DECISIONS That the Planning Enforcement Policy (attached at Appendix 1 to the report of the Environmental Protection Group Manager) be approved. 2. That delegated authority be granted to the Environmental Protection Group Manager in consultation with the Portfolio Holder to make amendments to the service standards and performance standards provided at Annex A to the Policy. Reasons: 1. The integrity of the Planning process depends on the Council’s readiness to take effective enforcement action when it is appropriate. Fair and effective planning enforcement is important to protect and enhance the quality of the District’s built and natural environment. 2. The Policy defines priorities so that resources can be put to best use, making sure that regulatory effort is directed primarily towards those whose activities give rise to the most serious problems. 3. Setting performance indicators and service standards clarifies what the customer should expect from the Council. Permitting regular review will ensure the service can continually be improved.
Word for word from the decision Blaby published for this meeting.Source: democracy.blaby.gov.uk
Environmental Protection Group June 2009 The Planning Enforcement Policy incorporates and is consistent with the Government’s 1998 Enforcement Concordat, which establishes principles of good practice. 1. INTRODUCTION
Blaby District Council has produced this Planning Enforcement Policy to set out clearly the approach it will take in relation to planning enforcement. It will provide its customers with a clear understanding of the enforcement process.
The integrity of the planning development control function depends on the Council’s readiness to take enforcement action and there are two strands to planning enforcement:
• Reactive enforcement – investigating complaints made to the Council.
• Proactive enforcement – ensuring compliance with planning permissions, associated conditions and agreements.
The policy also recognises that people want to comply with legislation and is designed to help them meet their legal obligations without unnecessary expense.
2. WHAT IS PLANNING ENFORCEMENT
Planning enforcement investigates and takes action against possible breaches of planning control and is a vital part of the planning process. It is a very complex area because the Town and Country Planning Act seeks to strike a balance between the freedom of owners to use or alter their property as they wish, with the need to safeguard the amenities of an area against significant and irreparable harm.
3. SHOULD ENFORCEMENT ACTION BE TAKEN
Even when it is technically possible to take enforcement action, in law the Council is required to decide whether such formal action would be ‘expedient’; this means that formal action is discretionary and all the relevant planning circumstances must first be considered.
The vast majority of breaches of planning control are resolved informally by negotiation with the owner/occupier. Formal action, in accordance with the law, only takes place where it is expedient to do so and where other means to resolve the problem have failed. Ordinarily formal action will only be taken as a last resort and when the breach of planning control is causing significant or irreparable harm to the amenity of the area or is a breach of planning policy. The impact of some development is more harmful than others and therefore enforcement action must always be appropriate to the seriousness of the breach of planning control.
o THE HARM SYSTEM
The Harm system allows unauthorised development to be scored according to its seriousness. Scoring is based on the following criteria: o the existence of a breach o highway safety o other safety issues o the potential to cause nuisance o the age of the breach o if harm to the environment exists and if it is reversible o is there a breach of a planning condition o if the problem occurs in a conservation area or is a sensitive site o if the development sets an undesirable precedent
Each case will be scored following a set format in order to provide a consistent result. However, provision is provided to allow for exceptional circumstance to be taken into consideration whilst making an assessment of an alleged breach of planning control.
4. PRINCIPLES OF ENFORCEMENT
The Local Planning Authority believes in firm but fair regulation. Underlying this are the principles of:
o EXPEDIENCY
In deciding whether it is appropriate to take enforcement action the degree of harm the unauthorised development is causing, or is likely to cause will be carefully considered. Action will only be taken when it is expedient to do so.
o PROPORTIONALITY
The question as to whether enforcement action should be taken rests entirely with the Local Planning Authority. It is a discretionary tool to be used to protect the amenity of an area from serious harm. In deciding whether to take enforcement action it is necessary to show that there is a breach of planning control, that the breach is causing harm and that it is in the public interest to take action. Any action taken must be reasonable and proportionate to the breach.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Croft Conservation Area DesignationDECISION That the designation of a Conservation Area, as identified on the Croft Conservation Area, as identified on ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.