Resolved
The Executive agreed the recommendation as outlined above namely: That the essential steel works to Blackpool Tower as outlined are financed via Prudential Borrowing.
Executive agreed this item on Monday 20 July 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
The Executive agreed the recommendation as outlined above namely: That the essential steel works to Blackpool Tower as outlined are financed via Prudential Borrowing.
1.1To consider the option of £1,800,000 Prudential Borrowing in order to finance essential steel works to Blackpool Tower, as part of the current ongoing project.
2.0Recommendation(s):
2.1That the essential steel works as outlined to Blackpool Tower are financed via Prudential Borrowing.
3.0Reasons for recommendation(s):
3.1To allow the arrangement of funding to be used in financing essential steel work repairs to Blackpool Tower.
To ensure the condition of the Tower steel work remains structurally sound.
In order to avoid the costs of immediate abortive works, and limit further remedial attention in the future.
To support the regeneration and economy of the Town.
3.2a Is the recommendation contrary to a plan or strategy adopted or No approved by the Council?
3.2b Is the recommendation in accordance with the Council’s approved Yes budget?
3.3Other alternative options to be considered:
An alternative option would be to abort the current Tower steel works, restarting at a later date. This option is considered inferior to that being recommended as: • A significant proportion of the Prudential Borrowing requirements would still exist
• Abortive costs associated with dismantling the existing scaffold and vacating the site would be incurred
• Completion of the remaining essential steel work and the associated expense would still be required in the future
In addition, this option would result in further delays in completing this project, as well as increased overall costs and further operational disruption.
4.0Council Priority:
4.1The relevant Council Priorities are:
“Expand and promote our tourism, arts, heritage and cultural offer“ and “Attract sustainable investment and create quality jobs”
5.0Background Information
5.1Blackpool Council took ownership of the Tower in March 2010. An ongoing steel renovation and replacement programme has continued to take place since that time, in order to ensure the steel is structurally sound and safeguarded for the future.
5.2During these works, substantial amounts of severely corroded Steel, requiring urgent replacement, has been identified. Despite detection of damaged sections of the structure, the full scale of the problem could not be ascertained until work to rectify the issue was largely completed.
5.3A significant proportion of the issue has now been dealt with and this, together with the impact of inflation on the contract plus additional preliminary and ancillary costs has contributed to the requirement for additional financing.
5.4Does the information submitted include any exempt information? No 5.5 List of Appendices:
None
6.0Legal considerations:
6.1None. 7.0 Human Resources considerations:
7.1None
8.0Equalities considerations:
8.1None
9.0Financial considerations:
9.1Blackpool Council would be required to prudentially borrow £1,800,000 in order to finance the works to completion of the project.
9.2The resultant debt financing costs will add to the Leisure Assets cumulative deficit, currently standing at £3,308,000 and be managed through the balance sheet. This would now mean that the Leisure Assets Medium Term Financial Plan shows that an in-year surplus is forecast in the 2017/2018 financial year.
10.0Risk management considerations:
10.1Completion of the works as recommended in this report will:
• Significantly guard against the risk of further major steel work requirements in the short to medium term, and the associated operational disruption
• Help to mitigate against the risk of further degradation of the steel structure
10.2A number of robust financial and performance management controls and measures would be implemented and maintained in order to manage the remaining steel works. The Council has undertaken to ensure rigorous risk management remains in place in the delivery of this project.
11.0Ethical considerations:
11.1None
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
ESSENTIAL TOWER STEEL WORKSReport | 61 KB | DownloadRead as text |
PDF |
EX35 Tower Steel FinancingReport | 63 KB | Download |
Follow Executive at Blackpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 12 Oct 2026 | Adoption of the lancashire waste strategy 2026-2036The Executive agreed the recommendations as outlined above namely: 1. To approve the adoption of the final post-consu... | Agreed | Open |
| 12 Oct 2026 | Rent setting policyThe Executive agreed the recommendation as outlined above namely: To approve the Rent Setting Policy , attached at Ap... | Agreed | Open |
| 12 Oct 2026 | Adoption of the blackpool heritage investment strategy 2026-2031The Executive agreed the recommendations as outlined above namely: 1. To note the consultation findings and amendment... | Agreed | Open |
| 12 Oct 2026 | Establishment of a special educational needs and disabilities (send) specialist base at st mary's catholic academyThe Executive agreed the recommendations as outlined above namely: 1. To approve the establishment of a 20-place SEND... | Agreed | Open |
| 12 Oct 2026 | Blackpool childrens social care sufficiency strategy 2026-28The Executive agreed the recommendation outlined above namely: To approve the Blackpool Children’s Social Care Suffic... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.