Resolved
RESOLVED that the Audit Progress report, as presented to Committee, be received and noted.
Audit Committee noted this item on Thursday 25 September 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the Audit Progress report, as presented to Committee, be received and noted.
External Audit Progress Report Ashfield District Council
September 2025 Contents
1. Backstop update 2. Value for money arrangements 3. Audit Fee update Backstop update 01 Backstop update Background
The statutory backstop established a date in legislation by which local authorities were required to publish their financial statements irrespective of whether their external auditor had obtained sufficient appropriate audit evidence to issue a non-disclaimed audit opinion. The introduction of the backstop led to many local authority audits being disclaimed. Ashfield District Council received disclaimed audit opinions on the 2022/23 and 2023/24 financial statements.
Audit suppliers have worked with the National Audit Office (NAO) and the Financial Reporting Council (FRC) to develop guidance to support local audit suppliers to rebuild assurance after previous audits have been disclaimed. In June 2025, the NAO issued its guidance to auditors on the special considerations for rebuilding assurance. LARRIG 06 makes clear the work required to rebuild assurance following a disclaimer of opinion may be significant and will vary between authorities.
Rebuilding following a disclaimer of opinion
Under normal circumstances and following a financial year where the auditor has given an unmodified opinion on the financial statements, auditors would usually rely on assurance obtained in the prior period to be satisfied that the opening balances in the current year are free from material error. Following the completion of audit procedures on in-year transactions, the auditor would usually be able to form an opinion on the current year’s financial statements.
When a disclaimer of opinion has been issued in the prior periods, no such assurance can be taken and the auditor must design alternative audit procedures to be able to form a position on the current year’s financial statements.
Risk assessment process
The guidance requires auditors to consider the facts and circumstances impacting the financial statements and the different classes of transactions and account balances, and to apply professional judgement in determining the appropriate level of audit work to rebuild assurance. In general, the greater the number of financial years subject to a disclaimed opinion, the greater risk of material misstatement that auditors need to address when determining the most appropriate way to rebuild assurance. Even in circumstances where only one year’s financial statements have been subject to a disclaimed opinion, the inherent risk of material misstatement will inevitably be higher than would ordinarily be the case.
LARRIG 06 places an emphasis on the risk assessment procedures auditors should undertake. We will conduct a comprehensive risk assessment which considers: • the Council’s system of internal control for the periods subject to disclaimed audit opinions; and • a detailed assessment of the potential risks for each account balance. Backstop update Initial risk assessment
Based on their local assessment of the level of risk, audit teams need to determine the most efficient approach to re-build assurance recognising the desire of all system partners to return to a position where audit suppliers can issue non-disclaimed audit opinions as soon as possible. In accordance with guidance set out in the LARRIG, this may require audit teams to depart from the approach to substantive audit testing they have adopted in previous years.
Possible options for substantive testing are set out in the LARRIG and can broadly be split between two approaches: • Proof in total approach: the total reserves balances is deduced by undertaking procedure son the top-half of the balance sheet, and targeted substantive procedures are performed. Must be undertaken in one audit year. • Historic testing approach: Full substantive tests of detail on transactions recognised in financial statements that received a disclaimed audit opinion. Assurance to be rebuilt over a number of years.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
FORVIS MAZARS: External Audit Progress ReportReport | 471 KB | DownloadRead as text |
Follow Audit Committee at Ashfield and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 25 Jun 2026 | Public Sector Decarbonisation SchemeRESOLVED that a) the findings of the Public Sector Decarbonisation Scheme review, as presented, be received and noted... | Noted | Open |
| 25 Jun 2026 | Section 100A Local Government Act 1972: Exclusion of the Press and PublicRESOLVED that in accordance with the provisions of Section 100A of the Local Government Act 1972, the press and publi... | Decided | Open |
| 25 Jun 2026 | FORVIS MAZARS: 2024-25 Audit Opinion UpdateRESOLVED that the update report be received and duly noted. | Noted | Open |
| 25 Jun 2026 | Audit Committee Work Plan and Improvement Plan - 2026/2027RESOLVED that a) the draft Committee Work Plan 2026/2027, as attached at Appendix 1, be approved; b) the draft Improv... | Approved | Open |
| 25 Jun 2026 | Automated Distribution and Manufacturing Centre (ADMC) and Ashfield Innovation and Technology Park (AITP) - UpdateRESOLVED that a) the update report, presented to Cabinet on 15 June 2026, be received and noted; b) in line with the ... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.