Resolved
RESOLVED that the Follow Up Letter from Mazars outlining the conclusion of pending matters for the year ended 31 March 2022, as presented, be received and noted.
Audit Committee noted this item on Monday 20 March 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the Follow Up Letter from Mazars outlining the conclusion of pending matters for the year ended 31 March 2022, as presented, be received and noted.
Park View House 58 The Ropewalk Nottingham NG1 5DW
www.mazars.co.uk
Audit Committee Ashfield District Council Council Offices Direct dial [phone removed] Urban Road Kirkby in Ashfield Email [email removed] Nottinghamshire NG17 8DA
14 March 2023
Dear Members
Conclusion of pending matters – Audit Completion Report for Ashfield District Council Following on from our recent meeting and as required by International Standards on Auditing (UK and Ireland), I am writing to communicate the conclusion of those matters that were marked as outstanding within the Audit Completion Report dated 17 November 20222. The outstanding matters and the conclusions reached are detailed below:
Audit area Status Description of outstanding matters
S106 Capital Complete Included within our Audit Completion Report, dated 17 November Grants Unapplied 2022, we stated that the Council had identified a material prior period adjustment to the financial statements, that at the time was being quantified and processed. All information has been received and processed. No issues have been identified that need to be brought to the attention of members. Refer to Appendix A for further information in respect of the associated adjusted misstatement. Investment Complete All information has been received and processed. Property and No issues have been identified that need to be brought to the Property, Plant attention of members. and Equipment Valuations Loans and Complete All information has been received and processed. Borrowings No issues have been identified that need to be brought to the attention of members. Related Parties Complete All information has been received and processed. No issues have been identified that need to be brought to the attention of members.
Mazars LLP is the UK firm of Mazars, an integrated international advisory and accountancy organisation. Mazars LLP is a limited liability partnership registered in England and Wales with registered number OC308299 and with its registered office at Tower Bridge House, St Katharine’s Way, London E1W 1DD. We are registered to carry on audit work in the UK by the Institute of Chartered Accountants in England and Wales. Details about our audit registration can be viewed at www.auditregister.org.uk under reference number C001139861. VAT number: 839 8356 73 Audit area Status Description of outstanding matters
Information Complete All information has been received and processed. Technology No issues have been identified that need to be brought to the General Control attention of members. (ITGC) document IAS19 Defined Complete Included within our Audit Completion Report, dated 17 November benefit liability 2022, we stated that there was an unadjusted misstatement in valuation relation to the Council’s IAS19 Defined benefit liability valuation. In particular around the increase of related assets. Two additional letters were received from the Nottinghamshire Pension Fund Auditor’s, dated 14 November (which was still being processed at the time of writing our completion report) and 24 November 2022 stating variations to their intended report. This subsequently resulted in further procedures being undertaken an adjusted misstatement being identified and processed by management. Refer to appendix A for further information. Whole of Incomplete The National Audit Office’s Group Instructions for local authority Government 2021/22 audits remain unavailable and consequently WGA returns, Accounts and audit certificates cannot be issued at the present time. We will aim to complete this work as soon as these instructions are available and report back to the Audit Committee on completion. Completion Complete We have undertaken the outstanding procedures and received the Procedures residual audit documentation required and our work is complete.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
MAZARS: Conclusion of Pending Matters: Audit Completion ReportReport | 372 KB | DownloadRead as text |
Follow Audit Committee at Ashfield and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 25 Jun 2026 | Public Sector Decarbonisation SchemeRESOLVED that a) the findings of the Public Sector Decarbonisation Scheme review, as presented, be received and noted... | Noted | Open |
| 25 Jun 2026 | Section 100A Local Government Act 1972: Exclusion of the Press and PublicRESOLVED that in accordance with the provisions of Section 100A of the Local Government Act 1972, the press and publi... | Decided | Open |
| 25 Jun 2026 | FORVIS MAZARS: 2024-25 Audit Opinion UpdateRESOLVED that the update report be received and duly noted. | Noted | Open |
| 25 Jun 2026 | Audit Committee Work Plan and Improvement Plan - 2026/2027RESOLVED that a) the draft Committee Work Plan 2026/2027, as attached at Appendix 1, be approved; b) the draft Improv... | Approved | Open |
| 25 Jun 2026 | Automated Distribution and Manufacturing Centre (ADMC) and Ashfield Innovation and Technology Park (AITP) - UpdateRESOLVED that a) the update report, presented to Cabinet on 15 June 2026, be received and noted; b) in line with the ... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.