CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Blaby District Council
Audit Committee, Wednesday 27 September 2006

Internal Audit Progress Report July-September 2006

Noted Finance 4 papers

Audit Committee noted this item on Wednesday 27 September 2006. Below is the council's own wording, with the papers it was decided on.

Item198

Resolved

DECISION That the report of the Internal Audit and Risk Manager - Internal Audit Progress Report July-September 2006 be noted.
Word for word from the decision Blaby published for this meeting. Source: democracy.blaby.gov.uk

Follow this further

Built from Blaby's papers

What the report saysPro

Report to Audit Committee

Purpose of report

1.1To review the work of the Internal Audit section for the second quarter of the financial year 2006/2007.

Recommendation

2.1To note the Internal Audit report for the second quarter of the financial year 2006/2007.

3. Reason for Decision Recommended

3.1To enable the Audit Committee to monitor the work of the Internal Audit Section.

4. Forward Plan

4.1Not Applicable

5. Key Decision

5.1Not applicable

6. Matter(s) for Consideration

Introduction

6.1This is a progress report on the Internal Audit plan for the period July to September 2006 (Appendix A) and audit reports that have been issued (Appendix B).

D:\moderngov\data\published\Intranet\C00000301\M00001472\AI00003807\AuditCommitteeReportQ22006070.d oc Revised Audit Plan July – September 2006

6.2Due to pressures on housing staff, two planned audits in that service have been carried forward to the next quarter ending December 2006. This has allowed for three other unplanned audits to be undertaken – see Appendix A.

Summary of Audit report findings and recommendations

6.3Appendix B lists final reports issued during the quarter, an executive summary and number of recommendations made and accepted. The following reports are brought to the attention of members for information:

Special investigation in to Telephone charges -report ref 06/13

6.4Internal Audit was requested to investigate telephone calls costing £147 consisting of a significant number of international calls and some inappropriate premium rate calls. These calls appeared to be made from a BT telephone line (at the Depot). However upon investigation it was found that the line is linked to an alarm system for which no charges should have been incurred and thus it appeared that someone had hacked into the Council’s telephone system. Following an inconclusive investigation by BT, all costs previously paid have been refunded and BT will monitor use of the line in question.

Best Value Performance Indicators (BVPIs) / Data Quality checks - report ref. 06/12, 06/13

6.5As part of the managed audit arrangements with the Council’s external auditors (PWC), Internal Audit undertakes 100% verification checks on summary BVPI data submitted by Services, This is done to ensure accuracy of the data before it is published and submitted to the Audit Commission, who then use it to benchmark the performance of the Council. The results of the audit of BVPI data summary returns established that the accuracy level averaged only 62%. Valuable management time was required to get the returns “right”, before they could be published. The importance of “getting it right first time” will be addressed as part of routine training planned well in advance of BVPI data submissions for 2006/07. Further random testing of data collection will be incorporated into the remainder of the Internal Audit plan for 2006/07.

6.6More detailed data quality test checking of prime records, from which summary data is made up in respect of certain key BVPI’s, was undertaken in three Services, Housing, Waste Management and Human Resources. This further work revealed that, whilst there were no issues arising from data quality from Housing and Waste Management, there were fundamental weaknesses in data capture within Human Resources e.g. sickness absence data. In the short

D:\moderngov\data\published\Intranet\C00000301\M00001472\AI00003807\AuditCommitteeReportQ22006070.d oc term, Internal Audit and Performance have provided assistance to management in Human Resources to set up accurate spreadsheets to capture data.

6.7In the longer term (late 2006/07) the solution to maintaining accurate data in this area, lies in the proposed purchase of an integrated Human Resources and Payroll system. This solution will reduce significantly the incidence of human error and consequently raise the level of confidence in the data produced.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Q2Appendix A 12 KB Download
PDF
Q 2Appendix B 26 KB Download
PDF
Q2Appendix C 10 KB Download
PDF
Internal Audit Progress Report July-September 2006Report 41 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 12 attended
KD
Councillor K. D. ColesMember, present
JA
Councillor J. A. DolbyMember, present
JO
Councillor J. O. HudsonChairman, present
JK
Councillor J. KenneyMember, present
BM
Councillor B. M. ParkinsMember, present
JS
Councillor J. SpringthorpeMember, present
JL
Councillor J. L. WeatherstoneMember, present
JH
Mr J.L. HoldenOfficer, in attendance
GP
Mr G. ProctorOfficer, in attendance
MS
Mr M SpencerOfficer, in attendance
TW
Ms T. WatsonOfficer, in attendance
DJ
Diane JohnsonOfficer, in attendance

On this subject at Blaby

Search all
  1. Internal Audit Progress Report July-September 2006This decision
  2. Internal Audit Partnership ArrangementsApproved
  3. Shared Internal Audit ServiceApproved
  4. Recommendations of the Cabinet Executive - Shared Internal Audit ServiceApproved
  5. Shared Internal Audit ServiceApproved
  6. Internal Audit Progress Report October - December 2010Decided

More from Blaby Audit Committee

All decisions
MeetingDecisionOutcome
30 Jun 2011 Introduction to Audit and the Audit CommitteeIt was agreed that future dates for training for Members of the Audit Committee would be sought. Agreed Open
21 Dec 2010 Annual Audit LetterDECISION That the produced by PriceWaterhouseCooopers be acknowledged and its contents accepted. Reason: It is approp... Decided Open
21 Dec 2010 Use of ResourcesDECISION That the ‘’ assessment and the progress the Council has made be accepted. Reason: This assessment was carrie... Agreed Open
21 Dec 2010 Internal Audit Progress Report October - December 2010DECISION That the Internal Audit report for the third quarter of the 2010/2011 financial year be accepted. Reason: To... Decided Open
21 Dec 2010 Risk Management ReportDECISION That the Risk Management report be accepted. Reason: To enable the Audit Committee to monitor the management... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies