a) that the current Festival Hall site, Kirkby-in-Ashfield be approved as the preferred site for a new flagship leisure destination. b) that the indicative financial business model for the design and construction of the new leisure centre at the existing Festival Hall site, as attached to the officer’s report, be approved. c) that a further report be brought back to Cabinet, and subsequently to Council for funding approval after the completion of the tendering process. d) that authority be delegated to the Interim Director of Place and Communities, in consultation with Deputy Leader (Inward Focus), to: i. select a suitable Framework agreement to appoint the professional team for the project; ii. commission the professional team to undertake design and development work to progress the project through to the end of RIBA Stage 4; iii. approve the procurement of the leisure centre through the use of a competitive procedure with negotiation, for a Design and Build contract. REASONS FOR DECISIONS To enable the project to continue to be developed to the next stage. The report included indicative capital and revenue implications. In the longer term the project seeks to deliver revenue savings through an “invest to save” approach resulting in a reduction in revenue costs when the Council retenders the leisure operator contract. ALTERNATIVE OPTIONS CONSIDERED AND REASONS FOR REJECTION The alternative option of not doing anything was not recommended as the Leisure Facilities Review had allowed the Council to understand the appropriateness of its current leisure stock and future requirements. The provision of an effective facility infrastructure will be central to the successful delivery of the health and wellbeing objectives within the Corporate Plan and to achieving savings through the leisure contract.
Word for word from the decision Ashfield published for this meeting.Source: democracy.ashfield.gov.uk
To update Cabinet on the Leisure Transformation Programme and to seek authorisation to proceed with the next steps towards delivering a new flagship leisure destination at the current Festival Hall site, in Kirkby-in-Ashfield.
Recommendations
Cabinet is asked:
1) To agree the current Festival Hall site, Kirkby-in-Ashfield as the preferred site for a new flagship leisure destination.
2) To note and approve the indicative financial business model for the design and construction of the new leisure centre at the existing Festival Hall site and note a further report will be brought back to Cabinet and subsequently Council for funding approval post tendering.
3) To delegate authority to the Interim Director of Place and Communities, in consultation with the Portfolio Holder to:
a) select a suitable Framework agreement to appoint the professional team for the project;
b) commission the professional team to undertake design and development work to progress the project through to the end of RIBA Stage 4;
c) Approve the procurement of the leisure centre through the use of a competitive procedure with negotiation, for a Design and Build contract. Reasons for Recommendations
Approval of the recommendations will enable the project to continue to be developed to the next stage. The report includes indicative capital and revenue implications. In the longer term the project seeks to deliver revenue savings through an “invest to save” approach resulting in a reduction in revenue costs when the Council retenders the leisure operator contract.
Alternative options considered
Do nothing: not recommended for a number of reasons. The Leisure Facilities Review has allowed the Council to understand the appropriateness of its current leisure stock and future requirements. The provision of an effective facility infrastructure will be central to the successful delivery of the health and wellbeing objectives within the Corporate Plan and to achieving savings through the leisure contract.
Detailed Information
The Council’s Vision
The Council vision is for local people to have access to modern leisure facilities to help lead healthier lifestyles. A clear approach to providing facilities has been identified, including investment and rationalising the use of the Council’s assets alongside coordinated provision from other sources.
To help sustain leisure provision into the future, the Council’s Vision is ‘to secure a districtwide network of quality, affordable, accessible and sustainable Leisure Centres and services for the benefit of all residents of Ashfield'. In order to achieve the Council’s vision Key Projects have been identified within the Corporate Plan: firstly, to carry out a Leisure Facilities Review (July 2016) and secondly, to explore the feasibility for a replacement for the Festival Hall Leisure Centre (informed by the Leisure Review).
Leisure Review
The Council recognises the need to invest in its sport and leisure infrastructure to meet the objectives of reducing inactivity and improving the health and wellbeing of its residents; as well as ensuring the most cost effective provision. In order to address Corporate Plan priorities, an extensive Leisure Facilities Review was undertaken and Cabinet endorsed the findings on 14 th July 2016.
The transformation programme for leisure centre provision has a clear approach to providing future facilities, including investment and rationalising the use of Council assets, alongside coordinated provision from other sources.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Plan Year End Delivery 2025/26RESOLVED that a) the levels of delivery achieved against the Corporate Plan Priorities, as outlined in the report, be...
Corporate Risk Year End 2025/26 PositionRESOLVED that the current significant items on the Corporate Risk Register, as presented, be received and noted. Reas...
Appropriation of Land at Kingsway ParkRESOLVED that a) it be noted that the Secretary of State for Housing, Communities & Local Government granted consent ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.