Council: Note 1. That the actual capital spending in 2021/22 was £15.972M as shown in section 3 of the report. This is £5.126M less than the latest agreed capital programme budget of £21.098M and £5.115M less than the forecast outturn of £21.087M in quarter three. 2. The 2021/22 significant outturn variations and explanations for them are shown in Appendices 1 and 2 of the report. 3. The actual capital financing in 2021/22 as shown in paragraph 3.2 of the report. 4. The addition of £0.246M to the programme and rephasing since the last reported position in February 2022, under delegated powers, as shown in paragraph 4.3 of the report. 5. The impact of scheme variances for 2021/22 on future years’ capital expenditure has been reported to the Capital Programme Board and has been included in the revised capital programme to 2025/26 aligned to Council Plan Priorities and Outcomes. 6. The revised capital programme for 2022/23 to 2025/26, adjusted for slippage and rephasing and additions contained within section 4 of this report and detailed in Appendices 3 and 4 of the report. 7. That the capital programme remains fully funded up to 2025/26, based on the latest forecast of available resources. Approve: 8. The capital programme changes as detailed in Appendix 3 of the report including scheme virements detailed in paragraphs 4.15 to 4.19, relating to the Basing View (Plot W) and Basing View (Plot J – Norden House) (£0.166M in 2022/23), from Green Initiatives to CSPO Vehicles (£0.011M in 2022/23) and from Green Initiatives to a new capital scheme entitled Electric Vehicle (EV) Charging Points (£0.281M in 2022/23). 9. The proposed creation of a new capital scheme Public Art (S106) in relation to the provision of public art at the former Worting Infant School site to be funded from unspent S106 developers’ contributions collected for this purpose. 10. The revised capital programme for 2022/23 to 2025/26 as shown in Appendix 4 and the programme financing as shown in paragraph 5.1 of the report.
Word for word from the decision Basingstoke and Deane published for this meeting.Source: democracy.basingstoke.gov.uk
Capital Programme Outturn for 2021/22 Cllr John Izett – Cabinet Member for Finance and Property and Deputy Leader
Cabinet Report to Council Date 5 July 2022 14 July 2022 Ward(s): All Key Decision: No
Appendix 1: Capital Scheme Outturn Variations 2021/22 by Council Plan Priority Appendix 2: Significant Outturn Variance Explanations by Council Plan Priority Appendix 3: Proposed Programme Changes for Approval Appendix 4: Revised Capital Programme 2022/23 to 2025/26
Foreword - Cabinet Member for Finance and Property and Deputy Leader
The outturn report for 2021/22 shows a capital expenditure of £15.972M and demonstrates the strength of commitment of the council to invest in facilities that matter to residents. This includes, but is not limited to, sports and recreation improvements, adaptations that enable disabled people to live well at home, parking improvements and play area renovations.
However, the outturn also reports an underspend of £5.126M (24.30%) for the year, which is largely attributable to slippage (delayed spend). This level of slippage on the capital programme is disappointing and is being addressed. As the responsible portfolio holder, I have discussed these issues with the senior officer team and the measures required to materially improve programme management.
The economic climate, disruption and delays caused by the pandemic explains why a number of capital spends have been delayed until next financial year, but others are very specifically scheme related. Senior officers recognise that understanding the expected pattern of spend and reporting against this is paramount in properly forecasting annual capital spend, so that we are also able to understand the Council’s cashflow requirements. Also, and most importantly, this slippage affects the timing of delivery of council approved capital investments for the benefit of residents. The new Finance System introduced in April will allow for additional detail to be incorporated on how capital schemes are progressing to measure the expected activity and level of completion attached to each spend and this work is already underway. This will be reported to the regular Capital Programme Boards which can decide on action required depending on performance. Project Managers will be held more accountable for the performance of their projects.
It is recommended that:
Cabinet requests Council to note:
That the actual capital spending in 2021/22 was £15.972M as shown in section 3. This is £5.126M less than the latest agreed capital programme budget of £21.098M and £5.115M less than the forecast outturn of £21.087M in quarter three.
The 2021/22 significant outturn variations and explanations for them are shown in Appendices 1 and 2.
The actual capital financing in 2021/22 as shown in paragraph 3.2.
The addition of £0.246M to the programme and rephasing since the last reported position in February 2022, under delegated powers, as shown in paragraph 4.3.
The impact of scheme variances for 2021/22 on future years’ capital expenditure has been reported to the Capital Programme Board and has been included in the revised capital programme to 2025/26 aligned to Council Plan Priorities and Outcomes.
The revised capital programme for 2022/23 to 2025/26, adjusted for slippage and rephasing and additions contained within section 4 of this report and detailed in Appendices 3 and 4.
That the capital programme remains fully funded up to 2025/26, based on the latest forecast of available resources.
Cabinet requests Council to approve:
The capital programme changes as detailed in Appendix 3 including scheme virements detailed in paragraphs 4.15 to 4.19, relating to the Basing View (Plot W) and Basing View (Plot J – Norden House) (£0.166M in 2022/23), from Green Initiatives to CSPO Vehicles (£0.011M in 2022/23) and from Green Initiatives to a new capital scheme entitled Electric Vehicle (EV) Charging Points (£0.281M in 2022/23).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Programme Outturn for 2025/26Council note: 1) That the actual capital spending in 2025/26 was £16.281M as shown in Table 3 of the report. This is ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.