Executive Board, Thursday 12 March 2026 at 6.00pm

Blackburn Skills Campus - Project Update

Noted Executive 3 papers

AI summaryBlackburn Executive Board approves £10.3m borrowing and freehold sale of Building 1 to Star Academies, anchoring £45.3m first phase of renamed Star Square skills campus on former town centre car parks.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedBuilding 1 to Star Academies on completion
Money£45.3m phase one costPlus £10.3m new Council borrowing approved
What happens nextProcure building contractor 2026Section 73 planning application later this year
Who it affectsTown centre car parksBrown Street reduced from 310 to 260 spaces

What was decided

Approved the freehold disposal of Building 1 to Star Academies on completion of construction for an agreed Purchase Price of £10,300,000 (£10,000,000 for the building and £300,000 for the land, excluding VAT). Report 4.14, 6.4, P14

Approved adding £10.3m to the capital programme, funded by Council borrowing, with short-term Minimum Revenue Provision and interest costs of £670,000 in 2028/29 and £493,000 in 2029/30, to be repaid by the Star capital receipt on completion. Report 6.3, P10

Approved naming the new civic square as 'Star Square' to be included in the primary postal address of future buildings across the wider four building campus. Report P15, 3.6

Why

Star Academies has replaced the University of Lancashire, which withdrew from the project due to well documented financial challenges in the university sector, and will occupy the building as its new headquarters alongside National Institute of Teaching space. Report P2, 3.9, 3.10, 3.11

The campus underpins the Council's adopted Local Plan, the Growth Programme and the Lancashire Combined County Authority Growth Axis ambitions for the Business Innovation District. Report P1, 3.2, 5.1

Independent valuation confirmed the £10,300,000 Purchase Price reflects market value, and external advice has verified Subsidy Control Act compliance for both the Government grant and the disposal. Report 6.4, 6.5, 6.7, 7.6

What happens next

Procure a main building contractor via the North West Construction Hub Framework under a Pre-Construction Services Agreement, with contractor appointment and final cost subject to a future Executive Board report. Report 4.6, 4.7, 4.8

Submit an updated planning application under Section 73 of the Town and Country Planning Act 1990 later in 2026 to reflect Star's latest requirements. Report 4.2

Construction mobilisation is expected in early 2027, with the building works complete by early 2029 and the building operational by summer 2029, under a development long stop date of 29th March 2029. Report 4.8, 4.9, 4.11

The money

  • £45.3m Total estimated development cost for phase one Report 6.1
  • £20m UK Government grant funding, formerly Levelling Up Report 3.1, 6.2
  • £2m Lancashire Combined County Authority grant funding Report 6.2
  • £13m Council borrowing within existing approved capital programme Report 6.2
  • £10.3m New supplementary Council borrowing to be repaid by Star Report 6.2, 6.3
  • £10,300,000 Star Purchase Price, £10,000,000 building plus £300,000 land, excluding VAT Report 4.14
  • £670,000 Minimum Revenue Provision and interest estimated for 2028/29 Report 6.3
  • £493,000 Minimum Revenue Provision and interest estimated for 2029/30 Report 6.3

Options considered

  • Chosen: Replace the University of Lancashire with Star Academies as partner and occupier for Building 1. Provides a new headquarters and training building to anchor phase one after the university withdrew Report P2, 3.9, 3.10
  • Chosen: Procure the main contractor via the North West Construction Hub Framework under a two-stage PCSA. Two-stage design and build approach secures contractor interest, competition and value for money Report 4.6, 4.7
  • Chosen: Build on Brown Street Car Park with reconfiguration from 310 to 260 spaces and 45 free permits for Star at Penny Street. Reprofiled staff and police permit relocations are expected to avoid significant loss of parking income Report 6.11, 6.12

Implications

  • Financial: £10.3m new Council borrowing adds Minimum Revenue Provision and interest of £670,000 in 2028/29 and £493,000 in 2029/30 until repaid by the Star capital receipt on completion. Report 6.3
  • Financial: Annual parking income loss of £30,000 from the reduction of Brown Street spaces and provision of free parking permits for Star at Penny Street Car Park.
  • Financial: Up to £50,000 per year, capped at £100,000 in total, non-recoverable business rate grant to Star for under-utilised floors for up to two years or until occupied. Report 6.9, 6.10
  • Financial: Star's annual service charge capped at £24,000 (excluding VAT), with the Council's share of £48,000 per annum public realm maintenance estimated at £24,000 per year. Report P71, 6.13
  • Legal: External advice has confirmed Subsidy Control Act compliance for both the £20m MHCLG grant and the disposal of Building 1 to Star, with the MHCLG subsidy published by the Government. Report 6.5, 6.7, 7.6
  • Legal: An updated planning application will be submitted under Section 73 of the Town and Country Planning Act 1990 to vary the original consent granted in September 2024. Report 4.2
  • Risk: The Council accepts the risk profile of the development agreement including future adverse or unexpected inflationary pressures and developer risk, partly off-set by a contingency included in the capital funding. Report 6.14, P18
  • Staffing: Existing Council staff from Growth Programme, Property, Planning, Procurement and Legal teams will be used to deliver the project, with Blake Morgan and DWF providing external legal advice. Report P97, 4.3, 4.4, 7.6

Who and where

  • Star Academies, including its National Institute of Teaching operations, as occupier and buyer of Building 1 Report 3.7, 3.8, 3.10, 3.11
  • Brown Street and Penny Street car park users, with Brown Street reduced from 310 to 260 spaces and 45 free permits issued to Star at Penny Street Report 6.11, 6.12, 4.16
  • The Mall, receiving 300 relocated staff parking passes, and 80 Police Permits relocated to Penny Street Report 6.11
  • Future charity partners and organisations on the reserved Second and Third floors of Building 1 Report 3.13
  • Town centre businesses, key stakeholders and ward councillors, to be consulted through the statutory planning process Report P103
  • Turner & Townsend, BDP, Blake Morgan, Bethell and United Utilities as appointed consultants and contractors Report 4.1, 4.3, 4.5

Timeline

  • March 2023: Government announces up to £20m funding award for the Business Innovation District Phase 1 Report 3.1
  • September 2024: Original planning application granted under reference 10/24/0595 Report 4.2
  • April 2026: Highway works complete and United Utilities sewer diversion works commence via Bethell Report 4.5, P12
  • End of 2026: United Utilities sewer diversion works complete Report 4.5
  • Later 2026: Updated planning application under Section 73 submitted Report 4.2
  • Early 2027: Mobilisation and commencement of building works expected Report 4.8
  • 31st March 2028: MHCLG Government funding must be spent by this date Report 6.6
  • 29th March 2029: Development long stop date for completion under the development agreement Report 4.11

Plain English for the jargon

  • LCCA: Lancashire Combined County Authority, regional growth body
  • NIoT: National Institute of Teaching, government-designated teacher training body launched in 2022
  • PCSA: Pre-Construction Services Agreement, a contract for early design and cost work before main construction appointment
  • MHCLG: Ministry of Housing, Communities and Local Government, the funder of the £20m grant
  • Section 73: Section 73 of the Town and Country Planning Act 1990, used to vary conditions of an existing planning permission
  • EIA: Equality Impact Assessment, with the checklist completed and a full EIA not required
  • MRP: Minimum Revenue Provision, the Council's annual charge to repay borrowing from revenue
  • JCT and NEC: Standard building (Joint Contracts Tribunal) and civil engineering (New Engineering Contract) contract forms
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item183.10

Resolved

RESOLVED (1) That it be noted that the Blackburn Skills and Education Campus referred to the wider town centre development on Council owned land currently occupied by Brown Street and Penny Street Car Parks and centred on a new Civic Square, as illustrated on the masterplan and as attached as Annex A to the report, and when completed would comprise of 4 buildings. (2) That the agreement of commercial terms with Star to acquire and occupy Building 1 as indicated on the phase one masterplan as attached as Annex B to the report, with the intention for the project to be referred to now as Star Square (Phase 1: One Star Square and the public realm), with an ambition for the wider development of Star Square incorporating future Buildings 2, 3 and 4, be noted. (3) That it be noted that the estimated development costs for the first phase of the project were £45.3m which comprised of £32.3m for Building 1 and £13m for all external works and was being funded by £20m of Government funding, £2m of Lancashire Combined County Authority funding with the remaining £23.3m funded by the Council and Star. (4) That it be noted that the capital funding of £23.3m included £13m from within the existing capital programme funded through Council borrowings together with £10.3m of supplementary capital (borrowings) would be secured by a forward sale development agreement to Star and repaid to the Council in full on completion of the construction works. (5) That the addition of £10.3m to the capital programme, funded by Council borrowing, acknowledging the short-term additional revenue cost of £670,000 in 2028/29 and £493,000 in 2029/30, in respect of Minimum Revenue Provision and interest payable, until this was repaid by way of a capital receipt on completion of the construction works, be approved. (6) That the annual estimated loss of parking income from the reduction of spaces in Brown Street Car Park and provision of free parking permits for STAR in Penny Street Car Park of £30,000 be noted. (7) That the completion of the highway works in April 2026, with the final phase of enabling works due to commence thereafter by United Utilities and completed by the end of 2026, be noted. (8) That it be noted that an updated planning application would be submitted under Section 73 of the Town and Country Planning Act 1990 to reflect the latest requirements of Star and would be submitted later in the year. (9) That the freehold disposal of Building 1, following completion of the construction works for the agreed Purchase Price in accordance with the terms as set out in this report, be approved. (10) That the naming of the new civic square as ‘Star Square’ as illustrated on the masterplan, as attached at Annex A to the report, which would be included in the primary postal address of future buildings, be approved. (11) That the business rate position of Star as a charitable organisation with approval for the Council to ...
Word for word from the decision Blackburn with Darwen published for this meeting. Source: democracy.blackburn.gov.uk

Follow this further

Built from Blackburn with Darwen's papers

What the report saysPro

Report to Executive Board

Executive summary

The Blackburn Skills and Education Campus is central to the delivery of the Business Innovation District, the largest development opportunity of its kind in the Lancashire region and a key strategic initiative of our adopted Local Plan and the Growth Plan for the Lancashire Combined County Authority (‘LCCA’)

Following the University of Lancashire withdrawal from the project, due to well documented financial challenges in the university sector, the Council has worked tirelessly to secure a new partner for our flagship development scheme and is delighted to confirm Star Academies’ intention to acquire and occupy Building 1 on completion of the construction works.

This report provides an update on the project over the past year and confirms the Council has reached agreement with Star Academies (‘Star’) for the occupation of Building 1, thereby anchoring the first phase of the Skills and Education Campus and seeks approval to commence drafting of the legal agreements between the Council and Star Academies to finance and implement the scheme.

2. RECOMMENDATIONS That the Executive Board:

1. Notes the Blackburn Skills and Education Campus refers to the wider town centre development on Council owned land currently occupied by Brown Street and Penny Street Car Parks and centred on a new Civic Square, as illustrated on the masterplan, attached at Annex A, and when completed will comprise 4 buildings.

2. Notes the agreement of commercial terms with Star to acquire and occupy Building 1 as indicated on the phase one masterplan attached at Annex B, with the intention for the project to be referred to now as Star Square (Phase 1: One Star Square and the public realm), with an ambition for the wider development of Star Square incorporating future Buildings 2,3 and 4.

EBD: V3/23 Page 1 of 10 Classified as Official\Anyone

3. Notes the estimated development costs for the first phase of the project are £45.3m which comprises £32.3m for Building 1 and £13m for all external works and is being funded by £20m of Government funding, £2m of LCCA funding with the remaining £23.3m funded by the Council and Star;

4. Notes the capital funding of £23.3m includes £13m from within the existing capital programme funded through Council borrowings together with £10.3m of supplementary capital (borrowings) which will be secured by a forward sale development agreement to Star and repaid to the Council in full on completion of the construction works;

5. Approves the addition of £10.3m to the capital programme, funded by Council borrowing, acknowledging the short term additional revenue cost of £670,000 in 2028/29 and £493,000 in 2029/30, in respect of Minimum Revenue Provision and interest payable, until this is repaid by way of a capital receipt on completion of the construction works;

6. Notes the annual estimated loss of parking income from the reduction of spaces in Brown Street Car Park and provision of free parking permits for STAR in Penny Street Car Park of £30,000

7. Notes the completion of the highway works in April 2026 with the final phase of enabling works due to commence thereafter by United Utilities and completed by the end of 2026;

8. Notes an updated planning application will be submitted under Section 73 of the Town and Country Planning Act 1990 to reflect the latest requirements of Star and will be submitted later in the year;

9. Approves the freehold disposal of Building 1 following completion of the construction works for the agreed Purchase Price in accordance with the terms as set out in this report;

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Blackburn Skills and Education Campus Site PlanAppendix A 2.5 MB Download
PDF
Phase 1 Site Plan with Star Building Red Line BoundaryAppendix B 570 KB Download
PDF
Blackburn Skills Campus: Project UpdateReport 191 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 19 attended
MD
Councillor Mustafa DesaiCommittee Member, present
JF
Councillor Jackie FloydCommittee Member, present
JL
Councillor Julie Louise GunnOfficer, present
SH
Councillor Shaukat HussainCommittee Member, present
MK
Martin KellyOfficer, expected
AL
Asad LaherOfficer, present
DL
Dean LangtonOfficer, expected
QM
Councillor Quesir MahmoodCommittee Member, present
NM
Nafisha MasterSecretary, expected
VE
Councillor Vicky Ellen McGurkCommittee Member, apologies
ZM
Zahra MusaSecretary, present
DP
Denise ParkOfficer, present

All 19 on the meeting page

On this subject at Blackburn with Darwen

Search all
  1. Blackburn Skills Campus - Project UpdateThis decision
  2. Blackburn Town Centre - Skills and Education Campus (Phase 1)Noted

More from Blackburn with Darwen Executive Board

All decisions
MeetingDecisionOutcome
10 Sep 2026 Minutes of the Previous MeetingRESOLVED That the minutes of the last meeting held on Thursday, 13 August 2026 be agreed as a correct record for sign... Agreed Open
10 Sep 2026 Corporate Plan Performance, Quarter 1 2026/271) That the Quarter 1 performance against the delivery of the Council’s Corporate Plan Missions, as attached as Appen... Noted Open
10 Sep 2026 Children and Young People's Plan 2026 - 20281) That the Children and Young People’s Plan 2026-2028, which had been formally signed off by the Children’s Partners... Noted Open
10 Sep 2026 Variation to existing schools capital programme - Newfield Satellite Site1) That the requirement for a significant increase in the capital budget for the proposed Newfield School satellite s... Noted Open
10 Sep 2026 Enhancement of the Free Bulky Waste Collection Service1) That that introduction of a newly developed online access system to facilitate a full end to end self-serve option... Approved Open