Basingstoke and Deane Borough Council
Cabinet, Thursday 9 July 2026 at 6.30pm

Capital Programme Outturn 2025/26

Noted Executive 1 paper

AI summaryCabinet recommends Council to note £16.281M of 2025/26 capital spending, an underspend of £1.085M, and approve £1.751M of scheme additions and two new schemes including Basing View Regeneration.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCapital outturn noted, additions and new schemes approved
Money£16.281M spent2025/26 capital spending, £1.085M under budget
What happens nextCouncil approval 16 July 2026Final decision to be made by full Council
Who it affectsAll wardsBorough-wide capital programme

What was decided

Cabinet recommends Council to note that actual capital spending in 2025/26 was £16.281M, £1.085M less than the latest agreed budget of £17.366M, and that the programme remains fully funded from the council's own resources up to 2029/30. Report P6, P11, P24, P31

Cabinet recommends Council to approve additions of £1.751M to existing schemes, and two new schemes: Basing View Regeneration (£1.100M in 2026/27, £3.800M in 2027/28, £2.200M in 2028/29) and War Memorial Park Skate Park Improvements (£0.033M in 2026/27). Report P11, P12, P13, P14, P15

Cabinet recommends Council to approve the revised capital programme for 2026/27 to 2029/30 as set out in Appendices 2 and 3, incorporating rephasing, slippage, and the new additions. Report P10, P16, P17, P70

Why

The 2025/26 outturn shows an underspend of £1.085M (6.25%), primarily due to the rephasing of £1.434M of expenditure across several schemes, partially offset by a net overspend of £0.349M on others. Report P5, P24, P32

Senior officers recognise the importance of monitoring the expected profile of expenditure to ensure accurate forecasting and effective planning of the council's cashflow requirements. Report P5

The additions and new schemes are funded from S106 developers' contributions, government grants, capital receipts from property disposals, and savings identified in the existing capital programme. Report P12, P14, P15, P86, P87, P88, P103

What happens next

Council will consider the recommendations at its meeting on 16 July 2026. Report P1, P146

Any ongoing potential savings identified from the final review of the capital programme will be built into the budget setting process for 2027/28. Report P127

The capital programme will continue to be monitored monthly with regular in-year reviews to manage delivery and cashflow risks. Report P133

The money

  • £16.281M Actual capital spending in 2025/26 Report P6, P24, P31
  • £17.366M Latest agreed capital programme budget for 2025/26 Report P6, P24, P31
  • £1.085M Underspend against budget in 2025/26 (6.25%) Report P5, P24, P31
  • £1.434M Rephased spend to/from future years Report P5, P24, P32
  • £0.349M Net scheme overspends in 2025/26 Report P24
  • £0.019M Addition to programme under delegated powers since February 2026 Report P8, P36, P37
  • £1.751M Additions to existing capital programme schemes Report P12, P26
  • £1.100M Basing View Regeneration budget 2026/27 Report P14, P28, P88
  • £3.800M Basing View Regeneration budget 2027/28 Report P14, P28, P88
  • £2.200M Basing View Regeneration budget 2028/29 Report P14, P28, P88
  • £0.033M War Memorial Park Skate Park Improvements budget 2026/27 Report P15, P29, P88

Options considered

  • Chosen: Note 2025/26 outturn and approve revised capital programme with additions and new schemes. Recommended by the Co-Leader and Cabinet Member for Finance and Property Report P5, P6, P11

Implications

  • Financial: The capital programme remains fully funded from the council's own resources up to 2029/30, based on the latest forecast of available resources. Report P11, P114, P115
  • Financial: Forecast balance of available general capital receipts, grants and contributions that could fund new future capital programme expenditure is £1.126M as at 31 March 2030. Report P115
  • Risk: Risks include partners not delivering to agreed timescales, availability of suppliers, lead times, and adverse weather. Some rephased schemes may face further delays. Report P133
  • Equalities: An Equality Impact Assessment concluded the Capital Programme will have no negative impact on protected characteristics groups, with proposed schemes mainly positive for communities. Report P136
  • Climate: The updated capital programme should have a positive carbon impact, with funding for improvement works resulting in improved energy efficiency and reduced carbon footprint. Report P139, P140
  • Legal: The Capital Outturn is reported in accordance with the Local Government Act 2003 and the Local Authority (Capital Finance and Accounting) (England) Regulations 2003. Report P129
  • Staffing: There are no HR implications arising from this report. Report P142

Who and where

  • All wards in the borough Report P4
  • Residents and businesses at Basing View (regeneration scheme) Report P103
  • Disabled residents receiving home improvement grants and adaptations Report P5, P65
  • Users of play areas across the borough Report P5, P91, P92
  • Households needing temporary accommodation and Afghan Resettlement Programme accommodation (Local Authority Housing Fund) Report P99
  • Users of skate park at War Memorial Park Report P106, P107

Timeline

  • February 2026: Capital programme last approved by Council Report P8, P20, P35
  • March 2026: Quarter three monitoring report considered by Cabinet Report P20, P144
  • 31 March 2026: End of 2025/26 financial year; outturn position Report P23
  • 9 July 2026: Cabinet considers the report Report P1, P146
  • 16 July 2026: Council considers the recommendations Report P1, P146

Plain English for the jargon

  • S106: Section 106 Developers' Contributions - money paid by developers towards infrastructure
  • CIL: Community Infrastructure Levy - a charge on new development to fund infrastructure
  • AMP: Asset Management Programme
  • MHCLG: Ministry of Housing, Communities & Local Government
  • HCC: Hampshire County Council
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item19/26

Resolved

Cabinet recommends Council to note: 1. That the actual capital spending in 2025/26 was £16.281M as shown in Table 3 of the report. This is £1.085M less than the latest agreed capital programme budget of £17.366M. The actual capital financing in 2025/26 is also shown in Table 3 of the report. 2. The 2025/26 significant outturn variations and explanations for them are shown in Appendix 1 and section 2 of the report. 3. The addition of £0.019M to the programme and rephasing since the last reported position in February 2026, under delegated powers, as shown in Table 4 and paragraph 2.6 of the report. 4. The impact of scheme variances for 2025/26 on future years’ capital expenditure has been included in the revised capital programme to 2029/30 aligned to Council Plan Priorities. 5. The revised capital programme for 2026/27 to 2029/30, adjusted for slippage and rephasing and additions contained within section 3 of the report and detailed in Appendices 2 and 3 of the report. 6. That the capital programme remains fully funded from the council’s own resources up to 2029/30, based on the latest forecast of available resources. Cabinet recommends Council to approve: 7. Additions to existing capital programme schemes of £1.751M as follows: · Play Area Improvements - £0.008M in 2026/27 funded from S106 Developers’ Contributions; · May Place House - £0.161M in 2026/27 funded from S106 Developers’ Contributions and £0.374M in 2026/27 funded from housing capital receipts; · Local Authority Housing Fund - £0.825M in 2026/27 and £0.202M in 2028/29 funded from government grant; and · Waste Water Treatment Works - £0.181M in 2026/27 funded from government grant. 8. Two new capital schemes and funding as follows: · Basing View Regeneration with a scheme budget of £1.100M in 2026/27, £3.800M in 2027/28 and £2.200M in 2028/29 funded from capital receipts realised from property disposals. · War Memorial Park Skate Park Improvements with a scheme budget of £0.033M in 2026/27 funded from savings identified in the existing capital programme. 9. The other capital programme changes shown in Appendix 2 of the report including 2025/26 outturn and future years rephasing and savings. 10. The revised capital programme for 2026/27 to 2029/30 as shown in Appendix 3 of the report and the capital programme financing as shown in section 4 of the report.
Word for word from the decision Basingstoke and Deane published for this meeting. Source: democracy.basingstoke.gov.uk

Follow this further

Built from Basingstoke and Deane's papers

What the report saysPro

Report to Cabinet

Cabinet / Council Date: 9 July 2026 / 16 July 2026 Subject: Capital Programme Outturn for 2025/26 Cllr Gavin James Co-Leader and Cabinet Report of: Member for Finance and Property

Lead Officer: Chief Finance Officer (Section 151 Officer) Adam Swain Tel No: (01256) 845515 Email: [email protected]

Contact Accountancy Manager and Deputy S151 Officer Sarah Finch Officer: Tel No: (01256) 845330 Email: [email protected]

Ward(s): All Key Yes Decision: Appendix 1: Capital Scheme Outturn Variations 2025/26 by Service Area Appendix 2: Proposed Capital Programme Changes for Approval Appendix 3: Revised Capital Programme 2026/27 to 2029/30

Exempt or Confidential Information It is considered that information contained within this report (and appendices) does not contain exempt information under the meaning of Schedule 12A of the Local Government Act 1972, as amended, and therefore can be made public. Foreword – Co-Leader and Cabinet Member for Finance and Property The 2025/26 outturn report shows capital expenditure of £16.281M, demonstrating the Council’s continued commitment to investing in facilities that matter to residents. This includes accelerated delivery of a number of property improvement schemes, home improvement grants and adaptations that support disabled residents to live independently, as well as investment in play areas. The report also identifies an overall underspend of £1.085M (6.25%) for the year. This is primarily due to the rephasing of £1.434M of expenditure across several schemes, partially offset by a net overspend of £0.349M on others. With a significant capital programme planned for future years, senior officers recognise the importance of understanding and monitoring the expected profile of expenditure. This is essential to ensure accurate forecasting of annual capital spend and to support effective planning of the Council’s cashflow requirements.

It is recommended that: Cabinet requests Council to note: 1. That the actual capital spending in 2025/26 was £16.281M as shown in Table 3. This is £1.085M less than the latest agreed capital programme budget of £17.366M. The actual capital financing in 2025/26 is also shown in Table 3.

2. The 2025/26 significant outturn variations and explanations for them are shown in Appendix 1 and section 2.

3. The addition of £0.019M to the programme and rephasing since the last reported position in February 2026, under delegated powers, as shown in Table 4 and paragraph 2.6.

4. The impact of scheme variances for 2025/26 on future years’ capital expenditure has been included in the revised capital programme to 2029/30 aligned to Council Plan Priorities.

5. The revised capital programme for 2026/27 to 2029/30, adjusted for slippage and rephasing and additions contained within section 3 of this report and detailed in Appendices 2 and 3.

6. That the capital programme remains fully funded from the council’s own resources up to 2029/30, based on the latest forecast of available resources. Cabinet requests Council to approve: 7. Additions to existing capital programme schemes of £1.751M as follows:

• Play Area Improvements - £0.008M in 2026/27 funded from S106 Developers’ Contributions (paragraph 3.8); • May Place House - £0.161M in 2026/27 funded from S106 Developers’ Contributions and £0.374M in 2026/27 funded from housing capital receipts (paragraphs 3.10 and 3.14); • Local Authority Housing Fund - £0.825M in 2026/27 and £0.202M in 2028/29 funded from government grant (paragraph 3.11); and • Waste Water Treatment Works - £0.181M in 2026/27 funded from government grant (paragraph 3.12).

8. Two new capital schemes and funding as follows:

• Basing View Regeneration with a scheme budget of £1.100M in 2026/27, £3.800M in 2027/28 and £2.200M in 2028/29 funded from capital receipts realised from property disposals as detailed in paragraph 3.13.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme Outturn 2025/26Report 521 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 8 attended
PH
Councillor Paul HarveyChair, present
OC
Councillor Onnalee CubittCommittee Member, apologies
GJ
Councillor Gavin JamesCommittee Member, present
LJ
Councillor Laura JamesCommittee Member, present
AK
Councillor Andy KonieczkoCommittee Member, present
JM
Councillor John McKayCommittee Member, present
KM
Councillor Kerry MorrowCommittee Member, apologies
CT
Councillor Chris TomblinCommittee Member, present

On this subject at Basingstoke and Deane

Search all
  1. Capital Programme Outturn 2025/26This decision
  2. Capital Programme Outturn for 2025/26Agreed
  3. Capital Programme Update and Strategy Report 2025/26 to 2029/30Agreed
  4. Capital Programme Update and Strategy Report 2025/26 to 2029/30Noted
  5. Capital Programme Outturn 2024/25Agreed
  6. Capital Programme Outturn for 2024/25Noted

More from Basingstoke and Deane Cabinet

All decisions
MeetingDecisionOutcome
8 Sep 2026 Motion referred from Council - Protecting South Ham And Buckskin Residents From Compulsory Purchase And Ensuring Full Democratic AccountabilityThat Cabinet note the motion referred by Council and agree to progress the actions within the motion in accordance wi... Noted Open
8 Sep 2026 Motion referred from Council - Increasing Biodiversity Net Gain Through the Local PlanThat Cabinet support the direction of travel set out in the motion and continue work through the Local Plan process t... Decided Open
8 Sep 2026 Recommendations from the Environment and Infrastructure Committee – Climate Emergency StrategyThat Cabinet endorse the recommendations of the Environment and Infrastructure Committee and incorporate them into th... Decided Open
8 Sep 2026 Local Plan - Next Steps1) Agree that work on a new local plan should proceed under the new planning system as set out in the Planning and Co... Agreed Open
8 Sep 2026 Regeneration Lettings Plans – Amendment to Housing Allocations Scheme1) Approve the Regeneration Priority Assessment Framework as at Appendix 2 of the report. 2) Authorise the Head of Le... Approved Open