RECOMMENDATIONS TO COUNCIL 1. That the report be accepted. 2. That the latest Capital Programme totalling £6,376,295 be approved. Reason: To ensure that the Council has adequate resources in place to meet its capital expenditure commitments.
Word for word from the decision Blaby published for this meeting.Source: democracy.blaby.gov.uk
The original Capital Programme for 2020/21 was approved by Council on 17 February 2020, and amounted to £3.59m. This includes just under £1.1m in respect of the Fleet Vehicle Replacement Programme alone.
The following table shows the latest Capital Programme which now amounts to £6.38m, taking into account £2.06m brought forward from 2019/20. Appendix A gives a complete breakdown of planned expenditure on a scheme by scheme basis, including how it will be resourced. £ Approved Capital Programme 2020/21 3,593,736
Additions: Incomplete schemes brought forward from 2019/20 2,057,459 Disabled Facilities Grants 85,028 Works to Ice House, Bouskell Park, Blaby 52,699
Reductions: Improvement works to Strategic Parks and Open Spaces (1,726) Environmental Services (7,875) LALPAC Licensing System Upgrade (21,500) New Choice Based Letting System (7,960) Replace steps, etc, regrade and dress paths at Crow Mills, (1,515) Countesthorpe
5,748,346 Add S106 Contributions allocated to projects in 2020/21 627,949 Revised Capital Programme 2020/21 6,376,295
Incomplete schemes brought forward from 2019/20 – this represents the total value of schemes that were part of the 2019/20 Capital Programme but which, for various reasons, were not completed during the financial year. The remaining budget has been carried forward to 2020/21, along with the associated resources, to allow those schemes to be finalised in the new financial year.
Disabled Facilities Grants – the Approved Capital Programme included a provisional sum of £500,000 as final allocations had not been made available by the Ministry of Housing, Communities & Local Government (MHCLG). The final amount allocated to Blaby by MHCLG for 2020/21 is £585,028, the same level as for 2019/20.
In December 2019, the Council were successful in securing funding from the Heritage Lottery Fund to improve the Ice House at Bouskell Park and run a community Archaeological Dig. The project set up for Capital works to be carried out is expected to cost a total of £93,722. The Council is contributing £9,372, with the remaining £84,350 externally funded by the National Lottery Heritage Fund.
Expenditure of £9,601 was incurred at the end of the 2019/20 as part of improvement works to Strategic Parks and Open Spaces, and Air Quality within Environmental Services, which has reduced the Planned Capital Budget for 2020/21.
LALPAC Licensing System Upgrade – The project has been completed, and the system implemented. New Choice Based Letting System – The project has completed and the saving is due to a discount being agreed on termination of the contract.
Replace steps, etc, regrade and dress paths at Crow Mills, Countesthorpe – Project has completed.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.