RESOLVED that a) approval be given to the audited Statement of Accounts for 2020/21 subject to the outstanding items identified in the External Auditors Completion Report 2020/21; b) delegated authority be granted to the Corporate Finance Manager (Section 151 Officer), for final approval of the audited Statement of Accounts for 2020/21, subject to a satisfactory outcome of outstanding items with a proviso to report back to Audit Committee details of any changes, if required.
Word for word from the decision Ashfield published for this meeting.Source: democracy.ashfield.gov.uk
This report presents the Audit Committee with the Council’s Statement of Accounts for 2020/21 and reports on the outcome of the external audit of the Council’s Statement of Accounts 2020/21.
Subject to approval of the Statement of Accounts by the Audit Committee, a copy of the audited Final Statement of Accounts will be placed on the Council’s website.
Recommendation(s) To approve the audited Statement of Accounts for 2020/21 subject to the outstanding items identified in the External Auditors Completion Report 2020/21 .
To delegate authority for the final approval of the audited Statement of Accounts for 2020/21 to the Corporate Finance Manager (Section 151 Officer) subject to a satisfactory outcome of outstanding items and to report back to Audit Committee details of any changes, if required.
Reasons for Recommendation(s) To comply with Financial Regulations which form part of the Council’s Constitution. These state the Audit Committee is responsible for approving the Annual Statement of Accounts.
Alternative Options Considered None as it is a statutory requirement for Council’s to publish the audited Annual Statement of Accounts and a requirement of the Council’s Financial Regulations for the Audit Committee to approve the annual Statement of Accounts. Detailed Information Prior to the Covid-19 pandemic, the deadline for completion and publication of the draft Statement of Accounts was 31 May and the deadline for the final audited Statement of Accounts was the 31 July. Due to the on-going Covid-19 pandemic, these statutory deadlines were amended by the Accounts and Audit (Amendment) Regulations 2021. The deadlines for the publication of the draft accounts was extended to the 31 July and the deadline for the publication of final audited accounts was extended to 30 September, for the financial years beginning 2020 and 2021.
Despite these changes, the Council’s draft Statement of Accounts (excluding the Annual Government Statement (AGS)) were provided to Mazars, the External Auditors on the 18th June 2021, in advance of the publication deadline.
Due to providing the draft Statement of Accounts before the extended statutory deadline, the National Non Domestic Rates (NNDR) position included in the Statement of Accounts was based on an estimated position pending the completion of the NNDR 3 claim, which also had an extended deadline to 30th June 2021.
Adjustments have been made between the draft and final Statement of Accounts 2020/21 to reflect the final NNDR 3 claim, resulting in an increase in the General Fund balance of £24k.
An error was identified by Council Finance officers in relation to a revaluation and an adjustment has been made between the draft and final Statement of Accounts 2020/21. The error was due to a building value being overstated when the revaluation was accounted for. This amendment decreased the Property Plant and Equipment in the balance sheet by £1.531m, which passes through the Comprehensive Income & Expenditure Statement (CIES) but is reversed out in Movement in Reserves Statement (MIRS) to the Revaluation Reserve in the Balance Sheet, and therefore does not impact on the in-year surplus for 2020/21.
The audit resulted in some minor presentational changes being made to the note to the accounts: The banding identified for an officer remuneration payment had been amended The exit packages note has been amended following an adjustment to note being required, identified after the draft note had been prepared.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Public Sector Decarbonisation SchemeRESOLVED that a) the findings of the Public Sector Decarbonisation Scheme review, as presented, be received and noted...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.