Capital Programme Update and Strategy Report 2025/26 to 2029/30

Agreed Committee 1 paper

AI summaryBasingstoke and Deane Council approves a revised £129.276M capital programme to 2029/30, adding £31.140M of new schemes, removing £3.025M of underspends, and shifting £4.913M between years. The plan is fully funded from the council's own resources without external borrowing.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedTotalling £129.276M for 2025/26 to 2029/30
Money£129.276M total capital programmeNet increase of £28.115M from prior plan
What happens nextStrategy and CIL spend notedIncluding Infrastructure List for SCIL funding
Who it affectsResidents across the boroughThrough leisure, transport, housing and community schemes

What was decided

Council agreed to add £31.140M of new capital schemes, remove £3.025M of scheme underspends, giving a net increase of £28.115M to the overall capital programme, which now totals £129.276M. Report 1.6, 2.4

Council approved the rephasing of £4.913M of net spend from 2025/26 into future years and a virement of £0.031M from Parking and Access Schemes to the EV Charging Points scheme. Report 1.8, 1.9, 7.1, 8.1, 8.3

Council noted the programme remains fully funded from the council's own resources up to 2029/30 without external borrowing, and approved the Capital Programme Strategy with the Infrastructure List. Report 1.10

Why

Cabinet, senior officers and heads of service reviewed the existing programme for deliverability and proposed new priority additions funded from capital receipts, S106, CIL, grants and internal borrowing. Report 2.2, 2.3

The strategy links the council's longer-term vision and Council Plan priorities to infrastructure investment, and a new bidding process has identified CIL-funded projects for 2026/27 to 2029/30. Report 1.1, 1.2, 1.5, 9.10

Several schemes have been rephased because of procurement delays, planning requirements, leaseholder agreements, revised delivery schedules, or to align with Homes England funding for Manydown. Report 7.2

What happens next

The approved schemes will be incurred in accordance with the revised capital programme and the council's Financial Regulations.

The CIL Spending Report and Infrastructure List will be reviewed annually, with new SCIL bids assessed against the CIL Spend Protocol. Report 1.11, 9.10, 9.11

A future capital programme update will bring forward proposals for a replacement Westside Community Centre once cost and funding arrangements are worked up with partners. Report 1.6

The money

  • £31.140M New priority additions to the capital programme Report 1.6, 2.2
  • £3.025M Scheme underspends removed from the programme Report 6.1
  • £28.115M Net increase to the overall capital programme Report 1.6, 2.4, 3.1
  • £129.276M Revised total capital programme for 2025/26 to 2029/30 Report 1.6, 2.4
  • £4.913M Net spend rephased from 2025/26 into future years Report 1.8, 7.1
  • £5.292M Additions to rolling programmes Report 1.6, P19, 3.1
  • £25.848M Additions to other directorate schemes Report P20, 3.1
  • £12.249M Internal borrowing used in the programme Report 9.3, P121
  • £2.730M SCIL receipts for council-led schemes Report 1.11
  • £1.391M SCIL receipts made available to the Integrated Care Board Report 1.11
  • £14.482M Existing CIL receipts committed to the Leisure Park redevelopment Report 1.11, 9.10
  • £0.801M Saving from AMP Works (Various Sites) Report 6.4
  • £2.050M Saving from Basing View Car Parks
  • £0.125M Saving from Digital Programme Report 6.3

Options considered

  • Chosen: Add £31.140M of new capital schemes funded from council resources and external grants. Reflects new priority additions agreed by Cabinet, senior officers and heads of service to deliver Council Plan priorities Report 1.6, 2.2
  • Chosen: Remove £3.025M of scheme underspends from the programme. Reflects completed, scaled back or deferred elements of AMP Works, Basing View Car Parks and Digital Programme Report 6.1, 6.3, 6.4
  • Chosen: Rephase £4.913M of net spend from 2025/26 to later years. Aligns budgets with updated procurement, planning and delivery timelines across several schemes Report 1.8, 7.1
  • Chosen: Vire £0.031M from Parking and Access Schemes to EV Charging Points in 2025/26. Consolidates EV charging point funding in a single capital scheme Report 1.9, 8.1, 8.3
  • Rejected: Reclaim unspent Neighbourhood CIL from town and parish councils where funds have remained unspent for five years or more. Officers recommend not reclaiming funds that would have been repayable during 2025/26 Report 9.11, P132

Implications

  • Financial: The revised programme is fully funded from the council's own resources to 2029/30, with £12.249M of internal borrowing used and a £4.000M per annum revenue contribution to capital from the MTFS. Report 1.10, 9.3, 9.18
  • Financial: Any new schemes or cost increases before 2030/31 without new funding will need to be found from within the new capital programme to avoid further internal or external borrowing. Report 1.14
  • Legal: A new smoke extraction system is required at Eastlands car park to meet a legal fire safety requirement that Hampshire Fire and Rescue would rely on.
  • Equalities: Home Improvement Financial Assistance additions of £2.406M will support mandatory Disabled Facilities Grants and limited discretionary support for adaptations up to £0.030M to help disabled residents live independently.
  • Climate: Additions include EV charging points, sustainability works on operational properties, PV panels on investment properties to improve EPC ratings, and replacement council vehicles including an electric pickup. Report 4.1
  • Risk: Capital Risk Contingency budget is unchanged at £0.150M and is being rephased into 2026/27 to manage scheme delivery risks. Report 3.1, 8.1

Who and where

  • Residents of the borough receiving new or improved community, leisure, open space, play area and sports facilities Report 4.4, 4.7, 5.1, 5.6
  • Disabled residents needing home adaptations via the Disabled Facilities Grant
  • Patients of the Chineham Medical Practice following its expansion
  • Users of the Leisure Park through the redevelopment programme Report 1.11
  • Town and parish councils receiving neighbourhood CIL allocations Report 9.11, 9.13
  • Partners including the Integrated Care Board, Hampshire County Council, SNG, JLL and Hart District Council Report 1.11, 9.7, 9.16

Timeline

  • 2028/29: £29.488M of revised capital programme spend, including Basingstoke Golf Course / Hounsome Fields Community Centre and second year of Chineham Medical Practice expansion Report P22, 5.1
  • 2026-02-26: Council meeting approves the revised capital programme, rephasing, virements, CIL Spending Report and Capital Programme Strategy

Plain English for the jargon

  • CIL: Community Infrastructure Levy, a charge developers pay to fund local infrastructure
  • SCIL: Strategic Community Infrastructure Levy, the share of CIL retained by the council for priority community infrastructure
  • NCIL: Neighbourhood Community Infrastructure Levy, the share of CIL passed to town and parish councils or non-parished wards
  • S106: Section 106 developer contributions secured through planning obligations for site-specific infrastructure
  • MTFS: Medium Term Financial Strategy, the council's multi-year revenue and capital funding plan
  • MRP: Minimum Revenue Provision, the charge a council must make to repay capital expenditure over asset life
  • DBOM: Design, Build, Operate and Maintain contract approach used for the Leisure Park redevelopment
  • AMP: Asset Management Plan, the rolling programme of maintenance and replacement works for council property
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item89/25

Resolved

That Council 1. Agrees the addition of £31.140M to the capital programme and the removal of scheme underspends of £3.025M, which gives rise to a net increase of £28.115M to the overall capital programme as detailed in sections 4 to 6 and Appendix 2. 2. Approves the revised capital programme, which totals £129.276M (as detailed in sections 2 to 9 and Appendix 1) and the associated use of resources. 3. Approves expenditure being incurred on capital schemes in accordance with the revised capital programme and the Financial Regulations. 4. Approves the rephasing and scheme virements as set out in sections 7 and 8 and as detailed in Appendix 3. 5. Notes that the capital programme remains fully funded from the council’s own resources up to 2029/30 based on the latest forecast of available resources. 6. Notes the CIL Spending Report attached as Appendix 4. 7. Approves the Capital Programme Strategy shown as Appendix 5, which includes the council’s Infrastructure List shown as Annex 2.
Word for word from the decision Basingstoke and Deane published for this meeting. Source: democracy.basingstoke.gov.uk

Follow this further

Built from Basingstoke and Deane's papers

What the report saysPro

Report to Council

Executive summary

1.1The Capital Programme Strategy provides an important link between the ambitions set out in the council’s longer term vision and Council Plan and the important investment in infrastructure that will help turn that vision into a reality.

1.2The strategy looks at how the council will finance, allocate and manage capital investment into services that are vital to supporting the development of a successful and vibrant place.

1.3The economic climate remains challenging due to the recent period of higher interest rates and ongoing inflationary pressures. However, the council is committed to investing now for the longer term. Financing that commitment is made possible by the council’s strong financial position and the council’s track record of strong financial resilience and management.

1.4Through this strategy the council will aim to make every capital investment count by co-ordinating and prioritising all available funding to achieve the council’s goals.

1.5The Capital Programme Strategy has been updated in line with the revised capital programme and the Council Plan priorities and is detailed in Appendix 4.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme Update and Strategy Report 2025/26 to 2029/30Report 921 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

46 of 53 attended
CA
Councillor Chloe AshfieldCommittee Member, apologies
PB
Councillor Paul BashamCommittee Member, present
MB
Councillor Michael BlackberryCommittee Member, present
MB
Councillor Mike BoundCommittee Member, present
AB
Councillor Andrea BowesCommittee Member, present
SC
Councillor Samuel CarrCommittee Member, apologies
KC
Councillor Kevin ChatburnCommittee Member, present
MC
Councillor Marc ConnorCommittee Member, present
DC
Councillor David ConquestCommittee Member, present
RC
Councillor Richard CourtCommittee Member, present
OC
Councillor Onnalee CubittCommittee Member, present
SD
Councillor Sean DillowCommittee Member, present

All 53 on the meeting page

On this subject at Basingstoke and Deane

Search all
  1. Capital Programme Update and Strategy Report 2025/26 to 2029/30This decision
  2. Capital Programme Outturn for 2025/26Agreed
  3. Capital Programme Outturn 2025/26Noted
  4. Capital Programme Update and Strategy Report 2025/26 to 2029/30Noted
  5. Capital Programme Outturn 2024/25Agreed
  6. Capital Programme Outturn for 2024/25Noted

More from Basingstoke and Deane Council

All decisions
MeetingDecisionOutcome
16 Jul 2026 Capital Programme Outturn for 2025/26Council note: 1) That the actual capital spending in 2025/26 was £16.281M as shown in Table 3 of the report. This is ... Agreed Open
16 Jul 2026 Revenue Outturn Report 2025/26That Council approve: 1) The proposed transfer of the remaining outturn surplus of £1.51M after grant and income rese... Approved Open
16 Jul 2026 Treasury Management 2025/26 Annual ReportResolved that: The Treasury Management 2025/26 Annual Report be noted and the amendments to the Treasury Management S... Noted Open
16 Jul 2026 Old Basing and Lychpit Community Governance Review – Final RecommendationsResolved that: Council 1) Note the outcome of the consultations. 2) Agree the final recommendations for the Community... Noted Open
16 Jul 2026 Appointment of Interim S151 OfficerResolved : that Sarah Finch be appointed as Interim Section 151 Officer from 1 October 2026. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies