RESOLVED that progress regarding the Council’s major projects and funding programmes, as outlined in the report, be received and noted. Reasons: 1. To ensure that Cabinet is kept updated on progress with the Major projects, funding programmes and submission of funding bids. 2. To ensure that projects and spend within the funding programmes are achieved within the set timeframes and programme budget envelopes. 3. To ensure funding streams are delivered collaboratively and effectively. 4. To ensure Members are aware as early as possible about the potential cost pressures which may require additional Council funding in the future.
Word for word from the decision Ashfield published for this meeting.Source: democracy.ashfield.gov.uk
1. To ensure that Cabinet is kept updated on Major projects, progress of funded programmes and bids for external funding.
2. To note a potential future cost pressure for the Public Sector Decarbonisation Scheme (PSDS) programme which may require additional Council funding.
Recommendation(s)
1. To note the progress on Major projects and funding programmes.
Reasons for Recommendation(s)
1. To ensure that Cabinet is kept updated on progress with the Major projects, funding programmes and submission of funding bids.
2. To ensure that projects and spend within the funding programmes are achieved within the set timeframes and programme budget envelopes.
3. To ensure funding streams are delivered collaboratively and effectively.
1 4. To ensure Members are aware as early as possible about the potential cost pressures which may require additional Council funding in the future.
Alternative options considered
• No options to consider within this report.
Detailed Information
The report provides an overview of programme performance for the following:
1.0Future High Streets Fund 2.0 Towns Fund and Levelling Up Fund 3.0 UK Shared Prosperity Fund 4.0 Place Partnership bid 5.0 Public Open Space/ Public Realm 6.0 Public Sector Decarbonisation Scheme 7.0 Community Safety funded initiatives.
1.0Future High Streets Fund
1.1Progress A progress and risk-based summary for each project is provided below.
Project Achievements/ progress/next steps Risk Level / programme and cost
Theatre Project Funds have now been approved to be moved from the Towns Fund project to bridge the funding gap identified at RIBA stage 2. The design team are now progressing RIBA stage 3. We are now in discussion with DLUHC regarding revising the delivery programme. Low Street 14 Low Street - Complete. 9-11 Low Street - Value engineering completed which has identified a way to reduce the cost of the project. The adjustment will result in a minor change to the project outputs. The tender submission is due on 23rd August. The project remains on track to complete March 2024. High Pavement Project is on site and remains on track to complete November 2023. Heads of Terms have been agreed with a new anchor tenant who will take on the ground floor and first floor in the west wing of the building. Makerspace committee is growing and now leading on promotion of the new facilities and developing the fit out of the space. Fox Street Initial cost planning with a framework contractor has established further value engineering is required to
2 establish a fixed cost for the scheme within our budget envelop. Key options have been identified and are being evaluated. The project remains on track for completion March 2024. Risk has elevated due to the additional value engineering period required to bring the project within the budget envelope.
2.0Towns Fund and Levelling Up Fund 2.1 Project highlights report A progress and risk-based summary for each project is provided below. Project Achievements/ progress/next steps Risk Level / programme and cost Be Healthy Be Happy North Kirkby A specialist property legal team has been appointed to Gateway advise and develop an agreement with a developer to progress the land assembly and development for the Pond Hole / Ellis Street development. Kirkby Sports Hub The project design team are now appointed to review and finalise RIBA stage 2 and address budget risks to ensure the scheme remains within the budget envelope.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Plan Year End Delivery 2025/26RESOLVED that a) the levels of delivery achieved against the Corporate Plan Priorities, as outlined in the report, be...
Corporate Risk Year End 2025/26 PositionRESOLVED that the current significant items on the Corporate Risk Register, as presented, be received and noted. Reas...
Appropriation of Land at Kingsway ParkRESOLVED that a) it be noted that the Secretary of State for Housing, Communities & Local Government granted consent ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.