Lightbulb Partnership Extension

Agreed Executive 1 paper

AI summaryBlaby Cabinet extends the Lightbulb housing partnership agreement for 24 months to 31 March 2028, allowing time to review the delivery model alongside local government reorganisation. Total partnership cost is £1,369,155 for 2026/27.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedto 31 March 2028, with review of delivery model
Money£1,369,155 total 2026/27 costBlaby's net revenue share is £59,230
What happens nextReview delivery model and pilotsfull business case by March 2028
Who it affectsHousing support service across Leicestershirehosted by Blaby, serving 7 partner authorities

What was decided

Cabinet approved a 24-month extension of the Lightbulb agreement and of contracts with the other Leicestershire authorities, to allow a review of the delivery model and existing pilots. Report P8

Cabinet noted the cost of delivering the Lightbulb Service as set out in the report. Report 6.1

Delegated authority was given to the Environmental Health, Housing and Community Services Group Manager, in consultation with the Portfolio Holder, to monitor progress, review delivery methods and make minor changes.

Why

The current legal agreement with partner districts ends on 31 March 2025, and the partnership wants stability while Local Government Reorganisation and Devolution arrangements are clarified. Report P3, P5, P10

Extending avoids service disruption and gives time to evaluate key pilots, including a Caseworker role and a DFG Transformation Officer, before a full business case is brought forward. Report P4, P6, P10

Reverting to a pre-Lightbulb model would be less holistic and preventative and would offer a poorer service to residents. Report 8.1

What happens next

Partners will continue to embed and evaluate the Caseworker pilot and the DFG Transformation Manager pilot, with work to extend them into 2026/27 already agreed. Report P6, P10

Work is underway with Leicestershire County Council to gather further financial, operational and delivery analysis on integrating ceiling track hoists; a further report will come to Cabinet if that is pursued. Report P16

A full business case for the future model is to be brought forward by March 2028, with the Group Manager and Portfolio Holder overseeing progress under delegated authority. Report P10

The money

  • £1,369,155 Total annual cost of delivering the Lightbulb Service for 2026/27 across all partners Report 6.1
  • £388,670 Funded through capitalised Disabled Facilities Grant expenditure (2026/27) Report 6.1
  • £980,485 Net revenue cost of the Lightbulb Service across all partners (2026/27) Report 6.1
  • £146,125 Blaby District Council total contribution for 2026/27 Report P23, 6.1
  • £86,895 Blaby's contribution capitalised through DFG (2026/27) Report P23, 6.1
  • £59,230 Blaby's net revenue cost for 2026/27 Report P23, 6.1
  • £639,134 Leicestershire County Council total contribution for 2026/27 Report 6.1
  • £146,540 Hinckley and Bosworth total contribution for 2026/27 Report 6.1

Options considered

  • Chosen: Extend the Lightbulb Partnership Agreement for a further 24 months to 31 March 2028. Maintains continuity while LGR and devolution arrangements are clarified and pilots are evaluated Report P8, P10
  • Rejected: Deliver Disabled Facilities Grants as prior to Lightbulb. Would be less holistic and preventative and would provide a poorer service to Blaby residents Report 8.1

Implications

  • Financial: Blaby fully recovers its overhead and hosting costs through partner contributions, so no additional corporate overhead falls to Blaby as host. Report P24
  • Risk: Primary risks identified relate to financial pressures, workforce capacity, service demand and partner engagement, mitigated through partnership governance and annual budget review. Report 7.1, P27
  • Staffing: The Service Manager will hold joint responsibility for Lightbulb and the Housing Enablement Team on a 50/50 funding basis, with a new Lightbulb Team Leader post created. Report P11
  • Equalities: The author considered Human Rights, Legal, HR, Equalities and Public Health Inequalities matters and identified no areas of concern; the service supports the most vulnerable. Report 4.5
  • Climate: Future key decisions will continue to be made with the climate change agenda in mind, such as in procurement and service design. Report 5.1

Who and where

  • Residents across Leicestershire receiving housing support and Disabled Facilities Grants Report P1, P12
  • Partner district and county councils: Blaby, Charnwood, Harborough, Hinckley and Bosworth, Melton, North West Leicestershire, Oadby and Wigston, and Leicestershire County Council Report 6.1
  • Housing Enablement Team staff at Blaby District Council Report P11

Timeline

  • October 2017: Lightbulb service launched Report P1
  • 31 March 2025: Current legal agreement with partner districts due to end Report P3
  • 2024/25 and 2025/26: Pilots including the Caseworker and DFG Transformation Manager role have continued Report P6
  • 2026/27: Pilots agreed to be extended by partners Report P6
  • April 2026: Indicative point for potential integration of ceiling track hoists, subject to further analysis and a future Cabinet report Report P16
  • 31 March 2028: Proposed end of the 24-month extension; full business case for the future model to be brought forward Report P8, P10

Plain English for the jargon

  • Lightbulb: A Leicestershire-wide housing support partnership hosted by Blaby District Council, originally set up in October 2017.
  • Disabled Facilities Grant (DFG): A mandatory local authority grant to help fund home adaptations for disabled residents; some of the Lightbulb cost is met by capitalising DFG.
  • LGR: Local Government Reorganisation, the restructuring of councils referenced in the Government Devolution White Paper.
  • Hub-and-spoke: A delivery model in which Blaby hosts central functions (management, performance, quality assurance) for partner districts.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item220

Resolved

DECISIONS 1. That the Lightbulb agreement be extended for a further 24 months. 2. That the current contracts with the other Leicestershire Authorities be extended two years, whilst further work is undertaken to review the delivery model and pilots. 3. That the cost of delivering the Lightbulb Service, as set out in the report for 2025 – 2026 be noted. 4. That delegated authority be given to the Environmental Health, Housing & Community Services Group Manager in consultation with the Portfolio Holder to monitor progress, review delivery methods and make minor necessary changes to ensure effective delivery. Reasons: 1. The Lightbulb Executive and Operational Boards have agreed that Blaby District Council continue to host the Lightbulb Service and that a continued review of the delivery models be undertaken of the delivery models. 2. Extending the current contractual arrangements with partner authorities ensures continuity across Leicestershire, avoids service disruption, and allows sufficient time to undertake a structured review of the delivery model and existing pilots to inform any future long-term decisions 3. The proposed cost of delivering the Lightbulb Service for 2025–2026 reflects the staffing structure, roles and salary assumptions that have been reviewed and agreed by the Lightbulb Executive and Operational Boards and is necessary to ensure the service remains responsive and compliant. 4. Delegated authority is required to allow the service to respond flexibly to operational needs, emerging pressures while maintaining appropriate oversight through the Group Manager and Portfolio Holder to ensure effective governance and value for money.
Word for word from the decision Blaby published for this meeting. Source: democracy.blaby.gov.uk

Follow this further

Built from Blaby's papers

What the report saysPro

Report to Cabinet Executive

Background

Since its launch in October 2017, Lightbulb has continued to evolve through refreshed business cases, new initiatives, and ongoing improvements to operational processes. The service has been shaped by regular reviews of demand data, efficiency modelling and partnership feedback, ensuring it remains responsive to both resident need and system priorities.

The original hub-and-spoke model, with Blaby District Council hosting the central hub functions including management, performance reporting, resilience planning and quality assurance remains the foundation of the service.

The current legal agreement with partner districts is now due to end on 31 March 2025, making this an appropriate point to reassess future delivery arrangements.

Over the last 12 months, work has progressed on an updated delivery document exploring future service options, including the introduction of a dedicated Caseworker role and refinement of leadership structures to strengthen operational resilience.

The publication of the Government’s Devolution White Paper, and the emerging direction of Local Government Reorganisation (LGR), introduces the possibility of significant strategic and operational change for district councils. Strategic Leads across the partnership therefore support taking additional time to fully understand the implications of LGR, assess future structures, and identify areas where the Lightbulb model can continue to innovate and improve.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Lightbulb Partnership ExtensionReport 253 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 19 attended
BT
Councillor Ben TaylorLeader, present
CC
Councillor Cheryl CashmoreDeputy Leader, present
NC
Councillor Nick ChapmanMember, present
NG
Councillor Nigel GrundyMember, present
LP
Councillor Les PhillimoreMember, present
MS
Councillor Mike ShirleyMember, present
NB
Councillor Nick BrownMember, in attendance
NW
Councillor Neil WrightMember, in attendance
JS
Julia SmithOfficer, in attendance
MG
Marc GreenwoodOfficer, in attendance
SP
Sarah PennelliOfficer, in attendance
LR
Luke Raddon-JacksonOfficer, in attendance

All 19 on the meeting page

More from Blaby Cabinet Executive

All decisions
MeetingDecisionOutcome
21 Sep 2026 Quarter 1 Budget ReviewDECISIONS 1. That the financial performance against the budget for the quarter ending 30th June 2026 be accepted. 2. ... Approved Open
21 Sep 2026 Risk Management StrategyDECISION That the revised be adopted. Reasons: 1. The should be subject to regular review to ensure that it reflects ... Approved Open
21 Sep 2026 Quarter 1 Treasury Management Update 2026-27RECOMMENDATIONS TO COUNCIL 1. That the latest position in respect of treasury activities, and the prudential indicato... Approved Open
21 Sep 2026 Quarter 1 Capital Programme Review 2026-27RECOMMENDATIONS TO COUNCIL 1. That the report be accepted. 2. That the latest Capital Programme for 2026/27, totallin... Approved Open
29 Jun 2026 Update on Local Government Reorganisation and Establishment of voluntary Joint CommitteesDECISIONS 1. That the current position regarding Local Government Reorganisation in Leicester, Leicestershire and Rut... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies