Resolved
That Council 1. Agree the addition of £18.693M to the capital programme and the removal of scheme savings of £0.213M, which gives rise to a net increase of £18.480M to the overall capital programme as detailed in sections 4 to 6 and Appendix 2 of the report (as amended). 2. Approve the revised capital programme, which totals £136.128M (as detailed in sections 2 to 8 and Appendix 1 of the report as amended) and the associated use of resources. 3. Approve expenditure being incurred on capital schemes in accordance with the revised capital programme and the Financial Regulations. 4. Approve the rephasing, slippage and scheme virements as set out in sections 7 and 8 and as detailed in Appendix 3 of the report. 5. Note that the capital programme remains fully funded up to 2026/27 based on the latest forecast of available resources. 6. Approve the Capital Programme Strategy detailed in Appendix 4 of the report.