DECISION That the revised General Fund Revenue Account budget of £10,110,616 for 2008/2009 financial year be approved. Reason: As part of the Council’s budget monitoring arrangements a review is carried out of performance against the original approved General fund Revenue Account budget as the end of the financial year approaches. Any significant issues and estimated outturn variances are brought to the attention of the Cabinet Executive for approval.
Word for word from the decision Blaby published for this meeting.Source: democracy.blaby.gov.uk
1.1To set out for consideration and approval the revised General Fund Revenue Account budget for 2008/2009 financial year.
Recommendation
2.1That the revised General Fund Revenue Account budget of £10,110,616 for 2008/2009 financial year be approved.
3. Reason for Decision Recommended
3.1As part of the Council’s budget monitoring arrangements a review is carried out of performance against the original approved General fund Revenue Account budget as the end of the financial year approaches. Any significant issues and estimated outturn variances are brought to the attention of the Cabinet Executive for approval.
4. Forward Plan
4.1Forward Plan Reference Number 05/08 (831).
5. Key Decision
5.1Yes.
6. Matters for Consideration
6.1Introduction
As part of the Council’s overall arrangements for good financial governance formal revised estimates are produced each year in respect of the whole of the General Fund Revenue Account budget. This formal review is required in order to ascertain whether there are any significant adverse variances which may require corrective action and to seek approval for additional funding if required. It should be noted that the revised budget reflects the forecast position at an appropriate point in time and may not be indicative of the final outturn which will be dependant upon the performance over the full twelve months of the financial year.
The revised budget complements the more detailed regular portfolio budget monitoring reports which highlight specific variances throughout the course of the year and the cost centre specific review which is carried out at the half year stage.
6.2Cabinet Executive November 2008
At your meeting on the 3rd November 2008 a number of specific expenditure issues were brought to your attention in relation to the 2008/2009 budgets. These matters were as follows:-
One off items: Planning Appeals 54,000 Redundancy costs 79,500 Pension costs 19,800
Income Streams
Shortfall ( net) 43,000
Less
Expenditure savings
Establishment costs 125,000 Other costs 93,801
TOTAL 120,257
The net cumulative effect of the above issues on the General fund revenue budget at that time was a forecast increase in expenditure of £120,257 over the approved base budget.
This estimated variance was to be funded using arrangements set out at the beginning of the financial year to allow the in-year utilisation of balances within certain pre-defined parameters. This required a total contribution of £120,257 from the General Fund balances.
6.3Revised Budget
Due to the changes in both the management structure and the Cabinet Executive portfolio responsibilities which have taken place during the course of the current financial year, it has been decided to restrict the revised budget review to a high level exercise focussing on the key risk areas such as income streams. Because of the structure changes valid comparisons at the detailed cost centre level for all expenditure items have not been possible. Those issues previously identified at the meeting in November have also been reflected in the revised budget.
Income Streams
In my report in November I highlighted the significant reductions in a number of the Council’s key income streams as a result of the current economic downturn.
The table below sets out the original, half yearly revised and forecast outturn figures for these streams based on performance up until the end of December.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.