Resolved
RESOLVED that the current significant items on the Risk Register and the actions being taken to mitigate those risks, be received and noted.
Cabinet noted this item on Monday 19 July 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the current significant items on the Risk Register and the actions being taken to mitigate those risks, be received and noted.
For Cabinet to review the Corporate Risk Register and the analysis of movement in risk and mitigating actions in respect of those risks.
Recommendation(s)
Cabinet are asked to endorse the current significant items on the Register and to consider whether any further immediate actions are necessary to mitigate those risks.
Reasons for Recommendation(s)
On 23rd February 2021, Cabinet approved the updated Corporate Risk Strategy and new Risk Appetite Framework. Updates to the Corporate Risk Strategy were considered appropriate in order to facilitate greater understanding of risk maturity and improved organisational performance against the Alarm national performance model for risk management in public services, as suggested by Internal Audit. This was also highlighted as an improvement action in the Annual Governance Statement.
In accordance with the Corporate Risk Strategy, it is the role of Cabinet to monitor the Council’s risk management and internal control arrangements, as part of the established quarterly monitoring and to recommend action where necessary.
Alternative Options Considered None Detailed Information
Context/Background
All organisations are required to consider potential risks which may impede the delivery of corporate objectives. Effective risk management processes strengthen the ability of the Council to react to all situations and protect its own interests and those of the District, ensuring essential service delivery, through actively managing and mitigating risk effectively and innovatively. The management of risk forms an integral part of the Council’s business. Effectively managing our risks means that we can maximise opportunities and minimise the costs and disruption to the Council which may possibly be caused by undesired events.
All strategic risk at corporate and service level is incorporated into the Pentana performance system to enable quarterly updates at the same time as updating performance, therefore enhancing the consideration of risk in the delivery of services.
All levels of risk are discussed bi-annually in detail with each service manager as a standing agenda item for Performance Boards, led by the Chief Executive and Assistant Director – Corporate Services and Transformation.
In summary, despite the impacts of the pandemic, overall, the current corporate risk position indicates the positive management of risk:-
• 55% of corporate risks have been effectively managed without an increase in risk assessment rating over the last 12 months • Positively, 32% of corporate risks have been effectively managed and mitigated with a reduction in risk assessment rating over the last 12 months
Corporate Risk Register
The Corporate Risk Register (position as at year-end 2020/21) is appended to this report.
There was substantial review of our corporate risks in April 2020 to reflect the organisational impact of the COVID pandemic. As a result, during the last 12 months, the following risks impacted by COVID have been:-
Introduction of universal credit - At the end of the financial year, Universal Credit claiming tenants contributed to 50% of the total rent arrears cases and 68% of the rent arrears value. The total rent arrears value attributed to Universal Credit at week 52 = £274,124.93 (570 cases). At the end of the financial year, 26% of tenants were claiming Universal Credit.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Corporate Risk: Year End 2020/21 PositionReport | 191 KB | DownloadRead as text |
PDF |
Enc. 1 Corporate Risk RegisterReport | 468 KB | Download |
Follow Cabinet at Ashfield and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 27 Jul 2026 | Local Government Reorganisation (Verbal Update and Q/A Session)RESOLVED that a) the information provided and the ongoing work being undertaken to support the transition programme, ... | Noted | Open |
| 27 Jul 2026 | Corporate Plan Year End Delivery 2025/26RESOLVED that a) the levels of delivery achieved against the Corporate Plan Priorities, as outlined in the report, be... | Noted | Open |
| 27 Jul 2026 | Corporate Risk Year End 2025/26 PositionRESOLVED that the current significant items on the Corporate Risk Register, as presented, be received and noted. Reas... | Noted | Open |
| 27 Jul 2026 | Update - Charitable Trust Issues at Lord Francis Park (Kirkby-in-Ashfield), Hucknall Leisure Centre and Titchfield Park (Hucknall)RESOLVED that a) the current position relating to Charitable Trust Issues at Lord Francis Park (Kirkby-In-Ashfield), ... | Noted | Open |
| 27 Jul 2026 | Appropriation of Land at Kingsway ParkRESOLVED that a) it be noted that the Secretary of State for Housing, Communities & Local Government granted consent ... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.