RECOMMENDATION TO COUNCIL That the latest Capital Programme totalling £6,404,593 is accepted, including £80,000 in respect of the Grange, Narborough, subject to consideration and acceptance of the additional investment at the forthcoming meeting of Full Council. Reason: To ensure that the Council has adequate resources in place to meet its capital expenditure commitments.
Word for word from the decision Blaby published for this meeting.Source: democracy.blaby.gov.uk
The original Capital Programme for 2020/21 was approved by Council on 17 th February 2020, and amounted to £3.59m. This included just under £1.1m in respect of the Fleet Vehicle Replacement Programme alone.
The following table shows the latest Capital Programme which now amounts to £6.37m, taking into account £2.06m brought forward from 2019/20. Appendix A gives a complete breakdown of planned expenditure on a scheme by scheme basis, including how it will be resourced. £ Approved Capital Programme 2020/21 6,376,295
Additions: Conversion of the Grange, Narborough 80,000 Replacement Sampling Tube, Landfill Gas System 35,000 Air Quality Analysers 7,000
Less: Car Park and Bridge Improvement Project deferred to 2021/12 (40,000) Replacement of Boilers, Radiators and Pipework Project (40,000) deferred to 2021/22 Replacement of the Heating System – Phase 2 Project (55,000) deferred to 2021/22 Contingency funding applied (42,000)
6,321,295 Add S106 Contributions allocated to projects in 2020/21 47,299 Revised Capital Programme 2020/21 6,368,593
Budget of £350,000 was approved in February for the conversion of the Grange in Narborough. During the planning stage of the project additional works that need to be undertaken have been identified, and will require a additional budget of £80,000 added to the project. Further information regarding this will be included in a separate report to be considered at the forthcoming Council meeting.
An additional £7,000 has been added to allow for the replacement of air quality analysers that are nearing end of life. This is funded from the contingency budget.
£35,000 has been taken from the contingency pot to fund the replacement of 2,000 metres of tubing that forms part of the landfill gas monitoring system in place at Huncote Leisure Centre. This is necessary due to a change in specification set out in new Health & Safety Executive guidance.
Budget of £40,000 in respect of the Car Park and Bridge improvement project at Bouskell Park has been deferred to the 2021/22 Capital Programme to allow for a proposed redesign to be undertaken.
The projects relating to the heating system, and boiler, radiator, and pipeworks at the Council Offices have been deferred to the 2021/22 Capital Programme to enable a green heating solution to be considered.
S106 contributions allocated to projects has increased by £47,299, bringing the total to £675,247. 4.2 At the end of the second quarter of 2020/21, the Council had spent £1,461,610 against its planned Capital Programme, excluding Section 106 contributions, of £5,808,346. S106-backed schemes are covered in paragraph 4.3 below.
Members will be aware from the Quarter 1 report presented in September that the outbreak of COVID-19 had prevented a number of Capital Projects from being carried out as planned. We are now starting to see a clearer picture and Capital projects progressing.
Explanations for the main variances in Quarter 2 are as follows:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.