CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Blackpool Borough Council
Blackpool, Fylde and Wyre Economic Prosperity Board, Tuesday 5 February 2019 at 2.00pm

LANCASHIRE ESIF PROGRAMME 2014-2020 FORWARD PLANNING UPDATE

Noted Committee 1 paper

Blackpool, Fylde and Wyre Economic Prosperity Board noted this item on Tuesday 5 February 2019. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

Decision The Board noted the report.
Word for word from the decision Blackpool published for this meeting. Source: democracy.blackpool.gov.uk

Follow this further

Built from Blackpool's papers

What the report saysPro

Report to Blackpool, Fylde and Wyre Economic Prosperity Board

Report to: Blackpool, Fylde and Wyre Economic Prosperity Board

Report Lead : Nick Gerrard, Growth and Prosperity Programme Director, Blackpool Council (Author : Sean McGrath, Lancashire County Council)

Date of Meeting: 05/02/19

Lancashire ESIF Programme 2014-20 1.1 Purpose

To set out a possible approach for the commitment of unallocated ESIF funds.

A detailed paper will be presented to the Lancashire ESIF Committee in January 2019 with a view to agreeing a plan for allocating remaining ESIF funds by the end of 2019.

1.2Current Position

The Lancashire ESIF Programme recently received an additional £32 million of ERDF and ESF funds due to a revaluation of the exchange rate. The gives a total ESIF allocation of £245.63 million.

As at the end of November 2018 the Lancashire ESIF Programme had committed 44% of the total funding allocation to approved projects. This breaks down between the funds as ERDF 38% of funds committed, ESF 55% and EAFRD 24%.

There is a current pipeline of projects that are at various stages of development, commissioning or appraisal totalling in excess of £76 million across all three funds, which will substantially increase commitment levels should this pipeline come to fruition.

Commitment of ERDF Funds

The current position of ERDF is as follows:

ERDF Summary 1 2 3 4 5 6 ERDF BY PRIORITY AXIS (£m) Low Climate Innov ICT SME Enviro Total Carbon Change TOTAL FUNDING ALLOCATION 29.08 1.42 79.13 22.30 11.69 2.89 146.50 94% of FUNDING ALLOCATION 27.33 1.33 74.38 20.96 10.99 2.72 137.71 TOTAL APPROVED PROJECTS 19.61 0.00 26.13 8.94 0.64 1.16 55.66 TOTAL ALLOCATED TO 20.85 0.00 55.21 10.68 10.26 2.23 99.23 APPROVED & PIPELINE 100% UNALLOCATED FUNDING 8.23 1.42 23.92 11.61 1.43 0.66 47.27 AVAILABLE FUNDING (94% of 6.49 1.33 19.17 10.28 0.73 0.49 38.48 allocation)

1 *As at 30th November 2018

Outline Applications

These figures are subject to change depending on the outcome of the recent calls for proposals which closed on 23rd November 2018. Details of the applications received for this call period are as follows:

October 2018 Call PA1 PA2 PA3 PA4 Number of applications received 3 0 4 3 Value of applications received (£m} 5.52 0 7.23 1.14

These applications will be subject to an initial gateway assessment and then a formal Stage 1 appraisal. It is likely that the outcome of these initial appraisals will be known by late January 2019. Those projects that pass the Stage 1 appraisal will be invited to submit a full application. On this basis the full outcome of this call period will not be known until Spring 19. Should all these projects be successfully funded the overall ERDF funding position would be as follows:

ERDF Summary including Outline Applications (October 2018 Call) ERDF SUMMARY (£m) PA1 PA2 PA3 PA4 PA5 PA6 TOTAL 100% UNALLOCATED FUNDING 2.71 1.42 16.69 10.47 1.43 0.66 33.39 AVAILABLE FUNDING (94% of allocation) 0.97 1.33 11.94 9.14 0.73 0.49 24.60 % ALLOCATED TO APPROVED & PIPELINE PROJECTS (Percentage of total 91% 0% 79% 53% 88% 77% 77% allocation)

1.3Future ERDF Calls

The next ERDF call period is provisionally scheduled for March 2019. As it stands this will be the last local call to be issued as a national Reserve Fund is to be established with future ERDF funds being allocated in response to national calls for proposals. How this Reserve Fund will operate is still being finalised.

As this will be the last local call it is imperative to allocate as much funding as possible to projects for this call period. Furthermore, it will be crucial for the future delivery of the programme to develop a pipeline of potential schemes to demonstrate demand for the proposed Reserve Fund as well as other funds that may become available through the achievement of Performance Reserve targets and underspends from other LEP areas.

1.4Key Upcoming Dates

Date of Meeting Role of meeting in relation to ESIF calls meeting

2 Engagement with partners on the development of LEDOG 17/12/18 potential ESIF projects

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
LANCASHIRE ESIF PROGRAMME 2014-2020 FORWARD PLANNING UPDATEForward_plan 118 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

2 of 9 attended
SB
Councillor Simon BlackburnCommittee Member, present
YB
Yvonne BurnettSecretary, expected
AC
Alan CavillOfficer, expected
NG
Nick GerrardOfficer, in attendance
LH
Lorraine HurstSecretary, expected
NJ
Neil JackOfficer, present
AL
Antony LockleyOfficer, expected
MS
Councillor Mark SmithCommittee Member, expected
MT
Mr Mark TowersSecretary, expected

More from Blackpool Blackpool, Fylde and Wyre Economic Prosperity Board

All decisions
MeetingDecisionOutcome
14 Mar 2024 Appointment of chairmanThat Councillor Mark Smith be appointed Chairman for the meeting. Decided Open
14 Mar 2024 Exclusion of public and pressThat the public and press be excluded from the meeting whilst the agenda items 7 and 8 are considered, on the ground ... Decided Open
14 Mar 2024 Minutes of the last meeting held on 7 december 2023That the minutes of the meeting held on 7 December 2023 be approved and signed by the Chair as a correct record. Approved Open
14 Mar 2024 Fylde coast green growth updateThat the update be noted. Noted Open
7 Dec 2023 Appointment of chairThat Councillor Mark Smith be appointed Chair of the Blackpool Fylde and Wyre Economic Prosperity Board for the meeting Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies