CONFIRMATION OF BLACKPOOL COUNCIL SUPPORT FOR DELIVERY PHASE OF MUSEUM PROJECT

Agreed Executive 2 papers

Executive agreed this item on Monday 20 July 2015. Below is the council's own wording, with the papers it was decided on.

Item2

Resolved

The Executive agreed the recommendation as outlined above namely: That £2,000,000 is formally approved as Blackpool Council's contribution to the delivery phase of the Museum for Blackpool project and the project update and next steps are noted.
Word for word from the decision Blackpool published for this meeting. Source: democracy.blackpool.gov.uk

Follow this further

Built from Blackpool's papers

What the report saysPro

Report to Executive

Report to: EXECUTIVE Relevant Officer: Belinda Betts, Blackpool Museum Project Director Relevant Cabinet Member Councillor Simon Blackburn, Leader of the Council Date of Meeting: 20th July 2015

CONFIRMATION OF BLACKPOOL COUNCIL SUPPORT FOR DELIVERY PHASE OF MUSEUM PROJECT 1.0 Purpose of the report:

1.1To consider the approval of Blackpool Council's financial contribution to the delivery phase of the Museum for Blackpool Project

2.0Recommendation(s):

2.1That £2,000,000 is formally approved as Blackpool Council's contribution to the delivery phase of the Museum for Blackpool project and the project update and next steps are noted.

3.0Reasons for recommendation(s):

3.1The Heritage Lottery Fund (HLF) committed in principal a total of £13.7million to this project on the basis of matched funding from the project sponsor organisation. Part of the assessment criteria for the Heritage Lottery Fund is value for money and the financial contribution of the applicant. Advice was sought from Heritage Lottery Fund during the preparation of the Round 1 application to ascertain the level of contribution which would be expected for a project of this scale. If this contribution were to be reduced it could have a detrimental effect on the Round 2 decision. The formal approval of this contribution is now required in advance of the Round 2 Heritage Lottery Fund application being made.

In addition work is now progressing on other funding bids as the Project Board works closely with fundraising consultants and look to target a number of trusts and foundations. For all of these funding sources the confirmation of the Council’s financial contribution will add weight to the bids and increase their chances of success. Consequently it makes sense to formally approve the Council’s contribution now.

3.2a Is the recommendation contrary to a plan or strategy adopted or No approved by the Council? 3.2b Is the recommendation in accordance with the Council’s approved Yes budget?

3.3Other alternative options to be considered:

There are no alternative options. Without this level of commitment from Blackpool Council the Round 2 application to the Heritage Lottery Fund is very unlikely to succeed.

4.0Council Priority:

4.1The relevant Council Priority is:

“Expand and promote our tourism, arts, heritage and cultural offer “

5.0Background Information

5.1The purpose of this decision paper is for the Executive to formally approve Blackpool Council’s financial contribution of £2 million towards the delivery phase of the Museum for Blackpool project.

5.2During the preparation of the Round 1 Heritage Lottery Fund a match fundraising plan was prepared. This was written on the basis of a realistic assessment of potential funding sources and with support and guidance from the Heritage Lottery Fund (HLF).

5.3Part of the assessment criteria which Heritage Lottery Fund makes on all applications relates to value for money and the financial contribution of the applicant. As a result a cash contribution of £2 million by Blackpool Council to the Delivery Phase of the Museum for Blackpool project was included in the Round 1 submission. This was discussed and agreed by the Project Board. An earmarked reserve of £2m was established on the 23rd October 2014 following a comprehensive review of all the Council’s earmarked reserves that enabled the Council to ringfence and protect its funding contribution to this project. This decision was made in the knowledge of the current financial constraints being felt by local authorities, whilst also demonstrating a major commitment to the museum project by Blackpool Council. The formal approval of this contribution is now required in advance of the Round 2 Heritage Lottery Fund application being made.

5.4Does the information submitted include any exempt information? No 5.5 List of Appendices:

None

6.0Legal considerations:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CONFIRMATION OF BLACKPOOL COUNCIL SUPPORT FOR DELIVERY PHASE OF MUSEUM PROJECTReport 66 KB DownloadRead as text
PDF
EX30 Council Museum ContributionReport 70 KB Download

At this meeting

Whole meeting

Who was there

8 of 10 attended
LB
Lennox BeattieSecretary, expected
SB
Councillor Simon BlackburnCommittee Member, present
GC
Councillor Graham CainCommittee Member, present
GC
Councillor Gillian CampbellCommittee Member, absent
FJ
Councillor Fred JacksonCommittee Member, present
JJ
Councillor John JonesCommittee Member, present
MK
Councillor Maria KirklandCommittee Member, present
MS
Councillor Mark SmithCommittee Member, present
IT
Councillor Ivan TaylorCommittee Member, present
MC
Councillor Mrs Christine WrightCommittee Member, present

More from Blackpool Executive

All decisions
MeetingDecisionOutcome
12 Oct 2026 Adoption of the lancashire waste strategy 2026-2036The Executive agreed the recommendations as outlined above namely: 1. To approve the adoption of the final post-consu... Agreed Open
12 Oct 2026 Rent setting policyThe Executive agreed the recommendation as outlined above namely: To approve the Rent Setting Policy , attached at Ap... Agreed Open
12 Oct 2026 Adoption of the blackpool heritage investment strategy 2026-2031The Executive agreed the recommendations as outlined above namely: 1. To note the consultation findings and amendment... Agreed Open
12 Oct 2026 Establishment of a special educational needs and disabilities (send) specialist base at st mary's catholic academyThe Executive agreed the recommendations as outlined above namely: 1. To approve the establishment of a 20-place SEND... Agreed Open
12 Oct 2026 Blackpool childrens social care sufficiency strategy 2026-28The Executive agreed the recommendation outlined above namely: To approve the Blackpool Children’s Social Care Suffic... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies