RECOMMENDATIONS TO COUNCIL 1. That the total capital resources of £763,700, including £550,700 of Prudential Borrowing, for 2013/14 be approved. 2. That the proposed Capital Programme for 2013/14, including schemes brought forward from prior years, as set out at Appendix A be approved. Reason: To obtain approval for the proposed level of capital resources for 2013/14 and the proposed programme of capital investment.
Word for word from the decision Blaby published for this meeting.Source: democracy.blaby.gov.uk
1.1To set out the estimated resources and investment proposals in relation to capital expenditure during 2013/14.
2. Recommendation to Cabinet/Council
2.1That the total capital resources of £763,700, including £550,700 of Prudential Borrowing, for 2013/14 be approved.
2.2That the proposed Capital Programme for 2013/14, including schemes brought forward from prior years, as set out at Appendix A be approved.
3. Reason for Decision Recommended
3.1To obtain approval for the proposed level of capital resources for 2013/14 and the proposed programme of capital investment.
4. Forward Plan
4.1Yes
5. Key Decision
5.1No – Council decision 6. Matters for Consideration
6.1Introduction
A key element in the process for determining the proposed annual capital investment programme is to consider the Council’s priorities for improvement, as set out in the Corporate Plan, which have capital funding implications and to ascertain the estimated overall level of resources available to fund any proposed expenditure taking into account the affordability factor in terms of loss of investment income and borrowing costs.
6.2Background: Funding and Capital Receipts
The Prudential Code, introduced on 1st April 2004, provides local authorities with greater flexibility to borrow to fund capital projects, subject to that borrowing being affordable, prudent, and sustainable. The Code constitutes a framework of self regulation for capital expenditure which enables Councils to invest in capital projects without any centrally imposed pre-determined limit. The Council now routinely uses borrowing to support the delivery of the capital programme. Local authorities still have access to other forms of capital funding such as capital grants, revenue contributions, useable capital receipts and other forms of reserve and renewal funds.
Following the transfer of the housing stock the arrangements for the Council to access receipts from the disposal of Council owned properties changed. The Council has been entitled, over the first five years, following transfer, to receive 100% of the receipts from the sale of the first ten properties less £50,000. However, to date, there have been no receipts in respect of sales of former Council houses.
A number of former housing related land assets, primarily garage sites were retained by the Council at the time the housing stock transferred with a view to disposing of these after the closedown of the Housing Revenue Account to either generate a capital receipt or to deliver affordable housing opportunities in partnership with our housing partners. At its meeting of 6th December 2010, Cabinet Executive approved the disposal of a number of these sites and to date the Council has received £527,000 from those sales.
6.3Capital Programme 2013/14
As part of the budget planning process officers were invited to put forward schemes for inclusion in the 2013/14 Capital Programme. The value of original bids received and subsequently considered by the Asset Management Group amounted to £963,635.
It is notable that the bids received have diminished year on year as the Council has faced further financial constraints and Officers have taken this into consideration when putting bids forward.
Included within these bids was £600,635 in respect of Disabled Facilities Grants (DFG’s), of which £193,000 would be funded by specified capital grant received from central government. As was the case in the 2012/13 capital programme, consideration was made as to the cost of continued funding of DFG’s. The bid was therefore reduced to £393,000, the amount included in the 2012/13 capital programme.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.