a) Cabinet endorse the current significant items on the Risk Register and also agree that the following issues be included: - · Mitigation against Planning Appeals exceeding the 10% threshold which could result in Government intervention; · Recognition of potential risk in the event of Local Government Reorganisation; b) the Corporate Risk Strategy, as appended to the report, be approved. REASON FOR DECISIONS To prioritise and manage the mitigation of Risk in order that the Council can achieve its objectives. Updates to the Corporate Risk Strategy were considered appropriate in order to facilitate greater understanding of risk maturity and improved organisational performance against the Alarm national performance model for risk management in public services, as suggested by Internal Audit. This is also highlighted as an improvement action in the Annual Governance Statement.
Word for word from the decision Ashfield published for this meeting.Source: democracy.ashfield.gov.uk
For Cabinet to review the Corporate Risk Register and the analysis of movement in risk and mitigating actions in respect of those risks. For Cabinet to also consider and approve the updated Corporate Risk Strategy.
Recommendation(s)
Cabinet are asked to endorse the current significant items on the Register and to consider whether any further immediate actions are necessary to mitigate those risks. Cabinet are asked to approve the updated Corporate Risk Strategy.
Reasons for Recommendation(s)
To prioritise and manage the mitigation of Risk in order that the Council can achieve its objectives.
Updates to the Corporate Risk Strategy were considered appropriate in order to facilitate greater understanding of risk maturity and improved organisational performance against the Alarm national performance model for risk management in public services, as suggested by Internal Audit. This is also highlighted as an improvement action in the Annual Governance Statement.
Alternative options considered
None Detailed Information
Context/Background
All strategic risks at corporate and directorate level are incorporated into the Pentana performance system to enable quarterly updates at the same time as updating performance, therefore enhancing the consideration of risk in the delivery of services.
The Risk Template was revised to incorporate new columns to ensure we identify:- - business continuity links - ability to influence - actions required and milestones separate to actions completed
Risk Audit Update
An Internal Audit of risk was undertaken in 2016/17, outstanding recommendations in 2017/18 were:- Ensure employees attend risk management training –completed and incorporated into corporate training programme for CLT and ELT leadership levels Ensure risk management training built into Member training schedule –completed and incorporated into Member training programme Reports to Members should include a section on the implications associated with Risk – completed and now incorporated into the report template Council undertake an exercise to identify its current risk maturity level using the ALARM model. The results of this should then highlight any areas for improvement and inform a plan of action to achieve the desired level of risk maturity and risk appetite – the Corporate Risk Strategy has been reviewed and updated in order to facilitate improved performance against the ALARM model. Cabinet are requested to review and approve the revised strategy. A detailed action plan will be adopted in order to achieve the desired level of risk maturity against the model.
Corporate Risk Strategy
The Corporate Risk Strategy has been reviewed in order to ensure that it continues to meet the needs of the organisation and aligns with the Public Risk Management Association model known as ‘’The Alarm national performance model for risk management in public services’’ . This model is comprehensive and focuses on seven strands of risk management activity, by which the organisation can measure current performance against recognised achievement levels for each of the seven strands. The model provides the basis for clear performance indicators and acts as a catalyst for improved risk management performance within the organisation. It will also inform assurance in corporate governance terms and the further embedding of risk management across the organisation. See Appendix 1.
Corporate Plan Year End Delivery 2025/26RESOLVED that a) the levels of delivery achieved against the Corporate Plan Priorities, as outlined in the report, be...
Corporate Risk Year End 2025/26 PositionRESOLVED that the current significant items on the Corporate Risk Register, as presented, be received and noted. Reas...
Appropriation of Land at Kingsway ParkRESOLVED that a) it be noted that the Secretary of State for Housing, Communities & Local Government granted consent ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.