RECOMMENDATIONS TO COUNCIL 1) That the report be accepted. 2) That the latest Capital Programme totalling £9,104,806, including the changes listed in paragraph 4.1, be approved. 3) That the request to bring forward £47,000 of capital expenditure from 2020/21 into 2019/20 for the purchase of an additional District Cleansing vehicle be approved. Reason: To ensure that the Council has adequate resources in place to meet its capital expenditure commitments.
Word for word from the decision Blaby published for this meeting.Source: democracy.blaby.gov.uk
The original Capital Programme for 2019/20 was approved by Council on 21 February 2019, and amounted to £7,062m.
Members will recall that the Quarter 1 Capital Programme report was brought to Cabinet on 9 September and approval was given for the latest Capital Programme of £9.373m. Since then, schemes to the value of £232,106 have been added to the Capital Programme, whilst two schemes totalling £500,000 have been deferred to next financial year.
The following table shows the latest Capital Programme which now amounts to £9,105m. Appendix A gives a complete breakdown of planned expenditure on a scheme by scheme basis, including how it will be resourced.
£ Approved Capital Programme (September 2019) 9,372,700
Additions: Conversion of the Grange (approved by Council 9 April 2019) 200,000 Install Passive Venting at BMX Track 19,650 Contribution to Flood Gates for Watery Gate Lane, Thurlaston 16,250 Windows Server Migrations 10,464
Reductions: Works to Landfill Gas Monitoring System, Pavilion (14,258) Revenues & Benefits System (250,000) HR & Payroll System (250,000)
Revised Capital Programme 2019/20 9,104,806
An initial funding estimate of £200,000 was approved by Council on 9 April 2019 for the renovation of the Grange in Narborough. The funding is to be used to convert the building into four apartments with a view of retaining the apartments and renting out the accommodation to generate an income stream.
The final cost of works to the Landfill Gas Monitoring System amounted to £35,742, a saving of £14,258. This is because the additional bore holes that have been added have increased the efficiency of the monitoring system. The saving has been transferred to support the cost of the works required at the BMX track.
Additional works are needed at the BMX track on the landfill gas site to enable passive venting. The cost of the works has initially been met by a combination of the savings referred to above, and a one-off revenue saving. It is intended that the cost of these works should be met by the BMX Club, and discussions are in progress to agree a repayment schedule.
A separate report on this agenda seeks approval for a £16,250 contribution towards a County Council scheme for the installation of flood gates at Watery Gate Lane, Thurlaston. This has been provisionally added to the Capital Programme pending consideration by Cabinet Executive.
An additional £10,464 is required to facilitate the migration of TRIM, the Council’s electronic document management system, to a new secure server. The existing server, on which TRIM is currently hosted, will be unsupported from January 2020 due to Windows 8 reaching the end of its useful life. Revenues & Benefits System – the procurement has been deferred for a further year to allow more time to prepare for a full tender exercise.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.