RECOMMENDATIONS TO COUNCIL 1. That the report be accepted. 2. That the latest Capital Programme totalling £9,372,700, including the additions listed in paragraph 4.1, be approved. Reason: To ensure that the Council has adequate resources in place to meet its capital expenditure commitments.
Word for word from the decision Blaby published for this meeting.Source: democracy.blaby.gov.uk
The original Capital Programme for 2019/20 was approved by Council on 21 February 2019, and amounted to £7.062m. This includes £5m in respect of the refurbishment of Enderby Leisure Centre and the Pavilion as part of the new leisure management contract with SLM.
The following table shows the latest Capital Programme which now amounts to £9.373m, taking into account £1.946m brought forward from 2018/19. Appendix A gives a complete breakdown of planned expenditure on a scheme by scheme basis, including how it will be resourced. The items marked with an asterisk, totalling £200,000, were approved by Council on 25 June 2019.
£ Approved Capital Programme 2019/20 7,062,100
Additions: Incomplete schemes brought forward from 2018/19 1,945,760 Audio Visual Equipment & Furniture for Civic Area (approved by Council 190,000 on 25 June 2019)* Disabled Facilities Grants 85,028 Replacement BACS Submission Software 14,000 Cash Receipting System upgrade 13,000 Relining of Public Car Parks (approved by Council on 25 June 2019)* 10,000 Purchase of new Flat-bed Trailer for Grounds Maintenance team 4,494 9,324,382 Add S106 Contributions allocated to projects in 2019/20 48,318 Revised Capital Programme 2019/20 9,372,700
Incomplete schemes brought forward from 2018/19 – this represents the total value of schemes that were part of the 2018/19 Capital Programme but which, for various reasons, were not completed during the financial year. The remaining budget has been carried forward to 2019/20, along with the associated resources, to allow those schemes to be finalised in the new financial year.
Disabled Facilities Grants – the Approved Capital Programme included a provisional sum of £500,000 as final allocations had not been made available by the Ministry of Housing, Communities & Local Government (MHCLG). The final amount allocated to Blaby by MHCLG for 2019/20 is £585,028.
The Council’s contract in respect of BACS payments and collections has expired, and quotations have been sought for a replacement solution. A new five year contract has been awarded and the new solution is currently being implemented.
The current version of our cash receipting and income management software will be de-supported later this financial year. Since this software provides critical interfaces with our financial management system and our website, it is important that we migrate to the latest version. Implementation plans are currently being put in place and the upgrade is planned to go live in mid December.
New flat-bed trailer for the Grounds Maintenance Service – this has been financed from revenue contributions, including the proceeds of other asset sales.
Section 106 contributions – an additional £48,318 of Section 106 funding has been allocated to projects following consideration by the Planning Obligations Monitoring Group. 4.2 Main Capital Programme
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.