EB Procurement Strategy - Surfacing and Civils Framework
AgreedExecutive1 paper
AI summaryBlackburn with Darwen Executive Board approves new £50 million Surfacing and Civils Framework for highway works, with streamlined call-off approvals.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedNew four-lot framework for highway works
Money£50 million estimated valueOver maximum four-year framework term
What happens nextTender exercise to beginAdvertised on Central Digital Platform and The Chest
Who it affectsHighways contractors and suppliersUp to three appointed per lot
What was decided
The Executive Board approved a procurement strategy to establish a new Surfacing and Civils Framework Agreement lasting 2 years with options to extend by 2 x 12 months, totalling a maximum of 4 years. Report P4
The Board approved four framework lots covering surfacing, civils, cold milling, and repairs to asphalt surfaces, with up to three highest scoring contractors appointed per lot. Report P4
The Board approved an evaluation based on price, quality and social value, and that call-off contracts be awarded through further competition or direct award, without further procurement strategy approvals. Report P4
Why
The current Surfacing and Civils framework is expiring and must be replaced to maintain the council's statutory highways delivery and comply with procurement law. Report P1, P5
Officers argued that running a new framework is more efficient than using an external framework or tendering each scheme separately, and would cut bidding costs and officer time. Report P13
The framework is intended to support the Highways Infrastructure Asset Management Plan, Local Transport Plan 4, and the council's net zero and social value objectives. Report P16
What happens next
A compliant procurement exercise will be run under the Procurement Act 2023 and advertised on the Central Digital Platform and The Chest e-tendering portal. Report P1, P20
Successful contractors will be appointed to the framework and then invited to further competitions, typically with a two-week pricing period, for individual work packages. Report P7
Individual call-off awards will still be reported and approved in line with the council's Constitution, with monthly reporting of contract values. Report P11, P23
The money
£50 million Estimated total value of the framework over its maximum four-year term Report P1, P4
Options considered
Rejected: Use an existing external framework. Would limit local suppliers, reduce local competition, and restrict flexibility on specification and social value Report P13
Rejected: Run individual tenders for each scheme. Would be resource intensive, increase delivery times and contractor bidding costs, and reduce programme certainty Report P13
Chosen: Establish a new in-house framework agreement with four lots. Provides the most efficient and compliant route, cutting procurement lead times and supporting social value and net zero goals Report P1, P13
Implications
Financial: Highway improvement projects will be funded through the Highways Maintenance Block and Local Transport Grant, with schemes monitored through normal financial monitoring processes. Report P5, P19
Legal: The procurement will comply with the Procurement Act 2023 and the council's Contract and Procurement Procedure Rules, and call-off contracts will be in a form approved by legal officers. Report P20, P21
Equalities: An Equality Impact Assessment checklist has been completed and the council considers the recommendations compliant with equality legislation. Report P28, P33
Climate: The framework will support net zero and sustainability objectives, with carbon and environmental performance monitoring built in. Report P1, P9
Staffing: There are no major resource implications; existing Highways and Transport Services staff will manage the contracts. Report P25
Risk: Call-off contracts will be subject to KPI monitoring covering safety, quality, cost, programme and social value, plus supply chain compliance checks. Report P9
Governance: Further competitions will not need additional procurement strategy approvals, but contract awards will still be reported and approved under the Constitution. Report P23
Who and where
The council's Highways and Transport Services, which manage statutory highways functions Report P5, P25
Contractors tendering for surfacing, civils, cold milling and asphalt repair work Report P4, P7
Highway users and residents affected by footway and carriageway schemes Report P7
Timeline
20th January 2026: Report dated and prepared for the Executive Board Report P37
12 March 2026: Executive Board considered and approved the procurement strategy Report P4
2 years initial term: Framework Agreement to run for 2 years from establishment Report P4
Up to 2 further periods of 12 months: Extension options, giving a maximum total term of 4 years Report P4
Plain English for the jargon
Framework Agreement: An arrangement with pre-qualified suppliers from which individual contracts, known as call-offs, can be awarded without a full new tender each time.
Call-off contract: A specific contract awarded under a framework agreement, either by further competition among framework suppliers or by direct award where rules allow.
Cold Milling Works: The process of removing the top layer of a road surface using specialist machinery before resurfacing.
Social value: Wider benefits beyond price, such as local employment, training, environmental gains and community outcomes, considered as part of the evaluation.
Procurement Act 2023: The UK law governing how public bodies run competitive procurement processes, replacing earlier regulations.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item184.1
Resolved
RESOLVED (1) That the procurement strategy to establish a new Surfacing and Civils Framework Agreement for a period of 2 years, with options to extend for a further 2 x 12 months (maximum total term of 4 years) and with an estimated total value of £50 million, be approved. (2) That the framework structure of four lots be approved: o Lot 1 – Surfacing Works o Lot 2 – Civils Works o Lot 3 – Cold Milling Works o Lot 4 – Repairs to Asphalt Surfaces (3) That the evaluation methodology for framework appointment, based on price, quality and social value (weightings to be confirmed in the Invitation to Tender), be approved. (4) That it be approved that subject to meeting the Council’s minimum quality and compliance requirements, up to three highest scoring contractors per lot be appointed to the framework. (5) That it be approved that the call-off contracts under the framework be awarded by following further competition or direct award (where permitted by the framework rules and procurement legislation). (6) That it be approved that all further competitions under this framework be conducted without the requirement for additional Procurement Strategy approvals. (7) That it be noted that any contract awards resulting from further competitions or direct award under this framework would be subject to reporting and approvals in accordance with the Constitution.
Word for word from the decision Blackburn with Darwen published for this meeting.Source: democracy.blackburn.gov.uk
The Council is required to establish a new long-term Framework Agreement for Surfacing and Civils works to replace the current expiring arrangement supporting delivery of the Council’s statutory Highways function. The proposed framework will have an estimated value of approximately £50 million over four years (2 years with options to extend for 2 x 12 months). A compliant procurement exercise will be undertaken and advertised on the Central Digital Platform and The Chest e-tendering portal in accordance with the Procurement Act 2023 and the Council’s Contract and Procurement Procedure Rules. The framework will: • Provide a compliant and efficient procurement route for surfacing and associated civils works. • Deliver improved programme certainty and value for money. • Reduce procurement lead times. • Strengthen supplier performance management. • Support sustainability, net zero and social value objectives. • Ensure consistent quality standards across schemes. This report seeks approval of the procurement strategy through framework arrangements to enable efficient operation throughout its lifetime.
Recommendations
That the Executive Board:
EBD: V3/23 Page 1 of 7 Classified as Official\Anyone
1. Approve the procurement strategy to establish a new Surfacing and Civils Framework Agreement for a period of 2 years with options to extend for a further 2 x 12 months (maximum total term of 4 years), with an estimated total value of £50 million. 2. Approve the framework structure of four lots: o Lot 1 – Surfacing Works o Lot 2 – Civils Works o Lot 3 – Cold Milling Works o Lot 4 – Repairs to Asphalt Surfaces 3. Approve the evaluation methodology for framework appointment, based on price, quality and social value (weightings to be confirmed in the Invitation to Tender). 4. Approve that up to three highest scoring contractors per lot be appointed to the framework, subject to meeting the Council’s minimum quality and compliance requirements. 5. Approve that call-off contracts under the framework be awarded by following further competition or direct award (where permitted by the framework rules and procurement legislation). 6. Approve that all further competitions under this framework be conducted without the requirement for additional Procurement Strategy approvals. 7. Note that any contract awards resulting from further competitions or direct award under this framework shall be subject to reporting and approvals in accordance with the Constitution.
Background
The Council delivers its statutory Highways Authority functions through planned capital and maintenance programmes funded through the Highways Maintenance Block and Local Transport Grant. The current Surfacing and Civils framework is due to expire and must be replaced to ensure continuity of delivery and compliance with procurement legislation. The proposed framework will appoint a panel of pre-qualified contractors capable of delivering surfacing and civil engineering works to defined standards of: • Quality • Health and safety • Environmental management • Sustainability • Programme performance • Social value Scope of Works
EBD: V3/23 Page 2 of 7 Classified as Official\Anyone
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the Previous MeetingRESOLVED That the minutes of the last meeting held on Thursday, 13 August 2026 be agreed as a correct record for sign...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.