RESOLVED that the Treasury Management performance including the compliant prudential indicators, as outlined in the report, be received and noted and recommended to Cabinet for further consideration.
Audit Committee noted this item on Monday 26 July 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the Treasury Management performance including the compliant prudential indicators, as outlined in the report, be received and noted and recommended to Cabinet for further consideration.
This report provides information on the Council’s Treasury Management activities which the Council carries out to manage both its funding and its cash flow, with the aim of minimising the risks to which the Council is exposed when borrowing and lending monies.
It sets out the performance in 2020/21 against the prudential indicators, which were previously approved by Full Council on the 5th March 2020, as part of the Treasury Management Strategy. This ensures that borrowing and lending are controlled within reasonable limits, in line with good practice.
Recommendation(s)
Members are requested to: i) Note the performance including the compliant prudential indicators, as outlined in the report.
ii) Recommend consideration of the report by Cabinet, including points raised by the Audit Committee in respect of the report (if any).
Reasons for Recommendation(s) The requirements of the Council’s Financial Regulations include:
(C.31) the Audit Committee is responsible for ensuring effective scrutiny of the Treasury Management Strategy and policies. (C.30), Cabinet will receive an annual Treasury Management Performance Report. In accordance with CIPFA Code of Practice for Treasury Management in Public Services (the “CIPFA TM Code”), Members should approve the annual report for Treasury Management activity in 2020/21 which forms part of this document.
Under CIPFA’s Prudential Code for Capital Finance in Local Authorities, Members have a statutory duty to adopt a set of annual indicators relating to capital expenditure and Treasury Management.
Alternative Options Considered None. A report must be received to comply with the Council’s Financial Regulations and CIPFA Codes of Practice.
Detailed Information
TREASURY MANAGEMENT - ANNUAL REPORT 2020/21
1. Introduction
1.1The Treasury Management Policy Statement includes a requirement for the production of an Annual Report on the Treasury Management activities undertaken during the year. This requirement is also incorporated in the Council's Financial Regulations and is considered as good practice in the Chartered Institute of Public Finance & Accountancy (CIPFA) Code of Practice for Treasury Management.
2. The Financial Markets During 2020/21
2.1Investment returns which had been low during 2019/20, plunged during 2020/21 to near zero or even into negative territory. Most local authority lending managed to avoid negative rates and one feature of the year was the growth of inter local authority lending. The expectation for interest rates within the treasury management strategy for 2020/21 was that Bank Rate would continue at the start of the year at 0.75 % before rising to end 2022/23 at 1.25%. This forecast was invalidated by the onset of the Covid-19 pandemic in March 2020 which caused the Monetary Policy Committee to cut the Bank Rate in March, first to 0.25% and then to 0.10%, in order to counter the hugely negative impact of the national lockdown on large swathes of the economy. The base rate has remained at 0.10% for the duration of 2020/21.
2.2The Bank of England and the Government also introduced new programmes of supplying the banking system and the economy with massive amounts of cheap credit so that banks could help cash-starved businesses to survive the lockdowns. The Government also supplied huge amounts of finance to local authorities to pass on to businesses. This meant that for most of the year there was much more liquidity in financial markets than there was demand to borrow, with the consequent effect that investment earnings rates plummeted.
3. Borrowing
3.1The borrowing activities undertaken during the year are summarised below: Table 1 – Borrowing Activities 2020/21
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Council's Treasury Management and Borrowing Activities 2020/21Report | 287 KB | DownloadRead as text |
Follow Audit Committee at Ashfield and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 25 Jun 2026 | Public Sector Decarbonisation SchemeRESOLVED that a) the findings of the Public Sector Decarbonisation Scheme review, as presented, be received and noted... | Noted | Open |
| 25 Jun 2026 | Section 100A Local Government Act 1972: Exclusion of the Press and PublicRESOLVED that in accordance with the provisions of Section 100A of the Local Government Act 1972, the press and publi... | Decided | Open |
| 25 Jun 2026 | FORVIS MAZARS: 2024-25 Audit Opinion UpdateRESOLVED that the update report be received and duly noted. | Noted | Open |
| 25 Jun 2026 | Audit Committee Work Plan and Improvement Plan - 2026/2027RESOLVED that a) the draft Committee Work Plan 2026/2027, as attached at Appendix 1, be approved; b) the draft Improv... | Approved | Open |
| 25 Jun 2026 | Automated Distribution and Manufacturing Centre (ADMC) and Ashfield Innovation and Technology Park (AITP) - UpdateRESOLVED that a) the update report, presented to Cabinet on 15 June 2026, be received and noted; b) in line with the ... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.