RECOMMENDATIONS TO COUNCIL 1) That the report be accepted. 2) That the latest Capital Programme totalling £9,175,206, including the changes listed in paragraph 4.1, be approved. Reason: To ensure that the Council has adequate resources in place to meet its capital expenditure commitments.
Word for word from the decision Blaby published for this meeting.Source: democracy.blaby.gov.uk
The original Capital Programme for 2019/20 was approved by Council on 21 February 2019, and amounted to £7,062m.
Members will recall that the Quarter 2 Capital Programme report was brought to Cabinet on 4 November and approval was given for the latest Capital Programme of £9.105m. Since then, schemes to the value of £191,140 have been added to the Capital Programme, whilst reductions totalling £120,740 have been deducted.
The following table shows the latest Capital Programme which now amounts to £9,175,206. Appendix A gives a complete breakdown of planned expenditure on a scheme by scheme basis, including how it will be resourced.
£ Approved Capital Programme (November 2019) 9,104,806
Additions: Fleet Vehicle Replacement Programme (Approved by Council on the 19 47,000 November 2019) Financial Management System 74,578
Reductions: New Performance Management System (27,000) Air Quality Action Plan (15,619) Resurfacing of car parks (31,770) Replacement Local Land Changes System & Customer Portal (26,675) Works to the Ice House, Bouskill Park, Blaby District Council (12,750) Savings (6,925)
9,105,645 Add S106 Contributions allocated to projects in 2019/20 69,561 Revised Capital Programme 2019/20 9,175,206
The Fleet Vehicle capital project has been increased by £47,000 by bringing forward budget from the 2020/21 Capital Programme for the acquisition of a vehicle following concern in regards to health and safety risks associated with overloading of the vehicles. This addition was approved by Council in November.
Members will recall from the report brought to Cabinet Executive on 4 November 2019, that the procurement had taken place for the new Finance system. Budget provision of £125,000 was originally included in the 2020/21 Capital Programme. However, set up of the hosted server is due to complete by mid February so some implementation costs are now expected to fall within the current financial year. It is proposed that £74,578 is brought forward to the 2019/20 Capital Programme.
The procurement of the new Performance Management system has been deferred until mid 2020. This is due to a major review being carried out of the performance management across the Council. The current system has been extended until mid September 2020 to allow time for the procurement exercise to be carried out.
The Air Quality Action Plan is to be implemented in 2020/21 so the budget is to be moved from the current year Capital Programme.
It is expected that £30k will be spent in this financial year for the resurfacing of the car parks however this is dependant on weather conditions in the last quarter of the year, the remainder of the budget is to be moved into the 2020/21 capital programme.
We are only expecting to spend £3,325 on the replacement Local Land Charges system in this financial year due to Land Registry requirements and barriers preventing us to be able to proceed with Hinckley and Bosworth Borough Council as they do not use IDOX. The remainder of the budget is to be moved into the 2020/21 capital programme.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies