Proposed Capital Strategy 2017/18 to 2021/22

Agreed Key decision Executive 1 paper

Cabinet agreed this item on Monday 19 February 2018. Below is the council's own wording, with the papers it was decided on.

ItemCA.55

Resolved

The following be agreed and recommended to Council for approval:- a) the proposed increase in Capital borrowing of £3.8m for 2020/21 and 2021/22; b) the potential use of Capital borrowing of £6m (estimated figure) to part fund the new Kirkby Leisure Centre; c) the carry forward of unused borrowing of £254k from 2016/17 into 2017/18.
Word for word from the decision Ashfield published for this meeting. Source: democracy.ashfield.gov.uk

Follow this further

Built from Ashfield's papers

What the report saysPro

Report to Cabinet

Purpose of report

The previous Capital Strategy covered the years 2017/18 – 2019/20. The revised capital strategy seeks to extend the capital strategy to cover years 2017/18 – 2021/22.

Recommendation(s) 1) The increase in Capital borrowing of £3.8m for years 2020/21 and 2021/22 be approved and recommended to Council 2) To approve the potential use of Capital Borrowing of £6m to part fund the new Kirkby Leisure Centre and recommend this is approved by Council (This figure is an estimate and subject to change through future reports following detailed cost assessments). 3) To approve and recommend to Council the carry forward of unused borrowing of £254k from 2016/17 into 2017/18.

Reasons for Recommendation(s)

To ensure that proposed capital expenditure could continue to be funded from borrowing to the end of 2021/22.

Alternative Options Considered (With Reasons Why Not Adopted)

None. Detailed Information

1. Changes to the Capital Strategy

The last Capital Strategy was approved on 30th November 2017 by Cabinet. The Capital Strategy has been revised on the basis that:-

1) Less capital expenditure (to be financed by borrowing) than projected was incurred as at 31st March 2017. This gap has been rolled forward into the current strategy. 2) The current capital strategy period ends on the 31st March 2020. The revised capital strategy includes the years 2020/21 and 2021/22. This allows the Capital Strategy to cover the same period as the proposed Capital Programme which is on the same agenda as this report. 3) The Authority is currently looking at options to provide a new leisure centre facility in Kirkby-in-Ashfield. The potential options are still being evaluated. It is expected that the Council will need to borrow at least £6m to fund this project.

2. The Capital Strategy

The borrowing limits for the General Fund have increased by £10.054m over the life of the Strategy. This comprises of £6m to potentially fund the new Kirkby Leisure Centre, £0.254m unused borrowing carried forward from 2016/17 and £3.8m for financial years 2020/21 and 2021/22. The new Capital Strategy total borrowing can be analysed as follows:

£000’s Investment Properties 25,000 Kirkby Leisure Centre 6,000 Other Borrowing – Vehicles etc. 9,500 Carried Forward from 2016/17 254 Grand Total 40,754

It is likely that there may be some changes in the expenditure mix. Any overspends in one area must be compensated by at a least a similar under spend in another area to ensure that the total prudential borrowing figure of £40.754m is not exceeded. Although within the overall strategy, no new projects will be included in the Capital Programme without a sound business case and appropriate approval by members.

The February 2018 proposed capital programme estimates that the overall borrowing for the period 2017/18 – 2021/22 will be £24.469m. As discussed in the Capital Programme Cabinet Report the purchase of £9.9m additional Investment Properties has been put on hold. The borrowing requirement for these is remaining in the Capital Strategy for the time being. The capital programme does not currently include £6m for the Kirkby Leisure Centre. If the Kirkby Leisure centre is approved at a future date, the total estimated borrowing requirement for the five years will be £30.469m. This will leave an available headroom of £10.285m compared to the Capital Strategy. The Government has issued guidance in February 2018 on Investments and Minimum Revenue Provision (MRP) which are effective from the 1st April 2018. This change has made it less feasible for Authorities to invest in Investment Properties. As result of this guidance the Authority is currently reviewing its future Investment property options.

3. Impact on the Medium Term Financial Strategy

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Proposed Capital Strategy 2017/18 to 2021/22Report 168 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 15 attended
AB
Councillor Amanda BrownCommittee Member, present
TB
Councillor Tim BrownCommittee Member, present
CB
Councillor Cheryl ButlerChair, present
DD
Councillor Don DavisCommittee Member, present
JJ
Councillor Jackie JamesCommittee Member, present
KM
Councillor Keir MorrisonCommittee Member, present
NN
Councillor Nicolle NdiweniCommittee Member, present
CB
Craig BonarOfficer, present
LC
Lynn CainOfficer, expected
SD
Sarah DanielOfficer, present
RD
Ruth DennisOfficer, present
MJ
Mike JoyOfficer, expected

All 15 on the meeting page

On this subject at Ashfield

Search all
  1. Proposed Capital Strategy 2017/18 to 2021/22This decision
  2. Proposed Amendments to the Capital Programme for 2022/23Approved
  3. Proposed Capital Programme Addition 2021/22Approved
  4. 2019/20 Quarter 2 Forecast Outturn for General Fund, Housing Revenue Account (HRA) and Capital Programme and Revised Proposed Capital Programme 2019/20 to 2023/24Noted
  5. Proposed Capital Strategy 2017/18 - 2021/22Approved
  6. Proposed Capital Programme 2017/18- 2021/22Approved

More from Ashfield Cabinet

All decisions
MeetingDecisionOutcome
27 Jul 2026 Local Government Reorganisation (Verbal Update and Q/A Session)RESOLVED that a) the information provided and the ongoing work being undertaken to support the transition programme, ... Noted Open
27 Jul 2026 Corporate Plan Year End Delivery 2025/26RESOLVED that a) the levels of delivery achieved against the Corporate Plan Priorities, as outlined in the report, be... Noted Open
27 Jul 2026 Corporate Risk Year End 2025/26 PositionRESOLVED that the current significant items on the Corporate Risk Register, as presented, be received and noted. Reas... Noted Open
27 Jul 2026 Update - Charitable Trust Issues at Lord Francis Park (Kirkby-in-Ashfield), Hucknall Leisure Centre and Titchfield Park (Hucknall)RESOLVED that a) the current position relating to Charitable Trust Issues at Lord Francis Park (Kirkby-In-Ashfield), ... Noted Open
27 Jul 2026 Appropriation of Land at Kingsway ParkRESOLVED that a) it be noted that the Secretary of State for Housing, Communities & Local Government granted consent ... Noted Open