DECISIONS That delegated authority be granted to the Director of Operations, in consultation with the Portfolio Holder and Legal Services Manager to negotiate a new lease agreement, including terms and a plan between the Council and Enderby Band Organisation in respect of their new location on similar terms to the existing agreement. That additional capital expenditure in the current financial year to maximum of £33,000 to facilitate the relocation of Enderby Band Organisation’s (EBO) building at the Pavillion be approved. Reason: To facilitate the relocation of the Band and enable the site to be used for the construction of the Children’s Centre.
Word for word from the decision Blaby published for this meeting.Source: democracy.blaby.gov.uk
1.1To seek approval for the expenditure necessary to relocate the Enderby Band building at the Pavilion.
Recommendations
2.1To approve additional capital expenditure in the current financial year to a maximum of £33,000 to facilitate the relocation of the Enderby Band Organisation’s (EBO) building at the Pavilion
2.2To permit the EBO to use the Council Chamber or Brooks Room for rehearsals during the period of relocation when not required for other purposes.
Recommendation to Council
2.3To authorise a new lease agreement to be finalised between the Council and the Enderby Band Organisation in respect of their new location on similar terms to the existing agreement.
3. Reason for Decisions Recommended
3.1To facilitate the relocation of the band and enable the site to be used for the construction of the Children’s Centre.
4. Forward Plan
4.1The matter has become apparent since the publication of the Forward Plan and because of the need to commence the construction works on site it is impracticable to defer the decisions on this report, however these are not key decisions. 5. Key Decision
5.1No.
6. Matters for Consideration
6.1As part of a nationwide initiative to support parents and young children the County Council have been building Children’s Centres throughout the County. The centre for this District is planned to be built at the Pavilion (subject to the necessary consents) in order to take advantage of the facilities at the Pavilion which will be available during the day and the synergies that can develop with the voluntary sector (VABD) and our own sports and leisure staff who are also based there. Several options for constructing the centre have been considered and all have foundered due to the restrictions of the site or the existing building. The only viable location for the new building is unfortunately in the area currently occupied by the Enderby Band (EBO) building.
6.2The EBO have been on the site for several years and have a lease that allows them to occupy the site for £50 per year. The lease allows the Council to terminate the lease by giving 6 months notice to the EBO. There is no provision under the terms of the lease for any compensation. The EBO themselves are a considerable asset to the community currently running 5 bands and involving people of all ages. The objective has therefore been to continue to support the EBO to undertake the necessary move and minimise the impact upon them. To this end discussions have been on-going with their secretary and trustees and culminated in a meeting at the Pavilion on the 23 June at which the relevant portfolio members were present together with the leader.
6.3It is acknowledged that the EBO have to relocate through no fault of their own and have nothing to gain from the move – this is entirely necessary for the construction of the Children’s Centre. As such it is felt that the Council should undertake to relocate the building and re-connect services, etc. so that the band are able to continue to enjoy the same facilities that they have at present. This is subject to planning consent being obtained which also could permit other “desirable” additional facilities such as security fencing, external lighting or CCTV, however if these are to be provided they would have to be funded by the EBO.
6.4Professional advice has been sought concerning the viability of dismantling and reconstructing the existing building and estimates for this work obtained. This is considered to be viable and the costs of the work are estimated at £33,000.
6.5No budgetary provision has been made for this cost in the current year. It is however proposed to fund this expenditure from capital income and the leisure centre renewals fund.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Croft Conservation Area DesignationDECISION That the designation of a Conservation Area, as identified on the Croft Conservation Area, as identified on ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.