a) that plans for the refurbishment and re-siting of the town clock in the vicinity of the Nags Head pub in Kirkby-in-Ashfield be progressed. b) that the use of Section 106 funding to support the implementation of the project be approved. c) that the Interim Director of Place and Communities, in conjunction with the Estates Manager and Director of Legal and Governance be delegated authority to enter into negotiations with landowners to reach agreement for the siting of the clock and to consequently enter into a suitable legal agreement. REASON FOR DECISIONS To respond to requests made by the local community that the clock be re-sited outside the Nags Head pub in Kirkby. The clock had stood outside the pub since 1960, until its removal in 2014. ALTERNATIVE OPTIONS CONSIDERED AND REASONS FOR REJECTION The alternative option of not to re-site the clock was not recommended as this would not have responded to the requests made by the local community.
Word for word from the decision Ashfield published for this meeting.Source: democracy.ashfield.gov.uk
To consider a proposal to re-site the Kirkby town clock outside the Nags Head pub.
Recommendations
1. To progress the refurbishment and re-siting of the town clock in the vicinity of the Nags Head pub in Kirkby;
2. To allocate Section 106 funding to support the implementation of the project.
3. To authorise the Interim Director of Place and Communities, in conjunction with the Estates Manager and Director of Legal and Governance, to enter into negotiations with landowners to reach agreement for the siting of the clock and to consequently enter into a suitable legal agreement.
Reasons for recommendations
The administration has been approached by the local community and members of the public to request that the clock be re-sited outside the Nags Head pub in Kirkby. The clock had stood outside the pub since 1960, until its removal in 2014.
Alternative options considered
Not to re-site the clock - there is support from the local community to re-site the clock. Detailed Information
Background
The clock was removed in November 2014, as part of the works to create Kirkby Plaza and modernise the pedestrianised area of the town centre, as well as reducing ongoing maintenance costs. The clock was in need of comprehensive refurbishment. The clock is currently in storage and requires cleaning, painting, fitting of new movements and cover glasses, internal LED lighting and automatic BST/GMT changes.
Associated Costs
The overall cost is estimated to be £19,322 which can be funded from unallocated Section 106 Kirkby town centre regeneration contributions from developers. Outline costs for refurbishment and re-siting of the clock are as follows:
Refurbishment and installation of the clock: £10,702 Installation of concrete plinth and ducting and making good: £3,200 Connecting to electric supply: £2,900 Contingency @ 15%: £2,520
The running costs (electricity) are estimated to be approximately £200 per year and annual maintenance costs are expected to be £210 per year.
The exact location for the re-siting of the clock will need to be determined and permission secured if the land is in private ownership. A formal legal agreement will be needed with land owners and this may take some time to negotiate and secure.
Implications
Corporate Plan: Place and Communities priority.
Legal: Legal advice and assistance will be provided as part of the process of negotiating and entering into a suitable formal legal agreement with any private land owners for the siting of the clock.
Finance:
Budget Area Implication
Total annual costs of £410. 10 annual maintenance General Fund – Revenue Budget visit
General Fund – Capital £19,322 - Section 106 Kirkby town centre regeneration Programme Housing Revenue Account – N/A Revenue Budget Housing Revenue Account – N/A Capital Programme Risk:
Risk Mitigation
None identified to date - a risk Agreement to use third party land if required assessment will be prepared if the project is approved.
Human Resources: No issues identified.
Equalities: No issues identified.
Other Implications: Not applicable
Reason(s) for Urgency Not applicable
Reason(s) for Exemption Not applicable
Background Papers None
Report Author and Contact Officer Sarah Daniel Place Team Leader [email protected] 01623 457249
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Plan Year End Delivery 2025/26RESOLVED that a) the levels of delivery achieved against the Corporate Plan Priorities, as outlined in the report, be...
Corporate Risk Year End 2025/26 PositionRESOLVED that the current significant items on the Corporate Risk Register, as presented, be received and noted. Reas...
Appropriation of Land at Kingsway ParkRESOLVED that a) it be noted that the Secretary of State for Housing, Communities & Local Government granted consent ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.