Resolved
RESOLVED that the status report be received and noted.
Audit Committee noted this item on Thursday 17 July 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the status report be received and noted.
To update the Committee about the production of the Statement of Accounts. The accounts are delayed and this paper sets out the context for the delay, and measures taken to mitigate the risks arising from the delay.
Recommendation(s)
The Committee is asked to note that the draft Statement of Accounts 2024-25 has been delayed, the context for that delay and the consequent risks and implications.
Reasons for Recommendation(s)
To ensure that the Committee is kept updated on progress with the production of the accounts.
Not to inform the Committee about the delay, context for and consequences of the delay. Detailed Information
Background The Accounts and Audit Regulations 2015 set out a timetable by which councils are required to produce draft and final (audited) statements of accounts. Historically, draft statements were due by 30 June and final (audited) statements were due by 30 September. These dates have been varied through Amendment Regulations in recent years following various national issues. These include: Government’s desire for faster closedown; delays during the Covid pandemic; skills and capacity shortages at some councils and audit firms; and regulatory issues that stalled many of the audits for a lengthy period.
In respect of the 2024/25 accounts, the deadlines were set as: • 30 June 2025 for draft statements. • 27 February 2026 “backstop date” for the final accounts.
In previous years, the Council has met the deadline for draft accounts. However, last year, when the deadline was set at 31 May, our external auditor found a number of trivial errors. Whilst not material, this was characteristic of a rushed process.
Progress with 2024/25 Draft Accounts
The Finance team initially set an ambitious timetable to produce the draft accounts by 31 May. This was based on the timetable from the previous year. It soon became clear that this could not be achieved due to the factors set out below. However, we were initially confident that the 30 June deadline would be met. It later became clear that this also could not be achieved and officers initially proposed to delay the draft accounts publication by one month. At the time of drafting this report, (01 July), substantial progress has been made, but a further delay into August is anticipated.
The reasons for the delay flow from the introduction of a new ledger system part way through the year. Fundamentally, this has required additional reconciliation work between the ledgers and the underlying data, to demonstrate continuity and consistency. It was further complicated by the introduction of new financial coding structures alongside the ledger. Also, during the introduction of the new system and ancillary technology (such as invoice scanning), various technical issues arose, which required ‘work arounds’ to address backlogs in day-to-day processes, such as paying suppliers. These ‘work around’ procedures have also required additional work downstream, to demonstrate the accuracy of the related accounting entries, to the standard that external auditors will require. This has proven more time consuming than originally anticipated.
A secondary factor has been significant turnover of personnel since the 2023-24 accounts were prepared, resulting in loss of continuity. We have had a change of Director, Assistant Director, interim Chief Accountant and two Principal Accountants, plus some other posts in the wider team. Only 2 staff undertaking key tasks on the accounts were undertaking this work at Ashfield last year. In addition, we had vacancy and a sickness absence in the wider team, but these are now resolved.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Statement of Accounts 2024-2025Report | 106 KB | DownloadRead as text |
Follow Audit Committee at Ashfield and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 25 Jun 2026 | Public Sector Decarbonisation SchemeRESOLVED that a) the findings of the Public Sector Decarbonisation Scheme review, as presented, be received and noted... | Noted | Open |
| 25 Jun 2026 | Section 100A Local Government Act 1972: Exclusion of the Press and PublicRESOLVED that in accordance with the provisions of Section 100A of the Local Government Act 1972, the press and publi... | Decided | Open |
| 25 Jun 2026 | FORVIS MAZARS: 2024-25 Audit Opinion UpdateRESOLVED that the update report be received and duly noted. | Noted | Open |
| 25 Jun 2026 | Audit Committee Work Plan and Improvement Plan - 2026/2027RESOLVED that a) the draft Committee Work Plan 2026/2027, as attached at Appendix 1, be approved; b) the draft Improv... | Approved | Open |
| 25 Jun 2026 | Automated Distribution and Manufacturing Centre (ADMC) and Ashfield Innovation and Technology Park (AITP) - UpdateRESOLVED that a) the update report, presented to Cabinet on 15 June 2026, be received and noted; b) in line with the ... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.