General Fund Revenue Account - Revised Budget 2009/10

Approved Executive 1 paper

Cabinet Executive approved this item on Monday 22 February 2010. Below is the council's own wording, with the papers it was decided on.

Item327

Resolved

DECISION That the revised General Fund Revenue Account budget of £10,510,421 for the financial year 2009/2010 be approved. Reason: As part of the Council’s budget monitoring arrangements a review is carried out of performance against the original approved General Fund Revenue Account budget as the end of the financial year approaches. Any significant issues and estimated outturn variances are brought to the attention of the Cabinet Executive for approval.
Word for word from the decision Blaby published for this meeting. Source: democracy.blaby.gov.uk

Follow this further

Built from Blaby's papers

What the report saysPro

Report to Cabinet Executive

Purpose of report

1.1To set out for consideration and approval the revised General Fund Revenue Account budget for 2009/2010 financial year.

Recommendation

2.1That the revised General Fund Revenue Account budget of £10,510,421 for the financial year 2009/2010 be approved.

3. Reason for Decision Recommended

3.1As part of the Council’s budget monitoring arrangements a review is carried out of performance against the original approved General Fund Revenue Account budget as the end of the financial year approaches. Any significant issues and estimated outturn variances are brought to the attention of the Cabinet Executive for approval.

4. Forward Plan

4.1Forward Plan Reference Number: 02/10(083).

5. Key Decision

5.1Yes.

6. Matters for Consideration

6.1Introduction

As part of the Council’s overall arrangements for good financial governance formal revised estimates are produced each year in respect of the whole of the General Fund Revenue Account budget. This formal review is required in order to ascertain whether there are any significant adverse variances which may require corrective action and to seek approval for additional funding if required. It should be noted that the revised budget reflects the forecast position at an appropriate point in time and may not be indicative of the final outturn which will be dependant upon the performance over the full twelve months of the financial year.

The revised budget complements the more detailed regular portfolio budget monitoring reports which highlight specific variances throughout the course of the year and the cost centre specific review which is carried out at the half year stage.

6.2Cabinet Executive November 2009

At your meeting on the 9th November 2009 a number of specific expenditure issues were brought to your attention in relation to the 2009/2010 budgets. These matters were as follows:-

£ Additional Expenditure

Existing budgets: Fuel Costs 6,000 Professional Fees – Standards Committee 6,800 Other net increases 25,216

One off items: External Audit Fees – Subsidy Claims 20,525 Energy Costs – Enderby Leisure Centre 50,000 Building Control – Staffing Adjustment 45,000

Income Streams

Net surplus -2,855

Less Expenditure Savings

Establishment Costs -50,000 Concessionary Travel -45,000

TOTAL 55,686

The net cumulative effect of the above issues on the General fund revenue budget at that time was a forecast increase in expenditure of £55,686 over the approved base budget.

This estimated variance equated to around 0.53% of net revenue expenditure and was within the normal tolerance levels of +/- 2.00%. It was, therefore, not recommended that any mid-year contribution should be made from the Council’s balances to support revenue expenditure.

6.3Revised Budget

A formal review of all the budget cost centres has now been completed as the financial year end approaches. Those issues identified at the meeting in November have been reflected in the review. The revised budget for the year, which is summarised by portfolio at Appendix A, is £10,510,421.

Movements in the budget identified since the November meeting appear in the table below.

£

Total Variance as per November report 55,686

Additional Expenditure: Conservation Areas – Consultancy Fees 10,000 Redundancy Costs 40,000 External Legal Fees 5,000 Public Inquiry, Leicester Road, Countesthorpe 15,000 Other Minor Variances 1,665

Reduced Expenditure/Additional Income: Reduction in estimated lease rentals payable -2,344 Reduction in Minimum Revenue Provision – capital expenditure funded through borrowing -46,696 Additional Housing & Council Tax Benefit Subsidy receivable -22,105 Development Control Fees -25,000

Latest Forecast Variance 31,206

The estimated adverse variance has therefore decreased from £55,686 to £31,206 which represents 0.29% of the original budget.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
General Fund Revenue Account: Revised Budget 2009/10Report 45 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 25 attended
EF
Councillor E. F. WhiteLeader, present
JO
Councillor J. O. HudsonDeputy Leader, present
DC
Councillor David ClementsMember, present
KD
Councillor K. D. ColesMember, present
JA
Councillor J. A. DickinsonMember, present
GJ
Councillor Guy JacksonMember, present
EA
Councillor E. A. Webster-WilliamsMember, present
DJ
Councillor David JenningsInvitee, in attendance
AT
Councillor Alan TannerObservers, in attendance
SW
Mrs Sandra WhilesOfficer, in attendance
JH
Mr J.L. HoldenOfficer, in attendance
SB
Mr S. BeardOfficer, in attendance

All 25 on the meeting page

On this subject at Blaby

Search all
  1. General Fund Revenue Account - Revised Budget 2009/10This decision
  2. General Fund Budget Proposals 2026/27Approved
  3. General Fund Budget Proposals 2025/26Approved
  4. General Fund Budget Proposals 2024/25Approved
  5. General Fund Budget Proposals 2022/23Approved
  6. General Fund Budget Proposals 2022/23Approved

More from Blaby Cabinet Executive

All decisions
MeetingDecisionOutcome
21 Sep 2026 Quarter 1 Budget ReviewDECISIONS 1. That the financial performance against the budget for the quarter ending 30th June 2026 be accepted. 2. ... Approved Open
21 Sep 2026 Risk Management StrategyDECISION That the revised be adopted. Reasons: 1. The should be subject to regular review to ensure that it reflects ... Approved Open
21 Sep 2026 Quarter 1 Treasury Management Update 2026-27RECOMMENDATIONS TO COUNCIL 1. That the latest position in respect of treasury activities, and the prudential indicato... Approved Open
21 Sep 2026 Quarter 1 Capital Programme Review 2026-27RECOMMENDATIONS TO COUNCIL 1. That the report be accepted. 2. That the latest Capital Programme for 2026/27, totallin... Approved Open
29 Jun 2026 Update on Local Government Reorganisation and Establishment of voluntary Joint CommitteesDECISIONS 1. That the current position regarding Local Government Reorganisation in Leicester, Leicestershire and Rut... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies