Risk Management Report July-September 2006

Noted Finance 3 papers

Audit Committee noted this item on Wednesday 27 September 2006. Below is the council's own wording, with the papers it was decided on.

Item199

Resolved

DECISION That the report of the Internal Audit and Risk Manager - Risk Management Report for the second quarter of the financial year 2006/2007 be noted.
Word for word from the decision Blaby published for this meeting. Source: democracy.blaby.gov.uk

Follow this further

Built from Blaby's papers

What the report saysPro

Report to Audit Committee

Purpose of report

1.1To review the management of risks for the second quarter of the financial year 2006/2007.

Recommendation

2.1To note the Risk Management report for the second quarter of the financial year 2006/2007.

3. Reason for Decision Recommended

3.1To enable the Audit Committee to monitor management of risks facing the Council.

4. Forward Plan

4.1Not Applicable

5. Key Decision

5.1Not applicable

6. Matter(s) for Consideration

Introduction

6.1Good corporate governance requires independent assurance and reporting on the effectiveness of risk management arrangements across the organisation. The Terms of Reference for the Audit and Risk Committee state that one of its roles is “To monitor the effective

D:\moderngov\data\published\Intranet\C00000301\M00001472\AI00003817\RiskManreporttoAuditCommitteeRe portQ22006070.doc development and operation of risk management”. Prior to this report, progress on implementation of risk management arrangements formed part of the general Internal Audit report (formerly to Cabinet and since May 2006 to the Audit and Risk Committee).

6.2However, in order to provide more Member focus on this particular aspect of corporate governance, the Risk Management Group (RMG) considered that this would be better achieved by issuing a separate report dealing with risk management issues. The following is a progress report on the arrangements for the management of risks for the period July to September 2006.

Risk Management Strategy – Action Plan

6.3Cabinet approved a Revised Risk Management Policy/Strategy in February 2006. The Strategy included an Action Plan (Appendix A), implementation of which, is monitored by the Risk Management Group that meets quarterly. There are six actions in the Action Plan and implementation of all six actions is being addressed. There are three actions which will be ongoing :

Embedding risk management (Action 2) 6.4 Embedding risk management into the business process involves a cultural change in individuals thinking and approach to business processes. This can be enabled through risk awareness training and mentoring and can be evidenced in a formal way e.g. identification of risks in business planning documents, reports to senior management as well as in a risk register. Progress along these lines is being made at a corporate level (see Partnerships below) but to a lesser degree at the operational (Service) level.

6.5This gap was recently evidenced following poor feedback from Services to a request for an update to the RMG on potential High risks in each Service. Two Services, Finance and Community Development have still yet to establish what their operational (business) risks are. Although 8 risk owners, out of a possible 14, did supply an update report, this was received only as a result of prompting and generally there was little evidence to suggest that Medium risks had been reviewed.

6.6An opportunity to bring risk registers up to date, in respect of High risks, is being taken at a forthcoming risk management workshop for officers which is planned for October. Also, active consideration is being given by the RMG to the purchase of a web based risk management system which will improve ownership and management of risks at a Service level, as well as, making it easier, at a corporate level, to monitor progress in the identification and management of risks across the Council. A demonstration of one such system will be given to risk owners at the October workshop.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Risk Management Report July-September 2006Report 43 KB DownloadRead as text
PDF
Risk Register 2006 for Audit Com SeptReport 56 KB Download
PDF
Risk man App A Sept 2006Appendix 22 KB Download

At this meeting

Whole meeting

Who was there

7 of 12 attended
KD
Councillor K. D. ColesMember, present
JA
Councillor J. A. DolbyMember, present
JO
Councillor J. O. HudsonChairman, present
JK
Councillor J. KenneyMember, present
BM
Councillor B. M. ParkinsMember, present
JS
Councillor J. SpringthorpeMember, present
JL
Councillor J. L. WeatherstoneMember, present
JH
Mr J.L. HoldenOfficer, in attendance
GP
Mr G. ProctorOfficer, in attendance
MS
Mr M SpencerOfficer, in attendance
TW
Ms T. WatsonOfficer, in attendance
DJ
Diane JohnsonOfficer, in attendance

On this subject at Blaby

Search all
  1. Risk Management Report July-September 2006This decision
  2. Risk Management StrategyApproved
  3. Risk Management Strategy 2023 - 2026Approved
  4. Risk Management Strategy 2019 - 2022Approved
  5. Risk Management Strategy 2015-18Approved
  6. Risk Management ReportDecided

More from Blaby Audit Committee

All decisions
MeetingDecisionOutcome
30 Jun 2011 Introduction to Audit and the Audit CommitteeIt was agreed that future dates for training for Members of the Audit Committee would be sought. Agreed Open
21 Dec 2010 Annual Audit LetterDECISION That the produced by PriceWaterhouseCooopers be acknowledged and its contents accepted. Reason: It is approp... Decided Open
21 Dec 2010 Use of ResourcesDECISION That the ‘’ assessment and the progress the Council has made be accepted. Reason: This assessment was carrie... Agreed Open
21 Dec 2010 Internal Audit Progress Report October - December 2010DECISION That the Internal Audit report for the third quarter of the 2010/2011 financial year be accepted. Reason: To... Decided Open
21 Dec 2010 Risk Management ReportDECISION That the Risk Management report be accepted. Reason: To enable the Audit Committee to monitor the management... Decided Open