ACQUISITION OF LAND FOR CENTRAL STATION SITE DEVELOPMENT

Agreed Executive 2 papers

Executive agreed this item on Monday 20 July 2015. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

The Executive agreed the recommendations as outlined above namely: 1. To approve the acquisition of Bonny Street Police station for £3,200,000. 2. To authorise the temporary Prudential Borrowing to fund this purchase. 3. To approve the granting of an appropriate tenancy of Bonny Street Police Station to Lancashire Constabulary. 4. To approve the granting of an appropriate legal agreement for the shared accommodation at Municipal Buildings. 5. To ring-fence the income from the two legal agreements outlined in 2.3 and 2.4 towards the associated of acquisition and the temporary Prudential Borrowing associated with this acquisition.
Word for word from the decision Blackpool published for this meeting. Source: democracy.blackpool.gov.uk

Follow this further

Built from Blackpool's papers

What the report saysPro

Report to Executive

Report to: EXECUTIVE Relevant Officer: Alan Cavill, Director of Place Relevant Cabinet Member Councillor Simon Blackburn, Leader of the Council

Date of Meeting: 20th July 2015

ACQUISITION OF LAND FOR CENTRAL STATION SITE DEVELOPMENT SITE 1.0 Purpose of the report:

1.1Further to decision EX 19/2015, to seek approval for the acquisition of Bonny Street Police station and lease back for the Police to occupy the Station until they move and for the granting of a legal agreement for the Police to use Municipal Buildings for their Town Centre team.

2.0Recommendation(s):

2.1To approve the acquisition of Bonny Street Police station for £3,200,000.

2.2To authorise the temporary Prudential Borrowing to fund this purchase.

2.3To approve the granting of an appropriate tenancy of Bonny Street Police Station to Lancashire Constabulary.

2.4To approve the granting of an appropriate legal agreement for the shared accommodation at Municipal Buildings.

2.5To ring-fence the income from the two legal agreements outlined in 2.3 and 2.4 towards the associated of acquisition and the temporary Prudential Borrowing associated with this acquisition.

3.0Reasons for recommendation(s):

3.1The site is contained within the former Central Leisure Quarter and is considered to be a key site for inclusion within any future large scale development. The early acquisition will help with the site assembly whilst the ability to lease back the accommodation which new facilities are constructed is consistent with joint working. 3.2a Is the recommendation contrary to a plan or strategy adopted or No approved by the Council?

3.2b Is the recommendation in accordance with the Council’s approved Yes budget?

3.3Other alternative options to be considered:

To not acquire the Police Station at Bonny Street. Whilst this initially a cheaper option the main reason for the lack of development at Central Station site to date is the incompleteness of the site and the fact that the courts and Police Station are both incompatible both visually with a modern leisure development .

In the interests of making a development on Central Station site possible and viable the preferred option is to acquire the Police Station and make it part of the development site that will come forward at a future date.

Moving the Town Centre policing team to the new site or a location other than Municipal Buildings were also considered as options. From a Community Safety point of view the Council could not support there being no direct Police presence in the Town Centre and the location of key services together in Municipal Buildings is an opportunity that it is recommended that the Council and partners pursue.

4.0Council Priority:

4.1The relevant Council Priorities are:

• Create safer communities and reduce crime and anti-social behaviour • Attracting sustainable investment and creating quality jobs

5.0Background Information

5.1The Executive at its meeting on the 9th March 2015 resolved to start negotiations on the possible purchase of Bonny Street Police Station from Lancashire Constabulary and to receive a further report on the terms for that acquisition and their funding (Executive Decision EX19/2015 refers).

5.2The Council has been negotiating with the Police regarding their move away from Central Station site for almost 10 years to facilitate the development of the area and make any proposal more viable. The acquisition of the police station is seen as a key element to opening up development and whilst the Council could contemplate making a CPO to acquire the remaining properties , it would best if these could be acquiring by negotiation , especially when dealing with another public agency. 5.3 The Central Station Site was identified as a key priority in the Lancashire Growth Deal and as such the Council has received funding and Government support to help to develop the site.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
ACQUISITION OF LAND FOR CENTRAL STATION SITE DEVELOPMENTReport 68 KB DownloadRead as text
PDF
EX34 Bonny St acquisition exec itemReport 72 KB Download

At this meeting

Whole meeting

Who was there

8 of 10 attended
LB
Lennox BeattieSecretary, expected
SB
Councillor Simon BlackburnCommittee Member, present
GC
Councillor Graham CainCommittee Member, present
GC
Councillor Gillian CampbellCommittee Member, absent
FJ
Councillor Fred JacksonCommittee Member, present
JJ
Councillor John JonesCommittee Member, present
MK
Councillor Maria KirklandCommittee Member, present
MS
Councillor Mark SmithCommittee Member, present
IT
Councillor Ivan TaylorCommittee Member, present
MC
Councillor Mrs Christine WrightCommittee Member, present

On this subject at Blackpool

Search all
  1. ACQUISITION OF LAND FOR CENTRAL STATION SITE DEVELOPMENTThis decision
  2. Central Housing Regeneration – Project update and acquisition of landAgreed
  3. The acquisition of land for the multiversityAgreed

More from Blackpool Executive

All decisions
MeetingDecisionOutcome
12 Oct 2026 Adoption of the lancashire waste strategy 2026-2036The Executive agreed the recommendations as outlined above namely: 1. To approve the adoption of the final post-consu... Agreed Open
12 Oct 2026 Rent setting policyThe Executive agreed the recommendation as outlined above namely: To approve the Rent Setting Policy , attached at Ap... Agreed Open
12 Oct 2026 Adoption of the blackpool heritage investment strategy 2026-2031The Executive agreed the recommendations as outlined above namely: 1. To note the consultation findings and amendment... Agreed Open
12 Oct 2026 Establishment of a special educational needs and disabilities (send) specialist base at st mary's catholic academyThe Executive agreed the recommendations as outlined above namely: 1. To approve the establishment of a 20-place SEND... Agreed Open
12 Oct 2026 Blackpool childrens social care sufficiency strategy 2026-28The Executive agreed the recommendation outlined above namely: To approve the Blackpool Children’s Social Care Suffic... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies