Resolved
Decision The Board noted the report.
Blackpool, Fylde and Wyre Economic Prosperity Board noted this item on Tuesday 5 February 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision The Board noted the report.
Report to: Blackpool, Fylde and Wyre Economic Prosperity Board
Report Author: Angela Kershaw, Senior Economic Development Officer, Wyre Council
Date of Meeting: 5 February 2019
Hillhouse Enterprise Zone: Progress Report
Masterplan and Baseline Report
The Hillhouse Technology Enterprise Zone Masterplan was adopted at Cabinet on November 28th 2018.
Marketing
The application for Advertising Consent was submitted January 4th. Site notices went up Friday 11th January (3 weeks). Pending any major issues installation should take place in February 2019.
A Marketing Strategy for Hillhouse Enterprise Zone will be prepared in house following the Implementation Plan. The Strategy will complement the overarching Lancashire Advanced Manufacturing Energy Cluster (LAMEC) branding and marketing approach adopted for the four Lancashire EZ’s.
Implementation / Delivery Plan
Work is progressing on the Implementation Plan.
We are currently awaiting comments from the main land owner NPL Group regarding phasing and some costings. A first draft will be considered by the council before being finalised. There are early issues that have been identified:
State Aid in terms of major land owners NPL Group – we are taking independent advice on this via our Head of Finance (Section 151 officer). To actively consider the recommendations made in the Masterplan regarding undertaking specific surveys and assessments of the whole site
We will continue to work with Genecon and NPL Group to develop the plan and envisage a first draft be completed by January / February 2019. Forthcoming Activity
i) Complete Delivery Plan by mid- February 2019 ii) A flood risk assessment to be commissioned for the entire site iii) A transport assessment be commissioned for the entire site iv) An Environmental and Ecology study to be commissioned for the entire site v) The planning application process for the gas fired power station, will be monitored and support offered as appropriate vi) Advice will be obtained on potential State Aid implications of public funding of enabling infrastructure – within this designated EU assisted area vii) Completing draft Marketing Strategy
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
HILLHOUSE TECHNOLOGY EZ PROGRESS REPORT (STANDING ITEM)Report | 163 KB | DownloadRead as text |
Follow Blackpool, Fylde and Wyre Economic Prosperity Board at Blackpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Mar 2024 | Appointment of chairmanThat Councillor Mark Smith be appointed Chairman for the meeting. | Decided | Open |
| 14 Mar 2024 | Exclusion of public and pressThat the public and press be excluded from the meeting whilst the agenda items 7 and 8 are considered, on the ground ... | Decided | Open |
| 14 Mar 2024 | Minutes of the last meeting held on 7 december 2023That the minutes of the meeting held on 7 December 2023 be approved and signed by the Chair as a correct record. | Approved | Open |
| 14 Mar 2024 | Fylde coast green growth updateThat the update be noted. | Noted | Open |
| 7 Dec 2023 | Appointment of chairThat Councillor Mark Smith be appointed Chair of the Blackpool Fylde and Wyre Economic Prosperity Board for the meeting | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.