Ashfield District Council
Cabinet, Monday 13 April 2026 at 10.00am

ADMC Funding and Contracts - Response to the Section 5A Local Government and Housing Act 1989 Report from the Monitoring Officer

Decided Executive 2 papers

AI summaryAshfield Cabinet accepted the Monitoring Officer's Section 5A report on the ADMC project, with alternative resolution proposals to be considered in private session. An extra £7,761,342 of capital funding is needed to complete the scheme.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedAlternative resolution options to be debated in private
Money£7,761,342 additional capital neededTotal ADMC build and highways cost now £29,494,483
What happens nextCabinet 20 April 2026Council vote on extra capital; contractor could restart in early May
Who it affectsADMC project and AITP siteConstruction on Lowmoor Road, Kirkby/Sutton suspended since 9 January 2026

What was decided

Cabinet resolved to receive and accept the Monitoring Officer's Section 5A report, with full consideration of alternative resolution proposals to take place in private session.

Cabinet acknowledged the report as urgent under Overview and Scrutiny Procedure Rule 13, so it is not subject to the call-in procedure.

Implementation of the construction elements of the project is suspended until the end of the first business day after consideration of the response report concludes. Report P21

Why

The Monitoring Officer found that contracts were signed and works paid for before formal contracts were in place, breaching the Council's Contract Procedure Rules and Financial Regulations, and that procurement advice from the County Council team was not sought. Report P22, P23

An independent review found governance deficiencies on the ADMC project but no evidence of wilful non-compliance, attributing issues to staff changes, stretched senior attention and teams not being aligned early enough. Report P32, P33, P34

Highways Authority requirements for a new crossroads and supporting works have pushed the highways cost from £3.5 million to £9.5 million, a £6 million uplift tied to the wider AITP scheme, which the ADMC cannot proceed without. Report P16, P44

What happens next

A further Cabinet report on 20 April 2026 will consider the Council's decision on the additional £7,761,342 capital allocation, after which Cabinet will pick its preferred option to resolve the contract and procurement issues and finalise contracts. Report P51

The construction contractor has indicated works could restart on site in early May 2026, with highways completion targeted for August 2027, building completion September 2027 and handover October 2027. Report P51

The Chief Executive is to develop an Improvement Plan based on the Independent Review's learning points, to be presented to Cabinet in June 2026 and then referred to the Audit Committee for monitoring. Report P36, P38

The money

  • £62.6 million Towns Fund award to Ashfield in 2021 for 16 Kirkby and Sutton regeneration projects Report P6
  • £19m Towns Fund allocation for the ADMC, with around £10m in-kind match from NTU and Vision West Notts College Report P7
  • £4.48 million Total land purchase price for the ADMC/AITP site off Lowmoor Road Report P44
  • £516,462 Land cost apportioned to the ADMC Report P44
  • £3.96 million Land cost relating to the AITP element Report P44
  • £265,000 Anticipated cost for AITP masterplanning, surveys and outline planning submission Report P44
  • £3.5 million Original ADMC budget for highways improvements Report P44
  • £9.5 million Revised total expected highways works cost Report P44
  • £6 million Uplift in highways cost attributable to the AITP rather than the ADMC Report P44
  • £21,733,141 Current ADMC project budget, comprising £19,983,141 Towns Fund and £1,750,000 General Fund capital Report P48
  • £29,494,483 Current projected total cost of constructing the ADMC, opening it and completing the Section 278 highways works Report P49
  • £7,761,342 Additional capital programme allocation required for the ADMC and AITP to proceed Report P49, P63

Options considered

  • Chosen: Consider the Monitoring Officer's Section 5A report within 21 days, as statutorily required. Cabinet has no alternative other than to consider the report within the statutory deadline Report P1, P21
  • Chosen: Consider alternative proposals to those in the report to resolve the issues raised. A number of options are outlined in the report for Cabinet to weigh up in private session Report P2, P24
  • Rejected: Phasing the AITP development, seeking a development partner, selling the site or doing nothing. A detailed business case on the preferred options identified by Cabinet will come to a future Cabinet meeting for approval Report P47

Implications

  • Legal: Section 5A Local Government and Housing Act 1989 report identified possible breaches of the Council's governance and procurement processes; external legal advice obtained to support options and reduce risk of legal challenge. Report P21, P22, P23, P73
  • Financial: An additional £7,761,342 of capital is required; some or all of the AITP investment may be reimbursed from future land sales, and further funding may be needed depending on the option chosen. Interest may be payable if borrowing is required. Report P49, P62, P63
  • Risk: Risks include repayment of MHCLG grant if the ADMC cannot proceed, failure to deliver economic benefits, changing construction costs and land values, and any legal challenge; mitigations include the March 2028 grant extension, locked-in supplier costs, contingency budgets and ongoing monitoring. Report P68, P69, P70, P71, P72, P73
  • Staffing: External experienced project management support is being engaged for the ADMC, with overall accountability remaining with a senior Council officer; new support is expected to be in place by 13 April 2026. Report P40
  • Other: The report was assessed as having no equalities, human resources or Local Government Reorganisation implications. Report P75, P77, P79

Who and where

  • Lindum Group Limited, the construction contractor for the ADMC build and Section 278 works, with works suspended on site Report P18, P19, P27
  • Armson and Partners Ltd and YMD Boon, engaged for specialist quantity surveyor advice on the ADMC Report P17, P27
  • Nottingham Trent University and Vision West Nottinghamshire College, the Council's education partners on the ADMC Report P7, P11, P27
  • MHCLG, as the Government department responsible for Towns Fund delivery, with grant deadline extended to March 2028 Report P27, P70
  • Mazars, the Council's external auditors, kept informed of the Council's response Report P27
  • Local MPs Lee Anderson and Michelle Welsh, briefed by the Chief Executive Report P27
  • Businesses and residents of Ashfield, identified as the intended beneficiaries of the ADMC's economic and skills outcomes Report P12, P13

Timeline

  • 2021: Ashfield District Council secured £62.6 million from the Towns Fund for 16 regeneration projects including the ADMC Report P6
  • September 2023: Cabinet approved purchase of the ADMC site off Lowmoor Road Report P15
  • July 2024: Planning approval for the ADMC building secured Report P15
  • January 2025: Land purchase completed; YMD Boon awarded specialist advice contract via an officer delegated decision Report P15, P17
  • 3 February 2025: Executive Lead Member for Finance, Revenues and Benefits took decision to enter into contracts with Lindum Group Limited for ADMC build and Section 278 works Report P18
  • August 2025: Site preparation works began, including utilities, hedgerow removal and invasive species clearance Report P16
  • 9 January 2026: Chief Executive suspended all works on site after initial concerns raised by the Monitoring Officer Report P19
  • March 2026: Revised Memorandum of Understanding signed with MHCLG, extending Towns Fund spending deadline to March 2028 Report P27, P70
  • 31 March 2026: Monitoring Officer issued the Section 5A report to all Members Report P21
  • 13 April 2026: Cabinet considered the Monitoring Officer's Section 5A report and resolved to accept it, with alternative resolution options to be considered in private session Report P21
  • 20 April 2026: Cabinet to consider the outcome of the Council meeting on the additional capital funding Report P51
  • Early May 2026 (indicated): Construction contractor indicated works could recommence on site Report P51
  • June 2026: Chief Executive's Improvement Plan to be presented to Cabinet, then referred to Audit Committee for monitoring Report P36
  • August 2027 (indicated): Highways works targeted for completion Report P51
  • September 2027 (indicated): Building construction targeted for completion Report P51
  • October 2027 (indicated): Building fit-out and handover to operator targeted Report P51
  • March 2028: Extended deadline for spending the Towns Fund grant Report P27, P70

Plain English for the jargon

  • ADMC: Automated Distribution and Manufacturing Centre, the Council's flagship Towns Fund project creating a national centre of excellence for automation on Lowmoor Road
  • AITP: Ashfield Innovation and Technology Park, the proposed wider commercial development on around 26 acres around the ADMC
  • Section 5A report: A statutory report from a local authority's Monitoring Officer under Section 5A of the Local Government and Housing Act 1989 flagging possible breaches of law
  • Section 278 works: Highways works required under an agreement with the Highways Authority, in this case Nottinghamshire County Council, to enable access and junction improvements
  • SCAPE Regional Framework: A procurement framework used to award the construction contracts to Lindum Group Limited
  • ESPO Framework: A procurement framework used to award the specialist quantity surveyor contract via YMD Boon
  • MHCLG: Ministry of Housing, Communities and Local Government, responsible for the Towns Fund programme
  • LGR: Local Government Reorganisation, referenced in the context of project delivery before any reorganisation order
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCA.68

Resolved

RESOLVED that the report be received and accepted with full consideration of the alternative proposals for resolving the issues being considered in private session as outlined at agenda item 12. Reason: To ensure each alternative proposal for resolving the issues is considered fully by Members thus enabling an informed decision to be reached. Cabinet acknowledged that the report, as considered, was deemed to be of an urgent nature pursuant to Overview and Scrutiny Procedure Rule 13 and would not be subject to the call-in procedure.
Word for word from the decision Ashfield published for this meeting. Source: democracy.ashfield.gov.uk

Follow this further

Built from Ashfield's papers

What the report saysPro

Report to Cabinet

Alternative options considered

The Cabinet has no alternative option other than to consider a report presented by the Monitoring Officer under Section 5A of the Local Government and Housing Act 1989 within 21 days from the date the report is issued.

Cabinet may consider alternative proposals to resolve the issues raised by the Monitoring officer to those outlined in the report. A number of options are outlined in the report itself for consideration.

Detailed Information

AUTOMATED DISTRIBUTION AND MANUFACTURING CENTRE (ADMC)

Project Background

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
ADMC Funding and Contracts: Response to the Section 5A Local Government and Housing Act 1989 Report from the Monitoring OfficerReport 166 KB DownloadRead as text
PDF
SCJ ADMC FinalReport 226 KB Download

At this meeting

Whole meeting

Who was there

10 of 24 attended
SD
Councillor Samantha DeakinCommittee Member, present
VH
Councillor Vicki HeslopCommittee Member, present
TH
Councillor Tom HollisCommittee Member, present
CH
Councillor Christopher HuskinsonCommittee Member, present
RM
Councillor Rachel MaddenCommittee Member, present
AM
Councillor Andy MeakinCommittee Member, present
MR
Councillor Matthew RelfCommittee Member, present
HS
Councillor Helen-Ann SmithCommittee Member, present
JW
Councillor John WilmottCommittee Member, present
JZ
Councillor Jason ZadroznyChairman, present
MJ
Mike JoyOfficer, expected
JB
John BennettOfficer, in attendance

All 24 on the meeting page

On this subject at Ashfield

Search all
  1. ADMC Funding and Contracts - Response to the Section 5A Local Government and Housing Act 1989 Report from the Monitoring OfficerThis decision
  2. ADMC Funding and Contracts - Response to the Section 5A Local Government and Housing Act 1989 Report from the Monitoring OfficerDecided
  3. ADMC Funding and Contracts - Response to the Section 5A Local Government and Housing Act 1989 Report from the Monitoring OfficerNoted
  4. Automated Distribution and Manufacturing Centre (ADMC) and Ashfield Innovation and Technology Park (AITP) - Capital Programme FundingApproved
  5. ADMC Funding and Contracts - Response to the Section 5A Local Government and Housing Act 1989 Report from the Monitoring OfficerNoted

More from Ashfield Cabinet

All decisions
MeetingDecisionOutcome
27 Jul 2026 Local Government Reorganisation (Verbal Update and Q/A Session)RESOLVED that a) the information provided and the ongoing work being undertaken to support the transition programme, ... Noted Open
27 Jul 2026 Corporate Plan Year End Delivery 2025/26RESOLVED that a) the levels of delivery achieved against the Corporate Plan Priorities, as outlined in the report, be... Noted Open
27 Jul 2026 Corporate Risk Year End 2025/26 PositionRESOLVED that the current significant items on the Corporate Risk Register, as presented, be received and noted. Reas... Noted Open
27 Jul 2026 Update - Charitable Trust Issues at Lord Francis Park (Kirkby-in-Ashfield), Hucknall Leisure Centre and Titchfield Park (Hucknall)RESOLVED that a) the current position relating to Charitable Trust Issues at Lord Francis Park (Kirkby-In-Ashfield), ... Noted Open
27 Jul 2026 Appropriation of Land at Kingsway ParkRESOLVED that a) it be noted that the Secretary of State for Housing, Communities & Local Government granted consent ... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies