DECISIONS 1. That the report of the Financial Services Group Manager be accepted. 2. That the current contract with HSBC be renewed for a period of 12 months. 3. That the overdraft facility be reduced further from £50,000 to nil. Reasons: 1. To allow the Council to make savings utilising the HSBC inter-net to access data. 2. The cashflow of the Council is closely monitored and over the past year it has been demonstrated that the overdraft facility has been unnecessary.
Word for word from the decision Blaby published for this meeting.Source: democracy.blaby.gov.uk
1.1To Provide an update to members of the Cabinet Executive on the progress regarding the renewal of the existing banking services contract with HSBC.
Recommendations
2.1That the report be accepted.
2.2That the current contract with HSBC be renewed for a period of 12 months.
2.3That the overdraft facility be reduced further from £50,000 to nil.
3. Reasons for Decisions Recommended
3.1To allow the Council to make savings utilising the HSBC inter-net to access data.
3.2The cashflow of the Council is closely monitored and over the past year it has been demonstrated that the overdraft facility has been unnecessary.
4. Forward Plan
4.1Forward Plan Reference Number: 02/11/(082)
5. Key Decision
5.1Yes.
6. Matters for Consideration
6.1The current banking services contract with HSBC is due to expire on 31st March 2011. HSBC had proposed a two year contract in March 2010 which incorporated rates for processing of cash banked, cheques presented, data for reconciliation purposes and the provision of an overdraft facility.
It was decided at that time to sign a one year contract which would allow HSBC time to demonstrate how the Council may source data more efficiently and at a lower cost.
6.2Prior to the contract being renewed in March 2010 a benchmarking exercise had been undertaken. This illustrated that HSBC, was comparable in terms of transactional pricing apart from the provision of reconciliation data. HSBC were made aware of this and put forward an option to obtain this data utilising the HSBC online capability so avoiding costs of £8,000.
6.3Although it has taken considerably longer than first anticipated, the facility to obtain this information is now in the final stages. The relevant data has been sourced via the HSBC Website and the conversion of this to integrate into the Council’s systems is the last step. Work is currently being undertaken to complete this.
6.4In addition to the transactional elements, the agreement with HSBC incorporates the provision of an overdraft facility. Historically the Council maintained an overdraft facility of £1.5m for which there was no charge. As part of the review in 2010, HSBC were suggesting that a charge would need to be made for this facility. Since Blaby had not utilised the overdraft a decision was taken at the Cabinet Executive meeting of 26th April 2010 to reduce this to £50,000 and avoid a charge of approx. £11,000.
6.5Since then, the utilisation of the overdraft facility has been monitored closely and HSBC has suggested that Blaby remove the overdraft facility completely to save on the arrangement fee and the facility charge. This seems appropriate given that HSBC have agreed that they would continue to honour any payments should Blaby in effect be ‘overdrawn’ at any point. A one off fee would be payable if such an instance arose, but this would be far smaller than the arrangement fee.
7. Other Relevant Considerations
7.1Human Rights Act 1998
Not applicable.
Legal implications
Not applicable.
7.3Human Resources Implications
Not applicable.
7.4Risk Assessment & Business Continuity
The fact that HSBC banking is web based and can be accessed via the internet from any location supports issues raised when considering business continuity.
7.5Equalities
Not applicable.
7.6Nottingham Declaration and Climate Change . Not applicable.
7.7Crime & Disorder
Not applicable.
7.8Other
Not applicable.
8. Other Options Considered
8.1Carry out a full tender exercise now rather than at the end of this 12 month extension. This would not allow us to fully understand the benefits of sourcing the data via the HSBC website before then going out to the market. It is this element of the contract that differentiated HSBC from those other providers identified in the benchmarking exercise.
9. Appropriate Consultations
9.1None.
10. Financial and Efficiency Implications
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.