To 1. Agree the addition of £73.310M to the capital programme and the removal of scheme savings of £1.015M, and the removal of uncommitted Section 106 (developers’ contributions) schemes of £1.402M, which gives rise to a net increase of £70.893M to the overall capital programme as detailed in sections 4 to 5 and Appendix 2 of the report. 2. Approve the revised capital programme, which totals £132.907M (as detailed in paragraphs 2 to 8 and Appendix 1 of the report) and the associated use of resources. 3. Approve expenditure being incurred on capital schemes in accordance with the revised capital programme and the Financial Regulations. 4. Approve the slippage and rephasing as set out in section 6 and as detailed in Appendix 3 of the report. 5. Note that the capital programme remains fully funded up to 2025/26 based on the latest forecast of available resources. 6. Approve the Capital Programme Strategy detailed in Appendix 4 of the report.
Word for word from the decision Basingstoke and Deane published for this meeting.Source: democracy.basingstoke.gov.uk
CAPITAL PROGRAMME UPDATE AND STRATEGY REPORT FOR 2021/22 to 2025/26
Executive Director of Corporate Services (Section 151 Officer) Sue Cuerden
Report to Council – 28 February 2022 Ward(s): All Key Decision: No Appendix 1: Updated Capital Programme 2021/22 to 2025/26
Appendix 2: Additions and Savings To Current Approved Capital Programme Appendix 3: Current Capital Programme Rephasing And Slippage Appendix 4: Capital Programme Strategy
Cabinet Report February 2022 MTFS and Budget Update Papers relied on: 2022/23 to 2025/26 Recommendations:
It is recommended that Council:
1. Agrees the addition of £73.310M to the capital programme and the removal of scheme savings of £1.015M, and the removal of uncommitted Section 106 (developers’ contributions) schemes of £1.402M, which gives rise to a net increase of £70.893M to the overall capital programme as detailed in sections 4 to 5 and Appendix 2.
2. Approves the revised capital programme, which totals £132.907M (as detailed in paragraphs 2 to 8 and Appendix 1) and the associated use of resources.
3. Approves expenditure being incurred on capital schemes in accordance with the revised capital programme and the Financial Regulations.
4. Approves the slippage and rephasing as set out in section 6 and as detailed in Appendix 3.
5. Notes that the capital programme remains fully funded up to 2025/26 based on the latest forecast of available resources.
6. Approves the Capital Programme Strategy detailed in Appendix 4. Background, corporate objectives and priorities
This report provides an update on the capital programme and Capital Programme Strategy for 2021/22 to 2025/26 for Council approval. This report accords with the Council’s Policy and Budget Framework in that it sets out the Council’s capital expenditure plans which together with the revenue budget plans provide the resources necessary to deliver its objectives and support the Council Plan priorities. Glossary of terms
Term Definition LIF Local Infrastructure Fund AMP Asset Management Plan Works DFG Disabled Facilities Grant S106 Section 106 Developer Contributions CIL Community Infrastructure Levy NHB New Homes Bonus Ministry of Housing, Communities and Local Government MHCLG (now DLUHC) DLUHC Department for Levelling Up, Housing and Communities EIA’s Equality Impact Assessments CIPFA Chartered Institute of Public Finance and Accountancy MTFS Medium Term Financial Strategy CPB Capital Programme Board PMO Project Management Office 1 Executive Summary
1.1The Capital Programme Strategy provides an important link between the ambitions set out in the council’s longer term vision and Council Plan and the important investment in infrastructure that will help turn that vision into a reality.
1.2The strategy looks at how the council will finance, allocate and manage capital investment into services that are vital to supporting the development of a successful and vibrant place.
1.3The economic climate, in the wake of the ongoing pandemic and post- Brexit international trading conditions, remains challenging. However, the council is committed to investing now for the longer term. Financing that commitment is made possible by the council’s strong financial position and the council’s track record of strong financial resilience and management.
1.4Through this strategy the council will aim to make every capital investment count by co-ordinating and prioritising all available funding to achieve the council’s goals.
1.5The updated capital programme for 2021/22 to 2025/26 is £132.907M and includes new portfolio priority additions to the programme of £73.310M which are funded from council resources. In accordance with Financial Regulations, Council is recommended to approve the additions to the programme and for expenditure being incurred on schemes as set out in this programme.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Programme Outturn for 2025/26Council note: 1) That the actual capital spending in 2025/26 was £16.281M as shown in Table 3 of the report. This is ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.