. This comprises of £6m to potentially fund the new Kirkby Leisure Centre, £0.254m unused borrowing carried forward from 2016/17 and £3.8m for financial years 2020/21 and 2021/22. The new Capital Strategy total borrowing can be analysed as follows:
£000’s Investment Properties 25,000 Kirkby Leisure Centre 6,000 Other Borrowing – Vehicles etc. 9,500 Carried Forward from 2016/17 254 Grand Total 40,754
It is likely that there may be some changes in the expenditure mix. Any overspends in one area must be compensated by at a least a similar under spend in another area to ensure that the total prudential borrowing figure of £40.754m is not exceeded. Although within the overall strategy, no new projects will be included in the Capital Programme without a sound business case and appropriate approval by members.
The February 2018 proposed capital programme estimates that the overall borrowing for the period 2017/18 – 2021/22 will be £24.469m. As discussed in the Capital Programme Cabinet Report the purchase of £9.9m additional Investment Properties has been put on hold. The borrowing requirement for these is remaining in the Capital Strategy for the time being. The capital programme does not currently include £6m for the Kirkby Leisure Centre. If the Kirkby Leisure centre is approved at a future date, the total estimated borrowing requirement for the five years will be £30.469m. This will leave an available headroom of £10.285m compared to the Capital Strategy. The Government has issued guidance in February 2018 on Investments and Minimum Revenue Provision (MRP) which are effective from the 1st April 2018. This change has made it less feasible for Authorities to invest in Investment Properties. As result of this guidance the Authority is currently reviewing its future Investment property options.
3. Impact on the Medium Term Financial Strategy
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Plan Year End Delivery 2025/26RESOLVED that a) the levels of delivery achieved against the Corporate Plan Priorities, as outlined in the report, be...
Corporate Risk Year End 2025/26 PositionRESOLVED that the current significant items on the Corporate Risk Register, as presented, be received and noted. Reas...
Appropriation of Land at Kingsway ParkRESOLVED that a) it be noted that the Secretary of State for Housing, Communities & Local Government granted consent ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.