RESOLVED that a) progress in relation to the major projects and funding programmes outlined in the report, be received and noted; b) in respect of the ‘Plan for Towns’ programme for Kirkby: · to recommend to Council to accept funding from the programme; · to agree that the Council will act as the Accountable Body; · to delegate authority to the Chief Executive Officer for the signing of documents including a Heads of Terms and Memorandum of Understanding; c) to recommend to Council to accept the Devolution – Retrofit funding. Reasons: 1. To ensure that Cabinet is kept updated on progress with the Major projects, funding programmes and submission of funding bids. 2. To ensure that projects and spend within the funding programmes are achieved within the set timeframes and programme budget envelopes. 3. To ensure funding streams are delivered collaboratively and effectively. 4. To ensure Members are aware as early as possible about the potential cost pressures which may require additional Council funding in the future. 4.
Word for word from the decision Ashfield published for this meeting.Source: democracy.ashfield.gov.uk
To ensure that Cabinet is kept updated on Major projects, progress of funded programmes and bids for external funding, and that the necessary approvals are in place.
Recommendation(s)
1. To note the progress on major projects and funding programmes
Plan for Towns programme for Kirkby 2. To recommend to Council to accept funding from the programme 3. To agree that the Council will act as the Accountable Body 4. To delegate authority to the Chief Executive Officer for the signing of documents including a Heads of Terms and Memorandum of Understanding
5. To recommend to Council to accept the Devolution – Retrofit funding. Reasons for Recommendation(s)
1. To ensure that Cabinet is kept updated on progress with the Major projects, funding programmes and submission of funding bids.
2. To ensure that projects and spend within the funding programmes are achieved within the set timeframes and programme budget envelopes.
3. To ensure funding streams are delivered collaboratively and effectively.
4. To ensure Members are aware as early as possible about the potential cost pressures which may require additional Council funding in the future.
Alternative options considered
Not to accept the funding from government for Kirkby from the Plan or Towns programme or the Devolution – Retrofit funding. This option was rejected as the funding is available and can utilised effectively to deliver the Council’s corporate priorities.
Detailed Information
The report provides an overview of programme performance and new/ potential funding for the following: 1.0 Future High Streets Fund 2.0 Towns Fund and Levelling Up Fund 3.0 UK Shared Prosperity Fund 4.0 Kirkby ‘Plan for Towns’ programme 5.0 Place Partnership bid 6.0 Public Open Space/ Public Realm 7.0 Public Sector Decarbonisation Scheme 8.0 Devolution – Retrofit Funding 9.0 Community Safety
1.0Future High Streets Fund
A progress and risk-based summary for each project is provided below.
Project Achievements/ progress/next steps Risk Level / programme and cost
Theatre Project RIBA stage 3 has been developed and reviewed and the procurement strategy is being progressed. We are in discussion with DLUHC regarding revising the delivery programme. The risk remains elevated because the project programme has slipped without the ability to bring forward the completion. Low Street 14 Low Street - Complete. 9-11 Low Street – the contract has been awarded and the Council is progressing the contract agreement and mobilisation.
High Pavement Project on site and remains on track to complete in November. Heads of Terms have been agreed with an anchor tenant who will take on the ground floor and first floor in the west wing of the building. Makerspace committee is growing and now leading on promotion of the new facilities and developing the fit out of the space. Business unit promotion is progressing alongside the UKSPF business grant scheme. Fox Street Value engineering has reduced the project budget requirements to £1.9 – £2.1 million to deliver the combined Portland Square and Fox Street projects. Subject to approval of funding reallocation and final value engineering options the project can be delivered.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Plan Year End Delivery 2025/26RESOLVED that a) the levels of delivery achieved against the Corporate Plan Priorities, as outlined in the report, be...
Corporate Risk Year End 2025/26 PositionRESOLVED that the current significant items on the Corporate Risk Register, as presented, be received and noted. Reas...
Appropriation of Land at Kingsway ParkRESOLVED that a) it be noted that the Secretary of State for Housing, Communities & Local Government granted consent ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.