RECOMMENDATIONS TO COUNCIL 1. That the proposed 5 Year Capital Programme for 2022/23 to 2026/27, be approved. 2. That the application of capital resources of £2,452,500 for 2022/23, including a borrowing requirement of £1,168,500, be approved. 3. That the Capital Strategy 2022/23 to 2026/27 be approved. Reasons: 1. To obtain approval for the proposed level of capital expenditure in 2022/23 and the suggested method of financing that expenditure. 2. To provide a longer term forecast of capital expenditure and financing requirements for the period 2022/23 to 2026/27. 3. To ensure compliance with CIPFA’s Prudential Code.
Word for word from the decision Blaby published for this meeting.Source: democracy.blaby.gov.uk
The Council approved its current Capital Strategy on 18th February 2021. The Capital Strategy is a high level document that considers the Council’s future capital spending plans and available capital resources, together with the implications for the revenue account. The strategy also sets out the overall governance process for setting the Capital Programme.
Part of the governance process involves the approval of a rolling 5 Year Capital Programme based around the Council’s strategic priorities and planned renewal and replacement of existing assets.
The summarised 5 Year Capital Programme covering the financial years 2022/23 to 2026/27 is attached at Appendix A. The starting point for the proposals is the existing 5 year programme, which was also approved by Council at the above meeting. The Asset Management Group has reviewed the existing programme and considered new bids for inclusion, as well as identifying where current year schemes need to be deferred. The headline proposals were considered by Strategic Board in November 2021, although some of the detail has since been refined to reflect emerging priorities.
4.2Proposal(s)
As can be seen at Appendix A, the total proposed Capital Programme for the next five years amounts to £11.5m, of which just under £2.5m falls in 2022/23. At this point in time, many of the schemes put forward for inclusion in the Capital Programme require further refinement in terms of specification and cost. Some of those schemes may also require separate approval from Council before proceeding. For example, the proposed 5 year plan includes an assumption that refuse vehicles will be replaced with electric equivalents from 2023/24, in line with the Council’s carbon neutral aims. In cases such as this a further report will be brought before Council at the appropriate time.
Across the life of the 5 Year Capital Programme it is forecast that just under £2.0m of capital expenditure can be met from the Council’s own resources (e.g. capital receipts and reserves), and another £3.3m from government grant. This leaves a projected borrowing requirement of £6.2m between 2022/23 and 2026/27.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.