Basingstoke and Deane Borough Council
Cabinet, Tuesday 8 July 2025 at 6.30pm

Capital Programme Outturn for 2024/25

Noted Executive 1 paper

Cabinet noted this item on Tuesday 8 July 2025. Below is the council's own wording, with the papers it was decided on.

Item17/25

Resolved

Cabinet requests Council to note: 1. That the actual capital spending in 2024/25 was £27.362M as shown in Table 3. This is £2.908M less than the latest agreed capital programme budget of £30.270M. The actual capital financing in 2024/25 is also shown in Table 3 of the report. 2. The 2024/25 significant outturn variations and explanations for them are shown in Appendix 1 and section 2 of the report. 3. The addition of £0.014M to the programme and rephasing since the last reported position in February 2025, under delegated powers, as shown in Table 4 and paragraphs 2.5 to 2.7 of the report. 4. The impact of scheme variances for 2024/25 on future years’ capital expenditure has been included in the revised capital programme to 2028/29 aligned to Council Plan Priorities. 5. The revised capital programme for 2025/26 to 2028/29, adjusted for slippage and rephasing and additions contained within section 3 of the report and detailed in Appendices 2 and 3 of the report. 6. That the capital programme remains fully funded from the council’s own resources up to 2028/29, based on the latest forecast of available resources. Cabinet requests Council to approve: 7. Additions to the capital programme of £0.192M shown in Appendix 2 and as detailed in paragraphs 3.17 and 3.18 of the report as follows: · Open Space Improvements - £0.016M in 2025/26 funded from S106 Developers’ Contributions · Replacement/refurbishment of community facilities - £0.115M funded from S106 Developers’ Contributions · Home improvement assistance fund - £0.061M in 2025/26 funded from additional external grant funding 8. A new capital scheme named Capital Contingency Fund with a scheme budget of £0.150M in 2025/26 funded from a draw from the General Reserve For Capital Purposes as detailed in paragraph 3.19. of the report. 9. The other capital programme changes shown in Appendix 2 including 2024/25 outturn and future years rephasing, savings and a scheme virement detailed in paragraph 3.24 of the report, relating to additional works at the Down Grange BMX track (£0.040M in 2025/26). 10. The revised capital programme for 2025/26 to 2028/29 as shown in Appendix 3 and the capital programme financing as shown in section 3 of the report.
Word for word from the decision Basingstoke and Deane published for this meeting. Source: democracy.basingstoke.gov.uk

Follow this further

Built from Basingstoke and Deane's papers

What the report saysPro

Report to Cabinet

Cabinet / Council Date: 8 July 2025 / 17 July 2025 Subject: Capital Programme Outturn for 2024/25 Cllr Gavin James Co-Leader and Cabinet Report of: Member for Finance and Property

Lead Officer: Chief Finance Officer (Section 151 Officer) Adam Swain Tel No: (01256) 845515 Email: [email protected]

Contact Accountancy Manager (Deputy S151 Officer) Sarah Finch Officer: Tel No: (01256) 845330 Email: [email protected]

Ward(s): All Key Yes Decision: Capital Scheme Outturn Variations 2024/25 by Council Plan Appendix 1: Priority Appendix 2: Proposed Capital Programme Changes for Approval Appendix 3: Revised Capital Programme 2025/26 to 2028/29

Exempt or Confidential Information It is considered that information contained within this report (and appendices) does not contain exempt information under the meaning of Schedule 12A of the Local Government Act 1972, as amended, and therefore can be made public. Foreword – Co-Leader and Cabinet Member for Finance and Property The outturn report for 2024/25 shows capital expenditure of £27.362M and demonstrates that the council is committed to invest in facilities that matter to residents. This includes advanced spending on some property related improvement schemes, home improvement financial assistance and adaptations which enables disabled people to live well at home and play areas. However, the outturn also reports an underspend of £2.908M (9.61%) for the year, which is attributable to rephased spend of £2.222M relating to a number of schemes and net savings of £0.686M across a range of schemes. With a significant capital programme in future years, senior officers recognise that understanding the expected pattern of spend and reporting against this is paramount in properly forecasting annual capital spend, so that we are also able to understand the Council’s cashflow requirements.

It is recommended that: Cabinet requests Council to note: 1. That the actual capital spending in 2024/25 was £27.362M as shown in Table 3. This is £2.908M less than the latest agreed capital programme budget of £30.270M. The actual capital financing in 2024/25 is also shown in Table 3. 2. The 2024/25 significant outturn variations and explanations for them are shown in Appendix 1 and section 2. 3. The addition of £0.014M to the programme and rephasing since the last reported position in February 2025, under delegated powers, as shown in Table 4 and paragraphs 2.5 to 2.7. 4. The impact of scheme variances for 2024/25 on future years’ capital expenditure has been included in the revised capital programme to 2028/29 aligned to Council Plan Priorities. 5. The revised capital programme for 2025/26 to 2028/29, adjusted for slippage and rephasing and additions contained within section 3 of this report and detailed in Appendices 2 and 3. 6. That the capital programme remains fully funded from the council’s own resources up to 2028/29, based on the latest forecast of available resources. Cabinet requests Council to approve: 7. Additions to the capital programme of £0.192M shown in Appendix 2 and as detailed in paragraphs 3.17 and 3.18 as follows: • Open Space Improvements - £0.016M in 2025/26 funded from S106 Developers’ Contributions • Replacement/refurbishment of community facilities - £0.115M funded from S106 Developers’ Contributions • Home improvement assistance fund - £0.061M in 2025/26 funded from additional external grant funding

8. A new capital scheme named Capital Contingency Fund with a scheme budget of £0.150M in 2025/26 funded from a draw from the General Reserve For Capital Purposes as detailed in paragraph 3.19.

9. The other capital programme changes shown in Appendix 2 including 2024/25 outturn and future years rephasing, savings and a scheme virement detailed in paragraph 3.24, relating to additional works at the Down Grange BMX track (£0.040M in 2025/26).

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme Outturn for 2024/25Report 446 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 8 attended
PH
Councillor Paul HarveyChair, present
OC
Councillor Onnalee CubittCommittee Member, present
GJ
Councillor Gavin JamesCommittee Member, present
LJ
Councillor Laura JamesCommittee Member, present
AK
Councillor Andy KonieczkoCommittee Member, present
JM
Councillor John McKayCommittee Member, present
KM
Councillor Kerry MorrowCommittee Member, present
CT
Councillor Chris TomblinCommittee Member, apologies

On this subject at Basingstoke and Deane

Search all
  1. Capital Programme Outturn for 2024/25This decision
  2. Capital Programme Outturn for 2025/26Agreed
  3. Capital Programme Outturn 2025/26Noted
  4. Capital Programme Update and Strategy Report 2025/26 to 2029/30Agreed
  5. Capital Programme Update and Strategy Report 2025/26 to 2029/30Noted
  6. Capital Programme Outturn 2024/25Agreed

More from Basingstoke and Deane Cabinet

All decisions
MeetingDecisionOutcome
8 Sep 2026 Motion referred from Council - Protecting South Ham And Buckskin Residents From Compulsory Purchase And Ensuring Full Democratic AccountabilityThat Cabinet note the motion referred by Council and agree to progress the actions within the motion in accordance wi... Noted Open
8 Sep 2026 Motion referred from Council - Increasing Biodiversity Net Gain Through the Local PlanThat Cabinet support the direction of travel set out in the motion and continue work through the Local Plan process t... Decided Open
8 Sep 2026 Recommendations from the Environment and Infrastructure Committee – Climate Emergency StrategyThat Cabinet endorse the recommendations of the Environment and Infrastructure Committee and incorporate them into th... Decided Open
8 Sep 2026 Local Plan - Next Steps1) Agree that work on a new local plan should proceed under the new planning system as set out in the Planning and Co... Agreed Open
8 Sep 2026 Regeneration Lettings Plans – Amendment to Housing Allocations Scheme1) Approve the Regeneration Priority Assessment Framework as at Appendix 2 of the report. 2) Authorise the Head of Le... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies