RESOLVED that a) progress on the Future High Streets bid for Sutton and the Towns Fund for Kirkby and Sutton, be noted; b) delegated authority be granted to the Director of Place and Communities, in conjunction with the Portfolio Holder for Place, Planning and Regeneration to: · commission consultancy work for the development of projects to be included within the Investment Plan, funded through the Towns Fund capacity funding; · submit the full business case for the FHSF bid in July 2020 and the joint Towns Fund Investment Plan for Kirkby and Sutton during autumn 2020.
Word for word from the decision Ashfield published for this meeting.Source: democracy.ashfield.gov.uk
To update Cabinet on the Future High Streets Fund bid for Sutton and the Towns Funding for Kirkby and Sutton and seek delegated authority for the submissions.
Recommendation(s) 1. To note progress on the Future High Streets (FHSF) bid for Sutton and the Towns Fund for Kirkby and Sutton. 2. To agree delegated authority to the Portfolio Holder for Place, Planning and Regeneration and the Director of Place and Communities to: a) Commission consultancy work for the development of projects to be included within the Investment Plan, funded through the Towns Fund capacity funding. b) Submit the full business case for the FHSF bid in July 2020 and the joint Towns Fund Investment Plan for Kirkby and Sutton during autumn 2020.
Reasons for Recommendation(s) To ensure that submissions can be made to the FHSF and Towns Fund within the required timescales.
Alternative Options Considered Not to agree submissions – this would mean that the business case for FHSF and the Towns Fund Investment Plan would not be submitted and the potential to access significant funding would be lost.
Detailed Information
Towns Fund update Towns Fund provides an allocation for Sutton and Kirkby and the Council is tasked with working with partners to submit a business case to the Government. In view of the Covid 19 lockdown, it was not possible to hold the large and open public consultation events which we had planned; these would have involved face to face meetings with community groups, public consultations via market stalls and meetings with businesses. Instead, the consultation strategy was necessarily changed to an entirely digital one. A Member and public web-based consultation closed on 31st May, with 847 responses for Sutton and 524 for Kirkby - c.4% response rate. Member workshops and a Discover Ashfield Board meeting took place in June to provide feedback from the consultation and to agree the capital projects to be included within the Investment Plan. There have also been c.150 suggestions through Government’s #MyTown campaign.
Partner engagement Prior to the Covid-19 lockdown, a well-attended stakeholder event took place in February, followed by meetings with Nottingham Trent University, Inspire and the County Council’s Local Transport Plan team. Other County Council responses/ project ideas were coordinated through the NCC economic development team. The feedback from all of the consultation was reported to the Town Board – Discover Ashfield on 24th June.
Skills and Enterprise Infrastructure theme Chimera Consulting were appointed to undertake work for this theme and are making good progress, liaising with partners including Nottingham Trent University (NTU), Mansfield & Ashfield 2020, Inspire, Nottinghamshire County Council and education providers. The work will provide an audit of the current provision for employment and skills development activity, clarification of local needs and issues, understanding employers’ needs and testing emerging ideas.
Government guidance and support The latest guidance was published in June which included a template for the investment plan and revised timeframes. Support is being provided through Department for Business, Energy & Industrial Strategy with an officer designated for Kirkby and Sutton. Low carbon/ clean growth is expected to be a focus for capital projects included within Investment Plans.
The Investment Plan will be prepared over the summer, informed by professional support to produce high-level costings and outputs for each of the projects.
Capacity funding Commitments and spend for the project to date are detailed below.
Kirkby Amount Masterplan £6,000 Consultation £352 Specialist advisors for skills and enterprise £7,150 Total £13,502 Remaining (£162,019) £148,517
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Plan Year End Delivery 2025/26RESOLVED that a) the levels of delivery achieved against the Corporate Plan Priorities, as outlined in the report, be...
Corporate Risk Year End 2025/26 PositionRESOLVED that the current significant items on the Corporate Risk Register, as presented, be received and noted. Reas...
Appropriation of Land at Kingsway ParkRESOLVED that a) it be noted that the Secretary of State for Housing, Communities & Local Government granted consent ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.