RESOLVED that a) Council be recommended to approve the total budget of £15.5m and the funding basis for the development of a new Leisure Centre in Kirkby in Ashfield; b) the identified prudential borrowing required to support the development, be approved; c) the progress with external funding applications for £3m, be noted; d) it be declared that the Housing Revenue Account land at Hucknall Leisure Centre is not required for housing purposes and approve the appropriation of the land from the Housing Revenue Account to the General Fund at a value of £4,000.
Word for word from the decision Ashfield published for this meeting.Source: democracy.ashfield.gov.uk
To update Cabinet on the Leisure Transformation Programme and to seek authorisation to proceed with the next steps:
1. To move forwards with the Kirkby Leisure Centre development. 2. To update Cabinet with the funding solution and progress with securing external funding. 3. To appropriate a small area of land within the Hucknall Leisure Centre site from the HRA.
Recommendation(s) Cabinet is recommended to approve: 1. To recommend to Council, approval of a total budget of £15.5m and the funding basis for the development of a new Leisure Centre in Kirkby in Ashfield. 2. To approve the identified prudential borrowing required to support the development. 3. To note the progress with external funding applications for £3m 4. To declare that the Housing Revenue Account land at Hucknall Leisure Centre is not required for housing purposes and approve the appropriation of the land from the Housing Revenue Account to the General Fund at a value of £4,000.
Reasons for Recommendation(s)
1. The development phases of the Leisure Centre have previously been approved. However in line with previous reports and effective governance procedures further approval is required for Council to agree the total budget envelope for the Leisure Centre development at £15.5m of which £12.157m is to be funded through prudential borrowing.
2. The appropriation of land at Hucknall Leisure Centre is required so that the Leisure Operating Contract that is currently being tendered for a start in April 2021 can move forwards utilising Sport England standard approaches. The land needs to be appropriated from the Housing Revenue Account as it is currently designated for potential use for housing. Alternative Options Considered
1. The Cabinet can decide not to recommend to Council approval of the required budget and funding mechanism for the Leisure Centre development – Not Recommended 2. Not appropriating the area of land – all of the land needs to be within the General Fund and appropriated for Recreation and Amenities in order for the project to progress. Not Recommended
Detailed Information
Leisure Centre Development Progress
Officers of the Council along with the appointed external professional team have been progressing with the design of Kirkby Leisure Centre.
The project has currently achieved completion of the Royal Institute of British Architects (RIBA) stage 3 of their Plan of Work 2015. When each stage completes, a full Cost Plan is developed to monitor progress and adherence to budgets. The RIBA 3 Cost Plan has identified a total budget of £15,500,000 for the works and on-costs. This Cost Plan has been reviewed and validated by the Council’s finance officers.
RIBA 4 development is currently ongoing as well as the early stages of procuring a Main Works Contractor to complete the works.
Planning permission for the leisure centre was granted at Planning Committee on 17th June 2020.
Funding Proposal The RIBA 3 Cost Plan has identified the necessary budget for the Leisure Centre as being £15,500,000. The Council has submitted an Expression of Interest to Sport England for funding support for £1,500,000 towards the project. The Local Enterprise Partnership (LEP) have been approached for £1,500,000. It is anticipated that a decision from both funding bodies will be achieved before contracts for the capital works are entered into which will be Autumn 2020. Finally, the Council has allocated £343,000 of Section 106 monies.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Plan Year End Delivery 2025/26RESOLVED that a) the levels of delivery achieved against the Corporate Plan Priorities, as outlined in the report, be...
Corporate Risk Year End 2025/26 PositionRESOLVED that the current significant items on the Corporate Risk Register, as presented, be received and noted. Reas...
Appropriation of Land at Kingsway ParkRESOLVED that a) it be noted that the Secretary of State for Housing, Communities & Local Government granted consent ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.