Resolved
DECISION That the report of the Internal Audit and Risk Manager - Risk Management Report for the second quarter of the financial year 2006/2007 be noted.
Audit Committee noted this item on Wednesday 27 September 2006. Below is the council's own wording, with the papers it was decided on.
Resolved
DECISION That the report of the Internal Audit and Risk Manager - Risk Management Report for the second quarter of the financial year 2006/2007 be noted.
1.1To review the management of risks for the second quarter of the financial year 2006/2007.
2.1To note the Risk Management report for the second quarter of the financial year 2006/2007.
3. Reason for Decision Recommended
3.1To enable the Audit Committee to monitor management of risks facing the Council.
4. Forward Plan
4.1Not Applicable
5. Key Decision
5.1Not applicable
6. Matter(s) for Consideration
Introduction
6.1Good corporate governance requires independent assurance and reporting on the effectiveness of risk management arrangements across the organisation. The Terms of Reference for the Audit and Risk Committee state that one of its roles is “To monitor the effective
D:\moderngov\data\published\Intranet\C00000301\M00001472\AI00003817\RiskManreporttoAuditCommitteeRe portQ22006070.doc development and operation of risk management”. Prior to this report, progress on implementation of risk management arrangements formed part of the general Internal Audit report (formerly to Cabinet and since May 2006 to the Audit and Risk Committee).
6.2However, in order to provide more Member focus on this particular aspect of corporate governance, the Risk Management Group (RMG) considered that this would be better achieved by issuing a separate report dealing with risk management issues. The following is a progress report on the arrangements for the management of risks for the period July to September 2006.
Risk Management Strategy – Action Plan
6.3Cabinet approved a Revised Risk Management Policy/Strategy in February 2006. The Strategy included an Action Plan (Appendix A), implementation of which, is monitored by the Risk Management Group that meets quarterly. There are six actions in the Action Plan and implementation of all six actions is being addressed. There are three actions which will be ongoing :
Embedding risk management (Action 2) 6.4 Embedding risk management into the business process involves a cultural change in individuals thinking and approach to business processes. This can be enabled through risk awareness training and mentoring and can be evidenced in a formal way e.g. identification of risks in business planning documents, reports to senior management as well as in a risk register. Progress along these lines is being made at a corporate level (see Partnerships below) but to a lesser degree at the operational (Service) level.
6.5This gap was recently evidenced following poor feedback from Services to a request for an update to the RMG on potential High risks in each Service. Two Services, Finance and Community Development have still yet to establish what their operational (business) risks are. Although 8 risk owners, out of a possible 14, did supply an update report, this was received only as a result of prompting and generally there was little evidence to suggest that Medium risks had been reviewed.
6.6An opportunity to bring risk registers up to date, in respect of High risks, is being taken at a forthcoming risk management workshop for officers which is planned for October. Also, active consideration is being given by the RMG to the purchase of a web based risk management system which will improve ownership and management of risks at a Service level, as well as, making it easier, at a corporate level, to monitor progress in the identification and management of risks across the Council. A demonstration of one such system will be given to risk owners at the October workshop.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Risk Management Report July-September 2006Report | 43 KB | DownloadRead as text |
PDF |
Risk Register 2006 for Audit Com SeptReport | 56 KB | Download |
PDF |
Risk man App A Sept 2006Appendix | 22 KB | Download |
Follow Audit Committee at Blaby and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 30 Jun 2011 | Introduction to Audit and the Audit CommitteeIt was agreed that future dates for training for Members of the Audit Committee would be sought. | Agreed | Open |
| 21 Dec 2010 | Annual Audit LetterDECISION That the produced by PriceWaterhouseCooopers be acknowledged and its contents accepted. Reason: It is approp... | Decided | Open |
| 21 Dec 2010 | Use of ResourcesDECISION That the ‘’ assessment and the progress the Council has made be accepted. Reason: This assessment was carrie... | Agreed | Open |
| 21 Dec 2010 | Internal Audit Progress Report October - December 2010DECISION That the Internal Audit report for the third quarter of the 2010/2011 financial year be accepted. Reason: To... | Decided | Open |
| 21 Dec 2010 | Risk Management ReportDECISION That the Risk Management report be accepted. Reason: To enable the Audit Committee to monitor the management... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.