Blaby District Council
Cabinet Executive, Monday 23 February 2026

Quarter 3 Capital Programme Review 2025/26

Approved Executive 4 papers

AI summaryBlaby Cabinet approves £8,305,120 capital programme for 2025/26 and backs purchase of six homes in Glen Parva for temporary accommodation, funded by central government grant and borrowing.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedIncluding six Glen Parva temporary accommodation plots
Money£8,305,120Revised capital programme for 2025/26
What happens nextDelegated authority for purchaseExecutive Director (S151) to finalise the buy
Who it affectsGlen Parva residents and homeless householdsSix properties to be used as temporary accommodation

What was decided

Cabinet accepted the Quarter 3 Capital Programme Review and approved the revised 2025/26 Capital Programme of £8,305,120. Report P2, P6

Cabinet approved the purchase of six plots for temporary accommodation in Glen Parva. Report P8

Delegated authority was given to the Executive Director (S151), in consultation with the Finance, People and Transformation Portfolio Holder, to finalise details and enter contracts.

Why

To keep resources aligned with capital commitments and reflect additions and changes made in the third quarter.

To take up LAFH4 funding and secure the plots to expand temporary accommodation in the district. Report P8

To allow contracts to be entered into without delay, in line with the business case.

What happens next

Finalise and sign contracts to buy the six properties, with deposit due in 2025/26 and completion expected in December 2026. Report P8, P18, P24

Transfer £51,000 from the PV panels underspend at Enderby Leisure Centre to the Huncote Leisure Centre roof replacement, after procurement. Report P10

Carry forward any unspent project budgets into 2026/27 so ongoing schemes can continue. Report P22

The money

  • £1,422,512 Original 2025/26 Capital Programme approved 25 February 2025, including £680,012 borrowing Report P1
  • £7,627,666 Capital Programme after Quarter 2 review (November 2025) Report P2, P3
  • 8,305,120 Revised Capital Programme 2025/26 after Quarter 3 changes Report P6
  • 2,258,970 New addition: Regeneration Property (six Glen Parva plots) Report P4, P8
  • 736,000 New addition: Lease of Dallington House Report P4, P9
  • 75,000 New addition: Huncote Leisure Centre Roof Replacement Report P4, P10
  • 70,000 New addition: Section 106 backed schemes Report P4, P11
  • 60,000 New addition: Food Waste Vehicles and Receptacles Report P4, P12
  • 15,000 New addition: GIS and LLPG System Upgrade Report P4, P13
  • 6,684 New addition: Open Space at Former Huncote BMX Track Report P4, P14
  • (58,570) Reduction: Finance System Upgrade Report P5, P15
  • (50,920) Reduction: Installation of PV Panels at Enderby Leisure Centre Report P5, P16
  • (2,252,970) Reduction: Proportion of Regeneration property spend moved to 2026/27 Report P5, P18
  • (63,056) Reduction: Proportion of UKSPF funds to be used in 2026/27 Report P5, P19
  • £2,819,343 Amount spent against the capital programme at end of December 2025 Report 4.2
  • £807k Central government grant funding the six Glen Parva plots Report P8
  • £1,452k Borrowing funding the six Glen Parva plots Report P8

Options considered

  • Chosen: Approve the revised Capital Programme and the Glen Parva purchases. To access LAFH4 funding and provide further temporary accommodation without delay Report P8
  • Rejected: Other options. None considered Report P45, 8.1

Implications

  • Financial: Borrowing requirement rises to support the £1,452k borrowing share of the six plots, with £680,012 originally approved for 2025/26. Report P1, P8
  • Financial: Food waste service launch by end of March 2026 will use five leased vehicles, with the remaining five new vehicles due by September 2026. Report P25
  • Financial: The Net Zero at the Depot project will be fully funded by the Council after an unsuccessful central government grant application. Report P26
  • Risk: Net spend may exceed approved budgets, and rising inflation could push project costs higher; mitigations include ongoing monitoring and reporting back to Council before proceeding. Report P44
  • Other: No concerns identified on Human Rights, Legal, HR, Equalities, Public Health Inequalities, or environmental impact. Report P36, 5.1, P39

Who and where

  • Households in Blaby District needing temporary accommodation, including homeless applicants Report P8, P24, P27
  • Residents and staff at Huncote Leisure Centre (roof replacement works) Report P10
  • Parish Councils and community groups bidding for Section 106 funded schemes Report P11, P33
  • Disabled residents supported through Disabled Facilities Grants (Lightbulb service) Report P28
  • Council taxpayers and the Council's wider revenue budget Report P44

Timeline

  • 25th February 2025: Original 2025/26 Capital Programme of £1,422,512 approved by Council Report P1
  • November 2025: Revised Capital Programme of £7,627,666 approved after Quarter 2 Report P2
  • 18th November 2025: Council approved lease of Dallington House and UKSPF homelessness project Report P9, P19
  • End of December 2025: £2,819,343 spent against the Capital Programme Report 4.2
  • January 2026: New gym equipment delivered at Enderby Leisure Centre; planning approval granted for Dallington House temporary accommodation Report P27, P34
  • February 2026: First occupants expected at Dallington House, Enderby (13 self-contained units) Report P27
  • End of March 2026: Food waste service launches; Net Zero at the Depot project forecast to complete; new walk and cycle route in Blaby due to complete Report P25, P26, P32
  • April 2026: Section 106 funded Countesthorpe Academy project forecast to be spent Report P33
  • September 2026: Remaining five food waste vehicles forecast to be delivered Report P25
  • December 2026: Expected completion and exchange of the six Glen Parva temporary accommodation properties Report P8, P18, P24

Plain English for the jargon

  • Capital Programme: The Council's plan for spending on long-term assets and projects, such as buildings and equipment.
  • S151 Officer: The council officer with statutory responsibility for proper financial administration (here, the Executive Director).
  • Section 106: Planning obligations paid by developers to fund local infrastructure or community projects.
  • LAFH4: Government funding stream referenced as available to support the temporary accommodation purchases.
  • UKSPF: UK Shared Prosperity Fund, central government funding for local regeneration and homelessness projects.
  • GIS and LLPG: Geographic Information System and Local Land and Property Gazetteer, used to record property data.
  • Disabled Facilities Grants (DFG): Grants to help disabled residents adapt their homes, administered via the Lightbulb service.
  • PV Panels: Photovoltaic (solar) panels installed at a council leisure centre.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item224

Resolved

DECISIONS 1. That the report be accepted. 2. That the latest Capital Programme for 2025/26, totalling £8,305,120, be approved. 3. That the purchase of 6 plots for Temporary Accommodation as detailed in the report be approved. 4. That Council give delegated authority to the Executive Director (S151), in consultation with the Finance, People & Transformation Portfolio Holder, to finalise the details and enter contractual arrangements to purchase the 6 houses for temporary accommodation as detailed in the report. Reasons: 1. To ensure that the Council has adequate resources in place to meet its capital expenditure commitments. 2. To reflect additions or other changes to the Capital Programme that have occurred in the 3rd quarter of the year. 3. To be in a position to take advantage of LAFH4 funding that is available and secure the plots to provide further temporary accommodation. 4. To enable the contractual arrangements to be entered into that align with the business case to purchase the temporary accommodation without delay.
Word for word from the decision Blaby published for this meeting. Source: democracy.blaby.gov.uk

Follow this further

Built from Blaby's papers

What the report saysPro

Report to Cabinet Executive

Background

The original Capital Programme for 2025/26 was approved by Council on 25th February 2025 and totalled £1,422,512, including a borrowing requirement of £680,012.

The revised Capital Programme following the 2nd quarter of 2025/26 was approved in November 2025 and amounted to £7,627,666. The following table shows the latest Capital Programme which now amounts to £8,305,120. Appendix A gives a scheme-by-scheme breakdown of the planned expenditure for 2025/26.

£ Approved Capital Programme 2025/26 7,627,666

New Additions 1. Regeneration Property 2,258,970 2. Lease of Dallington House 736,000 3. Huncote Leisure Centre Roof 75,000 Replacement 4. Section 106 backed Schemes 70,000 5. Food Waste Vehicles and 60,000 Receptacles 6. GIS and LLPG System Upgrade 15,000 7. Open Space at Former Huncote 6,684 BMX Track

Reductions 8. Finance System Upgrade (58,570) 9. Installation of PV Panels at Enderby Leisure Centre (50,920) 10. Income Management System 11. Proportion of Regeneration property (106,684) project to be spent in 2026/27 (2,252,970) (UKSPF4 Project) 12. Proportion of UKSPF funds to be utilised in 2026/27 (Regeneration (63,056) property approved November 2025)

Revised Capital Programme 2025/26 8,305,120 The reasons behind the additions and reductions highlighted in the table above are as follows:

Additions

1. Regeneration Property – Approval is sort for the purchase of six properties at Glen Parva for temporary accommodation. These purchases are being funded by £807k of central government grant and £1,452k by borrowing. If approved, it is expected that £6k will be spent on the deposit of these properties in the current financial year. The remaining will be spent in 2026/27 on completion and exchange. Further information is included in Appendix C.

2. Lease of Dallington House – Approved by Council on 18th November 2025

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Monitoring Statement to 31st December 2025Appendix A 148 KB Download
PDF
Capital Forecasting Statement to 31st December 2025Appendix B 126 KB Download
PDF
Proposal for Temporary AccommodationAppendix C 210 KB Download
PDF
Quarter 3 Capital Programme Review 2025/26Report 160 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 19 attended
BT
Councillor Ben TaylorLeader, present
CC
Councillor Cheryl CashmoreDeputy Leader, present
NC
Councillor Nick ChapmanMember, present
NG
Councillor Nigel GrundyMember, present
LP
Councillor Les PhillimoreMember, present
MS
Councillor Mike ShirleyMember, present
NB
Councillor Nick BrownMember, in attendance
NW
Councillor Neil WrightMember, in attendance
JS
Julia SmithOfficer, in attendance
MG
Marc GreenwoodOfficer, in attendance
SP
Sarah PennelliOfficer, in attendance
LR
Luke Raddon-JacksonOfficer, in attendance

All 19 on the meeting page

On this subject at Blaby

Search all
  1. Quarter 3 Capital Programme Review 2025/26This decision
  2. Quarter 1 Capital Programme Review 2026-27Approved
  3. Quarter 1 Capital Programme Review 2025/26Approved
  4. Quarter 3 Capital Programme Review 2024/25Decided
  5. Quarter 2 Capital Programme Review 2024/25Decided
  6. Quarter 1 Capital Programme Review 2024/25Approved

More from Blaby Cabinet Executive

All decisions
MeetingDecisionOutcome
21 Sep 2026 Quarter 1 Budget ReviewDECISIONS 1. That the financial performance against the budget for the quarter ending 30th June 2026 be accepted. 2. ... Approved Open
21 Sep 2026 Risk Management StrategyDECISION That the revised be adopted. Reasons: 1. The should be subject to regular review to ensure that it reflects ... Approved Open
21 Sep 2026 Quarter 1 Treasury Management Update 2026-27RECOMMENDATIONS TO COUNCIL 1. That the latest position in respect of treasury activities, and the prudential indicato... Approved Open
21 Sep 2026 Quarter 1 Capital Programme Review 2026-27RECOMMENDATIONS TO COUNCIL 1. That the report be accepted. 2. That the latest Capital Programme for 2026/27, totallin... Approved Open
29 Jun 2026 Update on Local Government Reorganisation and Establishment of voluntary Joint CommitteesDECISIONS 1. That the current position regarding Local Government Reorganisation in Leicester, Leicestershire and Rut... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies