Blackburn with Darwen Borough Council
Executive Board, Thursday 12 March 2026 at 6.00pm

Highways Capital Programme 2026-27 - approval to spend

Noted Executive 2 papers

AI summaryBlackburn with Darwen Executive Board approves the 2026/27 Highway Capital Programme, worth over £15m and described as the largest annual programme of highway works the borough has seen.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedPlus delegated authority to amend and award tenders
Money£15,067,307 totalDepartment for Transport funding via LCCA for 2026/27
What happens nextSpend during 2026/27 financial yearWith progress updates to the Growth portfolio holder
Who it affectsRoads, footpaths, signalling, bridges, lighting borough-widePlus walking, cycling and bus infrastructure

What was decided

The Executive Board approved the Highway Capital Programme for 2026/27, with the £15,067,307 Local Transport Grant to be added to it. Report P7, P8

The Board noted the £2,451,531 Bus Services Grant allocation alongside the overall £15,067,307 capital settlement from the Department for Transport via the Lancashire Combined County Authority. Report P5, P6, P12

The Strategic Director of Growth and Development, in consultation with the Executive Member for Growth and Development, was given delegated authority to amend the programme and to seek and accept tenders, subject to adequate budget provision. Report P7

Why

The programme is needed to fund road and footpath maintenance, resurfacing, bridge improvements, street lighting, traffic signals, active travel and bus infrastructure across the borough. Report P2, P13

It aligns with the draft Local Transport Plan Implementation Plan 2026 to 2030, the Council's Growth Programme and Core Missions in the Corporate Plan. Report P10, P20

The 2026/27 settlement comes from a new multi-year funding arrangement for Local Transport Authorities announced by Government in December 2025. Report P12

What happens next

Schemes listed in Appendix A will be delivered during 2026/27, with flexibility to reallocate spend between locations as needs change. Report P14, P17, P18

The Executive Member for Growth and Development will receive regular updates on scheme delivery and any budget variations. Report P15, P21

Residents and stakeholders will be informed before works start, via the Council's website, social media, leaflets and letters, and emergency services consulted where needed. Report P29, P31

The money

  • £15,067,307 Total 2026/27 capital funding allocation from the DfT via the LCCA Report P5, P12
  • £2,451,531 Bus Services Grant allocation for 2026/27 Report P6, P12
  • £8,126,648 Local Transport Grant share of the 2026/27 allocation Report P12
  • £3,974,216 Highways Maintenance share of the 2026/27 allocation Report P12
  • £514,912 Active Travel share of the 2026/27 allocation Report P12

Options considered

  • Chosen: Equality Impact Assessment not required, checklist completed. Officer option selected under the equality and health implications section Report P25

Implications

  • Financial: Programme will be closely monitored to ensure full spend, with variations reported to the Executive Member and through capital reporting. Report P21
  • Legal: Schemes will comply with relevant highway, transport, traffic and equality legislation, procurement law and any grant conditions. Report P22
  • Legal: Section 151 Officer confirmed recommendations do not incur unlawful expenditure and Monitoring Officer advice was received. Report P33
  • Equalities: Equality analysis and impact assessment has been considered and the recommendations are compliant with equality legislation. Report P33
  • Risk: Schemes and budgetary allowances cannot be treated as fixed budgets because the service responds to variable and unknown external factors. Report P17
  • Staffing: Staff time will be met from existing resources; external contractors procured where internal resources cannot deliver, in line with HMEP standards. Report P24

Who and where

  • Residents, businesses and road users across the Blackburn with Darwen borough Report P2, P11
  • Bus passengers (bus infrastructure improvements) Report P13
  • Pedestrians and cyclists (active travel and footpath schemes) Report P13
  • Developers contributing S106 funding used in the programme Report P2, P11

Timeline

  • December 2025: Government announced new multi-year funding arrangement for Local Transport Authorities; LCCA adopted its grant apportionment policy Report P12
  • 2026/27 to 2029/30: Four-year capital funding period covered by the DfT settlement via the LCCA Report P12
  • 2026 to 2030: Period covered by the draft LTP Implementation Plan Report P10
  • 2026/27 financial year: Year covered by the approved Highway Capital Programme Report P3, P7

Plain English for the jargon

  • LCCA: Lancashire Combined County Authority, the body through which the Department for Transport awarded the 2026/27 transport grants
  • Local Transport Grant: Department for Transport capital funding for development and delivery of transport schemes
  • Bus Services Grant: Department for Transport funding for highway and bus infrastructure that directly benefits bus services
  • S106: Section 106 developer contributions used to support highways improvement schemes
  • LTP4: The new joint Local Transport Plan being developed with the LCCA, Lancashire County Council and Blackpool Borough Council
  • HMEP: Highways Maintenance Efficiency Programme, whose standards guide procurement
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item184

Resolved

RESOLVED (1) That it be noted that the Council’s overall capital funding allocation from the Local Transport Grant Fund awarded by the Department for Transport to the Lancashire Combined County Authority for 2026/27 was £15,067,307. (2) That it be noted that the Council’s capital funding allocation from the Bus Services Grant awarded by the Department for Transport to the Lancashire Combined County Authority for 2026/27 was £2,451,531. (3) That it be approved that the Department for Transport 2026/27 Local Transport Grant be added to the Council’s Highway Capital Programme. (4) That the Highway Capital Programme for 2026/27, as set out in this report be approved. (5) That the Strategic Director of Growth and Development be granted delegated authority, in consultation with the Executive Member for Growth and Development, to amend, seek and accept tenders subject to adequate budget provision.
Word for word from the decision Blackburn with Darwen published for this meeting. Source: democracy.blackburn.gov.uk

Follow this further

Built from Blackburn with Darwen's papers

What the report saysPro

Report to Executive Board

Executive summary

The Council’s Highway Capital Programme for 2026/27 comprises over £15m of road and transport schemes, which is believed to be the highest annual programme of highway works ever seen in Blackburn with Darwen.

The programme focuses on significant investment in highway infrastructure, the maintenance of roads, footpaths, signalling and active travel initiatives, utilising funds like the Local Transport Grant Fund and the Bus Services Grant. Developer contributions are also used to fund schemes as reported in the Council’s annual Infrastructure Funding Statements. The programme, which aims to improve road conditions and safety across the borough, also includes resurfacing, bridge improvements, and new street lighting.

This report seeks the Executive Board’s approval for the allocation of funds detailed in the Highway Capital Programme for the financial year 2026/27.

Recommendations

The Executive Board is asked to:

(i) Note the Council’s overall capital funding allocation from the Local Transport Grant Fund awarded by the Department for Transport to the Lancashire Combined County Authority (LCCA) for 2026/27 is £15,067,307;

(ii) Note the Council’s capital funding allocation from the Bus Services Grant awarded by the Department for Transport to the LCCA for 2026/27 is £2,451,531;

(iii) Approve the Department for Transport 2026/27 Local Transport Grant is added to the Council’s Highway Capital Programme; (iv) Approve the Highway Capital Programme for 2026/27, as set out in this report; and (v) Delegate authority to the Strategic Director of Growth & Development, in consultation with the Executive Member for Growth and Development, to amend, seek and accept tenders subject to adequate budget provision.

Background

For 2026/27, the Council has been allocated over £15m of capital funding from the Department for Transport’s Local Transport Grant Fund (via the LCCA); believed to be the highest annual amount allocated to BwD date. The programme for 2026/27 is set out at Appendix A.

Strategic Context

The Council is currently working with the LCCA, alongside Lancashire County Council and Blackpool Borough Council, to develop, consult and approve a new joint LTP (LTP4), in accordance with Government guidance, and will include a LTP Implementation Plan - a 4-year Plan setting out the specific schemes and strategies to be developed and delivered between 2026 and 2030.

The programme for the year ahead aligns with the emerging Implementation Plan, and aims to provide a good, safe and resilient road network that supports communities and businesses across the borough to access employment, leisure, retail and education. The programme also promotes growth and development incorporating S106 funding to support highways improvement schemes to attract business and residential development opportunities.

Funding The Department for Transport (DfT) has confirmed the new local transport funding settlement to the LCCA for the next four years (2026/27 - 2029/30) as part of the new multi-year funding arrangement for Local Transport Authorities announced by Government in December 2025. This covers the Local Transport Grant, Local Authority Bus Grant, Highways Maintenance and Active Travel funds. The capital funding covers a four-year period whilst revenue funding is for three years (2026/27 - 2028/29). The funding allocations for Blackburn with Darwen Borough Council, using the LCCA grant apportionment policy (adopted in December 2025), is as follows: Local Transport Grant £8,126,648 Local Authority Bus Grant £2,451,531 Highways Maintenance £3,974,216 Active Travel £514,912 £15,067,307

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Highway Capital Programme 202627Appendix A 122 KB Download
PDF
Highways Capital Programme 2026-27: approval to spendReport 160 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 19 attended
MD
Councillor Mustafa DesaiCommittee Member, present
JF
Councillor Jackie FloydCommittee Member, present
JL
Councillor Julie Louise GunnOfficer, present
SH
Councillor Shaukat HussainCommittee Member, present
MK
Martin KellyOfficer, expected
AL
Asad LaherOfficer, present
DL
Dean LangtonOfficer, expected
QM
Councillor Quesir MahmoodCommittee Member, present
NM
Nafisha MasterSecretary, expected
VE
Councillor Vicky Ellen McGurkCommittee Member, apologies
ZM
Zahra MusaSecretary, present
DP
Denise ParkOfficer, present

All 19 on the meeting page

On this subject at Blackburn with Darwen

Search all
  1. Highways Capital Programme 2026-27 - approval to spendThis decision
  2. Highways Capital Programme 2025/26 - UpdatedApproved
  3. Highways Capital Programme 2025/26Approved
  4. Highways Capital Programme 2024/25Approved

More from Blackburn with Darwen Executive Board

All decisions
MeetingDecisionOutcome
10 Sep 2026 Minutes of the Previous MeetingRESOLVED That the minutes of the last meeting held on Thursday, 13 August 2026 be agreed as a correct record for sign... Agreed Open
10 Sep 2026 Corporate Plan Performance, Quarter 1 2026/271) That the Quarter 1 performance against the delivery of the Council’s Corporate Plan Missions, as attached as Appen... Noted Open
10 Sep 2026 Children and Young People's Plan 2026 - 20281) That the Children and Young People’s Plan 2026-2028, which had been formally signed off by the Children’s Partners... Noted Open
10 Sep 2026 Variation to existing schools capital programme - Newfield Satellite Site1) That the requirement for a significant increase in the capital budget for the proposed Newfield School satellite s... Noted Open
10 Sep 2026 Enhancement of the Free Bulky Waste Collection Service1) That that introduction of a newly developed online access system to facilitate a full end to end self-serve option... Approved Open