Report to: Blackpool, Fylde and Wyre Economic Prosperity Board
Report Author: Rob Green, Head of Enterprise Zones, Blackpool Council
Date of Meeting: 4th FEBRUARY 2019
1. Blackpool Airport Enterprise Zone: Progress Report
a) Masterplan
Formal feedback is still awaited from MHCLG on the submitted Masterplan, Implementation/ Delivery Plan and Marketing Strategies for the Enterprise Zone – in the absence of any comment work continues to progress the implementation of the plan following the phase one funding allocation made by Blackpool Council. A familiarisation site visit by MHCLG officials is still anticipated during the first quarter of 2019.
The masterplan is available to download from the LAMEC EZ website, together with a summary version of the written document to assist potential developers.
b) Development and investment partnerships
Thirteen responses where received to the initial PIN notice inviting interest from potential developers and investors, these are being evaluated and several respondents will be invited for further discussion prior to progressing a formal procurement exercise later in the year.
c) Current activity
Work is progressing to deliver phase one, of the Enterprise Zone, (shown in the 3 coloured areas on plan A below).Messrs Cassidy and Ashton have been commissioned to prepare an outline planning application for the main phase one site (shaded green on plan A). An informal consultation on the proposals held on the 6th December was attended by more than 70 local residents and businesses with generally a positive reaction. The work has been delayed slightly whilst awaiting confirmation of traffic survey data and the application is now expected to be submitted to Blackpool and Fylde councils in February and thereafter, as this is in part Greenbelt land, to the Secretary of State with a decision expected in June.
Consultants LK2 are also continuing their work in developing the design scope and business plan for the new Common Edge Sports Village. This is due for completion by mid-February.
In parallel, detailed design work is to be commissioned for both the Eastern Gateway access from Queensway/Common Edge and sports village including the provision of two 3G all weather sports pitches, grass football pitches and a HUB building to house changing facilities, social club accommodation for the various sports clubs and refreshment and local service retail. The potential inclusion of an indoor tennis facility and gym are being evaluated. The objective is to submit full planning applications for the road and Sports Village shortly after the outline consent is approved.
Work is also progressing at a pace to agree a bespoke 40,000 sq ft manufacturing facility within the phase one area, with a planning application targeted for April /May.
Planned activity over the next quarter also includes continuation of negotiations to either acquire or encourage the sites shaded blue on plan A to be brought forward for development , and the progression of initial design proposals for airport related infrastructure within the yellow shaded sections .Activity will also encompass the production of EZ wide drainage and utility strategies.
Plan A – PHASE ONE DEVELOPMENT ACTIVITY
d) Marketing
Work is ongoing to develop the content of the Blackpool Airport EZ pages of the LAMEC web site, with a news feed, downloadable facts sheets, rates relief and ECA information sheets, masterplan summary brochure and fly through imagery having been added prior to Christmas. Subject to approval from Lancashire County Council, additional features including social media feeds and links and an interactive property search facility will be added by Marketing Lancashire.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
BLACKPOOL AIRPORT EZ PROGRESS REPORT (STANDING ITEM)Report | 531 KB | DownloadRead as text |
Follow Blackpool, Fylde and Wyre Economic Prosperity Board at Blackpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Mar 2024 | Appointment of chairmanThat Councillor Mark Smith be appointed Chairman for the meeting. | Decided | Open |
| 14 Mar 2024 | Exclusion of public and pressThat the public and press be excluded from the meeting whilst the agenda items 7 and 8 are considered, on the ground ... | Decided | Open |
| 14 Mar 2024 | Minutes of the last meeting held on 7 december 2023That the minutes of the meeting held on 7 December 2023 be approved and signed by the Chair as a correct record. | Approved | Open |
| 14 Mar 2024 | Fylde coast green growth updateThat the update be noted. | Noted | Open |
| 7 Dec 2023 | Appointment of chairThat Councillor Mark Smith be appointed Chair of the Blackpool Fylde and Wyre Economic Prosperity Board for the meeting | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.